Oklahoma Natural Gas Co. v. Utility Contractors, Inc.

1998 OK CIV APP 132, 964 P.2d 977, 69 O.B.A.J. 3382, 1998 Okla. Civ. App. LEXIS 110, 1998 WL 685796
CourtCourt of Civil Appeals of Oklahoma
DecidedAugust 31, 1998
DocketNo. 88506
StatusPublished

This text of 1998 OK CIV APP 132 (Oklahoma Natural Gas Co. v. Utility Contractors, Inc.) is published on Counsel Stack Legal Research, covering Court of Civil Appeals of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Oklahoma Natural Gas Co. v. Utility Contractors, Inc., 1998 OK CIV APP 132, 964 P.2d 977, 69 O.B.A.J. 3382, 1998 Okla. Civ. App. LEXIS 110, 1998 WL 685796 (Okla. Ct. App. 1998).

Opinion

OPINION

ADAMS, Judge:

¶'1 Defendants/Appellants Utility Contractors, Inc. (Utility) and Middle Creek Mining Company, Inc. (Middle Creek) (collectively, Contractors), appeal the trial court judgment based upon separate jury verdicts in favor of Plaintiff/Appellee Oklahoma Natural Gas Company, a division of ONEOK Inc. (ONG) on its negligence and breach of contract/third party beneficiary theories of relief. We affirm.

FACTS

¶2 ONG sued Contractors for damages, alleging they negligently ruptured ONG’s high pressure gas line during construction of a sewer project in Tulsa, Oklahoma. Contractors denied the allegations, claiming instead that the damages were solely and proximately caused by ONG and its agents. After discovery, ONG asserted two additional theories of recovery or liability against Contractors: (1) negligence per se because of Contractors’ alleged failure to comply with the Oklahoma Underground Facilities Damages Prevention Act, 63 O.S.1991 § 142.1 et seq., (the Act), i.e., Contractors failed to notify the Oklahoma One-Call System, Inc. (Call-Okie)1 and to physically locate the gas [979]*979line before beginning excavations in the area; and (2) breach of the contract between the City of Tulsa (City) and Utility to which ONG claimed third party beneficiary status.

¶ 3 During the three day jury trial, the parties stipulated, in pertinent part, that: (1) Utility was awarded a contract with City to lay a 24 inch sewer line on the southside of Interstate 44 in Tulsa, Oklahoma, known as the Whitney Home Owners’ Sanitary Sewer Project, (2) that Middle Creek was working as an agent on behalf of Utility, and (3) that on March 3, 1993, an agent or employee of Contractors, while operating excavating machinery near 31st Street and South Memorial Drive in Tulsa, Oklahoma, struck a natural gas pipeline.

¶ 4 According to the undisputed evidence admitted at trial, ONG’s operating technician, Mr. Howard, marked the horizontal location of the gas line on the plans sent to ONG by the engineering firm hired by City, but not the vertical depth, because the depth would not be known unless the line was “physically dug out.” He also marked the same plans with a stamp “GAS LINES LOCATIONS APPROX.” Upon receiving those plans from ONG, the draftsman for City’s engineering firm noticed there was no vertical depth for the gas line so he assigned a “normal” depth of 4 feet to the gas line on the vertical profile on the set of engineering plans (final plans) ultimately used at a September 14, 1992 meeting called by City between Contractors, the engineers and all operators of underground facilities in the area of the project.

¶ 5 The first page of the final plans was stamped “Issued for Construction.” The second page had a box with the Call Okie “Do not dig” symbol next to the warning “Before you dig: Call Okie 1-800-522-6543,” and an explanation that a contractor must verify the location of the utilities prior to construction. The page with the gas line marked at the 4 foot level in the vertical profile included a box with the language “WARNING!! HIGH PRESSURE GAS CROSSING! CONTACT O.N.G. PRIOR TO BORE” from which two arrows pointed to the 16 inch high pressure gas line marked in the horizontal profile. ONG’s representative at the September 14, 1992 meeting, Mr. Lawson, did not know whether the 4 foot depth on the final plans was correct or not, and when asked about the gas line at the meeting, responded that it existed and that ONG should be notified before digging.

