Old Hattiesburg High, L.P. v. Harris Construction Services, LLC

CourtCourt of Appeals of Mississippi
DecidedSeptember 3, 2024
Docket2023-CA-00579-COA
StatusPublished

This text of Old Hattiesburg High, L.P. v. Harris Construction Services, LLC (Old Hattiesburg High, L.P. v. Harris Construction Services, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of Mississippi primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Old Hattiesburg High, L.P. v. Harris Construction Services, LLC, (Mich. Ct. App. 2024).

Opinion

IN THE COURT OF APPEALS OF THE STATE OF MISSISSIPPI

NO. 2023-CA-00579-COA

OLD HATTIESBURG HIGH, L.P. APPELLANT

v.

HARRIS CONSTRUCTION SERVICES, LLC APPELLEE

DATE OF JUDGMENT: 05/01/2023 TRIAL JUDGE: HON. RHEA HUDSON SHELDON COURT FROM WHICH APPEALED: FORREST COUNTY CHANCERY COURT ATTORNEYS FOR APPELLANT: BRIAN AUSTIN HINTON ROBERT DAVIS HOUSE CECELIA JENNIE HURT ATTORNEYS FOR APPELLEE: RALPH B. GERMANY JR. RANKIN SUMNER FORTENBERRY JAMES STEPHEN FRITZ JR. NATURE OF THE CASE: CIVIL - OTHER DISPOSITION: APPEAL DISMISSED - 09/03/2024 MOTION FOR REHEARING FILED:

BEFORE CARLTON, P.J., McDONALD AND McCARTY, JJ.

McDONALD, J., FOR THE COURT:

¶1. Old Hattiesburg High L.P. (Old Hattiesburg) appeals from the Forrest County

Chancery Court’s order denying its motion to reinstate an order Old Hattiesburg had obtained

expunging a lien Harris Construction Services LLC (Harris Construction) had filed on Old

Hattiesburg’s property.

¶2. More specifically, after a construction contract dispute, Harris Construction filed the

lien on property Old Hattiesburg owned, claiming that Old Hattiesburg still owed for work

Harris Construction had performed. Old Hattiesburg filed a petition to expunge the lien and

requested an award of triple-the-lien value as damages. When Harris Construction failed to appear at the hearing on Old Hattiesburg’s petition to expunge, the chancery court expunged

the lien, but its order did not address the claim for damages Old Hattiesburg had requested.

Harris Construction then moved to set aside the expungement order and the chancery court

granted the motion and set aside the expungement. Thereafter, based on new evidence it

discovered, Old Hattiesburg filed a motion to reinstate the expungement order. When the

chancery court denied Old Hattiesburg’s motion, Old Hattiesburg appealed.

¶3. Having considered the record and arguments of counsel, we find that the chancery

court’s initial order expunging Harris Construction’s lien was not a final appealable

judgment. Therefore, the chancery court’s orders on the subsequent motions were orders

revising an interim order and not final either. Accordingly, this Court lacks jurisdiction, and

we dismiss the appeal.

Facts

A. The Parties

¶4. In 2018, Old Hattiesburg, a company owned by J. Steve Nail and his family, and

Harris Construction, a company owned by David Harris, entered into two agreements to

develop properties in Hattiesburg and Jackson, Mississippi. At the time, the two companies

shared office space at 7538 Old Canton Road in Madison, Mississippi. Harris Construction

used this Madison address for its filings with the Secretary of State, including its July 2019

designation of an agent for service of process, Rocket Lawyer Corporate Services LLC

(Rocket Lawyer).1

1 Rocket Lawyer’s agent for service of process was yet another corporation, Paracorp Incorporated, whose registered agent was W. Eric West of McDavid, Noblin & West PLLC,

2 ¶5. Old Hattiesburg owned the former high school building in Hattiesburg and contracted

with Harris Construction to convert the property into apartments for senior citizens, which

would be known as the Preservation Crossing Apartments. The Nail family also contracted

with Harris Construction to refurbish Southpointe Apartments in Jackson, which the Nails

owned through Kinkead of Jackson II LP. In addition, the parties entered into a joint venture

agreement to share in the profits or losses of Harris Construction in performing construction

work for both projects.2 This appeal concerns the contract for the Hattiesburg project.

