Old Hattiesburg High, L.P. v. Harris Construction Services, LLC

Court of Appeals of Mississippi·Decided September 3, 2024·No. 2023-CA-00579-COA·Published

Opinion

IN THE COURT OF APPEALS OF THE STATE OF MISSISSIPPI NO. 2023-CA-00579-COA

OLD HATTIESBURG HIGH, L.P. APPELLANT v. HARRIS CONSTRUCTION SERVICES, LLC APPELLEE

DATE OF JUDGMENT: 05/01/2023 TRIAL JUDGE: HON. RHEA HUDSON SHELDON COURT FROM WHICH APPEALED: FORREST COUNTY CHANCERY COURT ATTORNEYS FOR APPELLANT: BRIAN AUSTIN HINTON ROBERT DAVIS HOUSE

CECELIA JENNIE HURT

ATTORNEYS FOR APPELLEE: RALPH B. GERMANY JR.

RANKIN SUMNER FORTENBERRY JAMES STEPHEN FRITZ JR.

NATURE OF THE CASE: CIVIL - OTHER DISPOSITION: APPEAL DISMISSED - 09/03/2024 MOTION FOR REHEARING FILED:

BEFORE CARLTON, P.J., McDONALD AND McCARTY, JJ.

McDONALD, J., FOR THE COURT:

¶1. Old Hattiesburg High L.P. (Old Hattiesburg) appeals from the Forrest County Chancery Court’s order denying its motion to reinstate an order Old Hattiesburg had obtained expunging a lien Harris Construction Services LLC (Harris Construction) had filed on Old Hattiesburg’s property.

¶2. More specifically, after a construction contract dispute, Harris Construction filed the lien on property Old Hattiesburg owned, claiming that Old Hattiesburg still owed for work Harris Construction had performed. Old Hattiesburg filed a petition to expunge the lien and requested an award of triple-the-lien value as damages. When Harris Construction failed to

appear at the hearing on Old Hattiesburg’s petition to expunge, the chancery court expunged the lien, but its order did not address the claim for damages Old Hattiesburg had requested. Harris Construction then moved to set aside the expungement order and the chancery court granted the motion and set aside the expungement. Thereafter, based on new evidence it discovered, Old Hattiesburg filed a motion to reinstate the expungement order. When the chancery court denied Old Hattiesburg’s motion, Old Hattiesburg appealed.

¶3. Having considered the record and arguments of counsel, we find that the chancery court’s initial order expunging Harris Construction’s lien was not a final appealable judgment. Therefore, the chancery court’s orders on the subsequent motions were orders revising an interim order and not final either. Accordingly, this Court lacks jurisdiction, and we dismiss the appeal.

Facts

A. The Parties

¶4. In 2018, Old Hattiesburg, a company owned by J. Steve Nail and his family, and Harris Construction, a company owned by David Harris, entered into two agreements to develop properties in Hattiesburg and Jackson, Mississippi. At the time, the two companies shared office space at 7538 Old Canton Road in Madison, Mississippi. Harris Construction used this Madison address for its filings with the Secretary of State, including its July 2019 designation of an agent for service of process, Rocket Lawyer Corporate Services LLC (Rocket Lawyer).1

1 Rocket Lawyer’s agent for service of process was yet another corporation, Paracorp Incorporated, whose registered agent was W. Eric West of McDavid, Noblin & West PLLC,

¶5. Old Hattiesburg owned the former high school building in Hattiesburg and contracted with Harris Construction to convert the property into apartments for senior citizens, which would be known as the Preservation Crossing Apartments. The Nail family also contracted with Harris Construction to refurbish Southpointe Apartments in Jackson, which the Nails owned through Kinkead of Jackson II LP. In addition, the parties entered into a joint venture agreement to share in the profits or losses of Harris Construction in performing construction work for both projects.2 This appeal concerns the contract for the Hattiesburg project.

B. The Contract and the Dispute

¶6. On December 4, 2018, Harris Construction and Old Hattiesburg signed the contract for the Preservation Crossing project. The contract required Harris Construction to submit notarized applications for payment when outstanding payments became due. As the project progressed, Old Hattiesburg authorized certain “change orders,” and the adjusted contract sum totaled $10,859,454.74.