¶ 6 City’s civil engineer and project manager for the sewer project at issue, Mr. Spear, testified that the very reason the bore was being performed was to avoid cutting up Memorial and affecting traffic flow, that he believed ONG had given the exact location, and that he would have arranged to have the line physically located if he had known that they did not have at least a very close approximation of the line’s location.

¶ 7 Contractors called Call-Okie to request markings for all underground utilities along the sewer project on September 23, 1992, two days before beginning construction. ONG marked the gas line on September 30, 1992, and then again in late January, 1993. The construction in the area of 31st Street and Memorial Drive did not begin until February, 1993. It is undisputed that Contractors did not contact ONG prior to boring at that location and made no attempt to field locate the gas line prior to its rupture on March 3,1993.

¶ 8 After ONG rested, Contractors demurred to the evidence. The trial court declined to make a decision until hearing all the evidence. After Contractors rested, they renewed their demurrer and moved for a directed verdict, which the trial court overruled. The trial court submitted verdict forms to the jury allowing them to separately find whether Contractors were liable on negligence theories and whether they were Hable on a breach of contract theory. The returned verdicts found in favor of ONG on negligence, finding Contractors 90% negli[980]*980gent and a non-party 10% negligent, and also found Contractors had breached its contract with City, that the breach directly caused damages to ONG, and that it was entitled to recover as a third-party beneficiary. Both verdicts assessed damages in the same amount — $134,469.39. After the trial court entered its judgment based on the jury verdicts, Contractors filed this appeal, arguing, as they did at trial, that as matter of law: (1) the sewer project was a “preengineered project” and thus is exempt from the Act’s requirements; (2) ONG was not an intended beneficiary of the sewer project contract; and (3) they had a right to rely on official plans pursuant to Magnolia Pipe Line Company v. Cowen, 1970 OK 223, 477 P.2d 848.

ANALYSIS

¶ 9 Pursuant to 63 O.S.1991 § 142.6, two duties are imposed on an “excavator”: (1) to notify all operators with underground facilities on or near the excavation area no more than 10 days nor less than 48 hours before excavation, and (2) after the operators of the underground facilities have marked the approximate location of such, to hand dig test holes to determine the precise location of the underground facilities in advance of excavation.2 An excavator is also required to determine the precise location of all underground facilities before using powered or mechanized equipment directly over marked routes of such facilities. See 63 O.S.1991 § 142.7. The Legislature intended the Act to protect both the public and the underground facilities. See Jones v. Oklahoma Natural Gas Company, 1994 OK 89, 894 P.2d 415.

¶ 10 In their first proposition of error, Contractors argue that the trial court erred in oveiruling their motion for directed verdict on the issue of negligence per se, submitting a negligence per se instruction, and submitting an instruction including numerous sections of the Act. They argue that the uncontradicted evidence clearly established that the sewer project was a “preengineered project,” which is specifically exempted from the § 142.6 duties. In support thereof, they rely on the “plain language” of the Act, specifically 63 O.S.1991 §§ 142.2(5), 142.2(12) and § 142.11.

¶ 11 Section 142.11, entitled “Exemptions,” provides that “public agencies and their contractors engaged in work within the public right-of-way which work is a pre-engi-neered project, certified project or routine maintenance

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jones v. Oklahoma Natural Gas Co.
1994 OK 89 (Supreme Court of Oklahoma, 1994)
Oliver v. City of Tulsa
1982 OK 121 (Supreme Court of Oklahoma, 1982)
City of Bethany v. Public Employees Relations Board
1995 OK 99 (Supreme Court of Oklahoma, 1995)
Keck v. Oklahoma Tax Commission
1940 OK 352 (Supreme Court of Oklahoma, 1940)
Magnolia Pipe Line Company v. Cowen
1970 OK 223 (Supreme Court of Oklahoma, 1970)
Oklahoma Employment Security Commission v. Oklahoma Merit Protection Commission
1995 OK CIV APP 76 (Court of Civil Appeals of Oklahoma, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
1998 OK CIV APP 132, 964 P.2d 977, 69 O.B.A.J. 3382, 1998 Okla. Civ. App. LEXIS 110, 1998 WL 685796, Counsel Stack Legal Research, https://law.counselstack.com/opinion/oklahoma-natural-gas-co-v-utility-contractors-inc-oklacivapp-1998.