B. The Contract and the Dispute

¶6. On December 4, 2018, Harris Construction and Old Hattiesburg signed the contract

for the Preservation Crossing project. The contract required Harris Construction to submit

notarized applications for payment when outstanding payments became due. As the project

progressed, Old Hattiesburg authorized certain “change orders,” and the adjusted contract

sum totaled $10,859,454.74.

¶7. At the end of 2020, Harris Construction contends, Old Hattiesburg needed to show

that the Preservation Crossing project was completed by December 2020 or else lose the tax

credits for which the projects were eligible. Old Hattiesburg proposed (and Harris

Construction agreed) to submit its final application for payment to Old Hattiesburg on

December 25, 2020, even though the project was not yet completed. Harris Construction’s

248 E. Capital Street, Jackson, Mississippi. 2 Parties to this joint venture were Old Hattiesburg, Harris Construction, Intervest Corporation, Harris-Intervest Construction JV LLC, and Kinkead. The parties agreed that the Nails’ companies would forego any performance bonding requirement in exchange for a share in Harris Construction’s profits or losses in the projects.

3 signed and notarized application included the original contract amount, the adjustments

added to the original amount, and the amount of payments previously received. Harris

Construction calculated that the final payment due was $594,172.24. On January 19, 2021,

Harris Construction executed a “Contractor’s Lien Release and Subordination,” which stated

that all payments were satisfied. Old Hattiesburg also received confirmation from the

architect working with Harris Construction who stated that the total contract sum had been

fully distributed to Harris Construction.

¶8. In subsequent litigation between the parties, Harris Construction contended that the

work was not completed when it signed the December application and that it continued to

work on the project through March 2021, for which it was owed $128,260. Harris

Construction claimed that Old Hattiesburg agreed to pay for any other work needing to be

done if Harris Construction would sign off on the project in December 2020.

¶9. Old Hattiesburg disagreed, however, and said that work on the project was completed

in December 2020 and that Harris Construction was fully paid. Old Hattiesburg contended

that any other amounts owed were “cost overruns” that Harris Construction should absorb.

¶10. When Harris Construction was not paid, its relationship with Old Hattiesburg

deteriorated.3 Harris Construction vacated the Madison office, but Old Hattiesburg continued

to do business from that location.4

3 Apparently there were also disputes about the amounts owed under the profit- sharing provisions of the joint-venture agreement. 4 On March 2, 2021, Harris Construction filed an annual report with the secretary of state listing its principal address as “105 W. Washington Street, Suite A2, Ridgeland, MS 39157.” However, Harris Construction later admitted that it did not inform Rocket Lawyer

4 C. The Lien

¶11. On July 28, 2021, Harris Construction filed a construction lien on Old Hattiesburg’s

property in the Forrest County Chancery Court, claiming that Old Hattiesburg had an unpaid

balance of $128,260.47 for labor, services, and materials that was due on May 11, 2021.5

Harris Construction contended that it mailed a copy of the lien to Old Hattiesburg at its post

office box number in Madison, Mississippi, by certified mail on July 29, 2021.

D. The Forrest County Chancery Court Lien Expungement Action and Order

¶12. On September 14, 2021, Old Hattiesburg filed a petition for expungement of the lien

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Harris v. Waters
40 So. 3d 657 (Court of Appeals of Mississippi, 2010)
Stringfellow v. Stringfellow
451 So. 2d 219 (Mississippi Supreme Court, 1984)
William Christopher Tucker v. Gay St. Mary Williams
198 So. 3d 299 (Mississippi Supreme Court, 2016)
Brooke Nejam Hoffman v. Michael Joseph Hoffman
200 So. 3d 465 (Court of Appeals of Mississippi, 2016)
Michael Stevens v. Derrick Wade
214 So. 3d 301 (Court of Appeals of Mississippi, 2017)
Newson v. Newson
138 So. 3d 275 (Court of Appeals of Mississippi, 2014)
Meekins v. Kennon
141 So. 3d 51 (Court of Appeals of Mississippi, 2014)
In re J.W.
220 So. 3d 202 (Court of Appeals of Mississippi, 2017)
LaFontaine v. Holliday
110 So. 3d 785 (Mississippi Supreme Court, 2013)
M.W.F. v. D.D.F.
926 So. 2d 897 (Mississippi Supreme Court, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
Old Hattiesburg High, L.P. v. Harris Construction Services, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/old-hattiesburg-high-lp-v-harris-construction-services-llc-missctapp-2024.