¶7. At the end of 2020, Harris Construction contends, Old Hattiesburg needed to show that the Preservation Crossing project was completed by December 2020 or else lose the tax credits for which the projects were eligible. Old Hattiesburg proposed (and Harris Construction agreed) to submit its final application for payment to Old Hattiesburg on December 25, 2020, even though the project was not yet completed. Harris Construction’s

248 E. Capital Street, Jackson, Mississippi.

2 Parties to this joint venture were Old Hattiesburg, Harris Construction, Intervest Corporation, Harris-Intervest Construction JV LLC, and Kinkead. The parties agreed that the Nails’ companies would forego any performance bonding requirement in exchange for a share in Harris Construction’s profits or losses in the projects.

signed and notarized application included the original contract amount, the adjustments added to the original amount, and the amount of payments previously received. Harris Construction calculated that the final payment due was $594,172.24. On January 19, 2021, Harris Construction executed a “Contractor’s Lien Release and Subordination,” which stated that all payments were satisfied. Old Hattiesburg also received confirmation from the architect working with Harris Construction who stated that the total contract sum had been fully distributed to Harris Construction.

¶8. In subsequent litigation between the parties, Harris Construction contended that the work was not completed when it signed the December application and that it continued to work on the project through March 2021, for which it was owed $128,260. Harris Construction claimed that Old Hattiesburg agreed to pay for any other work needing to be done if Harris Construction would sign off on the project in December 2020.

¶9. Old Hattiesburg disagreed, however, and said that work on the project was completed in December 2020 and that Harris Construction was fully paid. Old Hattiesburg contended that any other amounts owed were “cost overruns” that Harris Construction should absorb.

¶10. When Harris Construction was not paid, its relationship with Old Hattiesburg deteriorated.3 Harris Construction vacated the Madison office, but Old Hattiesburg continued to do business from that location.4

3 Apparently there were also disputes about the amounts owed under the profitsharing provisions of the joint-venture agreement.

4 On March 2, 2021, Harris Construction filed an annual report with the secretary of state listing its principal address as “105 W. Washington Street, Suite A2, Ridgeland, MS 39157.” However, Harris Construction later admitted that it did not inform Rocket Lawyer

C. The Lien

¶11. On July 28, 2021, Harris Construction filed a construction lien on Old Hattiesburg’s property in the Forrest County Chancery Court, claiming that Old Hattiesburg had an unpaid balance of $128,260.47 for labor, services, and materials that was due on May 11, 2021.5 Harris Construction contended that it mailed a copy of the lien to Old Hattiesburg at its post office box number in Madison, Mississippi, by certified mail on July 29, 2021.

D. The Forrest County Chancery Court Lien Expungement Action and Order

¶12. On September 14, 2021, Old Hattiesburg filed a petition for expungement of the lien in Forrest County Chancery Court, alleging that Harris Construction failed to provide Old Hattiesburg with notice of the claim within two days of filing the claim of lien as required under the statute for a lien to be enforceable.6 The hearing was set for October 14, 2021.

¶13. On September 17, 2021, Old Hattiesburg served a Rule 81 summons7 and a copy of

of the change in address.

5 Apparently, similar facts led to Harris Construction filing a lien on the Jackson property as well, which, in turn, led to similar litigation in the Hinds County Chancery Court.

6 Mississippi Code Annotated section 85-7-405(1)(b) (Rev. 2021) provides in part:

Free access — add to your briefcase to read the full text and ask questions with AI

Old Hattiesburg High, L.P. v. Harris Construction Services, LLC, (Mich. Ct. App. 2024).

Old Hattiesburg High, L.P. v. Harris Construction Services, LLC (Old Hattiesburg High, L.P. v. Harris Construction Services, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Harris v. Waters
40 So. 3d 657 (Court of Appeals of Mississippi, 2010)
Stringfellow v. Stringfellow
451 So. 2d 219 (Mississippi Supreme Court, 1984)
William Christopher Tucker v. Gay St. Mary Williams
198 So. 3d 299 (Mississippi Supreme Court, 2016)
Brooke Nejam Hoffman v. Michael Joseph Hoffman
200 So. 3d 465 (Court of Appeals of Mississippi, 2016)
Michael Stevens v. Derrick Wade
214 So. 3d 301 (Court of Appeals of Mississippi, 2017)
Newson v. Newson
138 So. 3d 275 (Court of Appeals of Mississippi, 2014)
Meekins v. Kennon
141 So. 3d 51 (Court of Appeals of Mississippi, 2014)
In re J.W.
220 So. 3d 202 (Court of Appeals of Mississippi, 2017)
LaFontaine v. Holliday
110 So. 3d 785 (Mississippi Supreme Court, 2013)
M.W.F. v. D.D.F.
926 So. 2d 897 (Mississippi Supreme Court, 2006)