Oklahoma Contracting Co. Inc. v. Magnolia Pipe Line Co

195 F.2d 391
CourtCourt of Appeals for the Fifth Circuit
DecidedJune 18, 1952
Docket13268_1
StatusPublished
Cited by4 cases

This text of 195 F.2d 391 (Oklahoma Contracting Co. Inc. v. Magnolia Pipe Line Co) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Oklahoma Contracting Co. Inc. v. Magnolia Pipe Line Co, 195 F.2d 391 (5th Cir. 1952).

Opinion

RUSSELL, Circuit Judge.

The litigation from which this appeal emerges involved many items of controversy, but the appeal itself involves only three main questions, as presented by the appellant’s numerous assignments of error, of whether the trial Court erred in denying the counter-claim of appellant for approximately one million and a half, dollars damages which appellant asserted against appellee; whether there was error in refusing to sustain the appellant’s motions to dismiss the complaint of appellee for the recovery of some $268,000, and for a declaration of non-liability of appellee to appellant upon any and all claims arising out of their contractual relationship; and whether the trial Court erred in denying the appellant’s request for a jury trial. The contentions are asserted in the order stated and since a discussion of the case is necessary to present the substance and claims of the rulings denying the motions to dismiss and the request for a jury trial we deal with the questions in the order in which they are presented to us.

The parties will sometimes be referred to as Oklahoma and Magnolia. On April 11th, 1947, Magnolia issued invitations for bids on any one or all of six sections of its projected 650 mile, 20 inch crude oil pipe line extending from Corsicana, Texas through Arkansas and Missouri to Patoka, Illinois. Each prospective bidder was furnished with a 23 page mimeographed copy of the general specifications. These specifications set forth under the title of “Location of Work” each of the six sections covering the line. . A seventh section concerned river crossings, but is not here involved. Attached to the specifications was a map showing the general outline of each section of the proposed pipe line. Oklahoma received the contracts to construct Sections 1, 4, 5, and 6. Separate contracts were executed to cover each section and consisted of some three or four typewritten pages which referred to, and incorporated, the specifications furnished at the time the bids were invited. *393 These specifications provided that Magnolia should furnish “all pipe, casing, primer, doping materials, wrappers, gate valves, fittings, vent pipe and other materials to be used in the construction of said pipe line, excepting welding rods” and Magnolia was obligated to deliver “such pipe and other materials which are to become a part of said line f. o. b. cars at Railroad Stations, Pump Stations, or railroad sidings advantageously located near the right of way”, but the contractor was to move the pipe to the actual location. Under the provisions of this section of the specifications, headed “Materials Company Shall Furnish”, is contained a purported schedule of delivery of pipe which forms the substantial basis of Magnolia’s defense to Oklahoma’s counter-claim. Because of its materiality it is set forth in full. 1 Under the headjng, “Time for Starting and Completing Work” time for starting of either section was provided as five days after the time the company notified the contractor that sufficient pipe would be delivered to complete five miles of line, and a specified *394 number of calendar days was provided for completion. The concluding paragraph of this section is directly material to the issues and is set forth in full. 2 3 In this connection, each typewritten contract contained a paragraph as set forth below. 3 Each of the contracts, the four covering the four sections which Oklahoma assumed to construct, and the two covered by contracts with others, was bid and contracted on a price per foot as to the separate sections and typewritten provisions of each contract placed the consideration to be paid by Magnolia as the amount thus computed. Oklahoma commenced construction on Section 1 on June 2nd, 1947. The record is replete with evidence as to subsequent transactions between the parties and the methods and times in which work was begun, but required to halt on Section 4, because of the lack of pipe, on September 23rd, 1947. Oklahoma contends that this shut-down projected the time of work on Sections 5 and 6 into the period of winter weather with consequent construction difficulties at increased costs which damaged it in the amount sued for. In the present litigation, the main point at issue between the parties is the proper construction of the contracts referred to. The question really arises from the contention of Oklahoma that, since, at the time it was forced to cease its operations there was approximately 100 miles of pipe lo cated at railheads near and on Sections 2 and 3 which were not then necessary, for those operations, that Magnolia should have granted its request that the pipe be moved to Section 4 so it could proceed there and that pipe thus delivered could have been replaced with pipe later obtainable and under order for Section 4. Magnolia contends that in accordance with the specifications and contract the pipe had been delivered to the contractors of Sections 2 and 3 in accordance with the schedule and thus could not be removed, since it was not known when it could be replaced and if- it were removed Magnolia would be liable to contractors on those sections for any damages caused by delay. Oklahoma vigorously asserts that the contract recognizes a clear difference between the pipe delivery schedule from the “pipe supplier to Magnolia”, and the contractual obligation of Magnolia to furnish Oklahoma with pipe, as needed, after Magnolia received the pipe from the pipe supplier. It construes the “present schedule of delivery of pipe as furnished by pipe supplier”, set forth above, as being a matter between Magnolia and the supplier, and that the exculpatory clause purports to release Magnolia for delay or work stoppage only in case the pipe supplier fails to deliver or if Magnolia is unable to furnish the materials as needed for any other reason beyond its control. 'Consequently, since Magnolia had been delivered pipe sufficient to supply Oklahoma needs it should have done so, and is liable for damages caused by a delay thus occasioned. Magnolia replies that the terms of the contract and specifications as a whole clearly show that -the exculpatory language relates to the schedule and failure of delivery to it by the suppliers as thus alloted to each section and that since it is undisputed that as to the sections involved in Oklahoma’s contracts the pipe was not so supplied the delay is clearly within the terms of the contract excusing it from any liability for damages. Our consideration of the contract leads to the *395 conclusion that the contention of Magnolia is correct and that under the terms of the contract and the undisputed facts Magnolia is not liable to Oklahoma for its damage sustained as a result of the delay in procuring the pipe necessary to the construction of Section 4, nor for such damages as may have been thereafter sustained by the projection of period of construction of Sections 5 and 6 into during the winter season. It seems clear that the “present schedule of deliveries” set forth in the specifications is, and must be, the “present schedule of delivery” referred to in the clause of the contract providing that Oklahoma should have no claim for damages for delay or work stoppage due to failure of pipe supplier to deliver pipe to Magnolia.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rachal v. Hill
435 F.2d 59 (Fifth Circuit, 1970)
Home Indemnity Co., New York v. Lechner
191 F. Supp. 116 (S.D. California, 1961)

Cite This Page — Counsel Stack

Bluebook (online)
195 F.2d 391, Counsel Stack Legal Research, https://law.counselstack.com/opinion/oklahoma-contracting-co-inc-v-magnolia-pipe-line-co-ca5-1952.