Ohio River Railroad v. Johnson

40 S.E. 407, 50 W. Va. 499, 1901 W. Va. LEXIS 139
CourtWest Virginia Supreme Court
DecidedDecember 14, 1901
StatusPublished
Cited by8 cases

This text of 40 S.E. 407 (Ohio River Railroad v. Johnson) is published on Counsel Stack Legal Research, covering West Virginia Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ohio River Railroad v. Johnson, 40 S.E. 407, 50 W. Va. 499, 1901 W. Va. LEXIS 139 (W. Va. 1901).

Opinion

Dent, Judge:

An appeal from the circuit court of Wood County, taken by Wm. Johnson, Jr., to a decree rendered on the 27th day of April, 1899, in a chancery suit wherein appellant was defendant and the Ohio River Railroad Company was plaintiff.

In its bill and amended bill the plaintiff alleges that in April, 1882, its right of way for a railroad was obtained from the defendant, through his farm, fifty feet wide, with necessary ground for cuts and fills, according to the original line of such road as surveyed by engineer Wharton. The grant was reduced to writing, signed and acknowledged by the defendant. Afterwards there was a slight addition added thereto as follows: “It having become necessary in the construction of above railroad to use certain ground to deposit waste dirt and also- to move the fence along the line of same and also being necessary to destroy some fruit trees in the grading and protecting the gravel bank mentioned above: Now, therefore, as a consideration of the same the said railroad company have paid to said Johnson the sum of [501]*501one bnndred dollars, the receipt of which the said Johnson hereby acknowledges, and the said Johnson waives all objections to nse of said land and destruction of said trees, and agrees to remove said fence at his own expense.” That there was a provision in the grant that, “It is understood and agreed that the said railroad company must either build said roadbed far enough from the gravel bank underneath which the line runs, so as to keep said bank from washing, or shall protect said bank by a wall or in some way prevent said washing.” That it was found impracticable to build such road without cutting through such gravel bank, which the company did and exposed it to washing, That in March, 188G, the defendant instituted an action for damages against the plaintiff for failing to comply with the covenants of grant, and for constructing the line of its said road outside of the fifty feet granted it according to the Wharton survey or line; that said suit was compromised by the defendant agreeing to let a judgment be entered for eight hundred dollars.

The plaintiff claims that this judgment was a satisfaction for the failure to perform its covenants, and that by reason of the payment of the damages and the possession, of the road outside of the line surveyed by engineer Wharton, it acquired the absolute title to the fifty feet of land of which its railroad as constructed formed the center line without regard to the Wharton line, and that it was entitled to a deed therefor from the defendant, and that the defendant also agreed thereby to the change in its right of way thus made; that the change thus made was the mere shifting of the center line of the entire right of way, to the extent of the change aforesaid against said gravel bank from the former location on the bottom on the river side of said center line. That at the north end of the farm of the defendant is an orchard, that plaintiff instituted a suit to condemn a portion of the same for the sand and gravel, that it had the damages estimated by commissioners and paid the amount three hundred dollars thereof into court, the defendant demanding á jury trial, plaintiff while such condemnation proceedings were pending entered upon such land and removed such sand and gravel. The proceedings were dismissed and abandoned because the court held that an orchard could not be condemned. The defendant then instituted a suit to recover the value of the sand and gravel taken from his land during the pendency of the condemnation [502]*502proceedings. The plaintiff tiren bad an accurate survey of its road bed made, and ascertained that the sand and gravel so taken was inside the fifty foot limit, including the necessary cuts or slopes to make it level, treating its railroad as constructed as the center line of such right of way, and it therefore prayed an injunction to such suit at law, and asked that defendant be required to make a deed tó it for such fifty foot strip with its road as the center line, whether it corresponded with the Wharton survey or not. Defendant answered admitting nearly all the allegations of the bill. He admitted that the railroad as constructed was not only off the Wharton survey, but wras to some extent and especially at the place where the sand and gravel were removed, entirely outside of the right of way which he had agreed to convey to the plaintiff. He admitted that his acquiescence for so long a period of time although under protest and recovery of damages would give the company tire right tj hold the land on which its road bed is constructed, but did not give them the right to go beyond the fifty feet with necessary cuts and fills, subject to the provision as to the gravel bank originally granted. That the confession of judgment and condemnation proceedings estopped the plaintiff from claiming ownership of the land from which the sand and gravel was last taken. On a hearing of the controversy the circuit court decided for the plaintiff and required the defendant to make a deed to the plaintiff covering a strip of ground fifty feet wide through the land with ground for necessary cuts and fills with the road as at present located as the center line.

There are but two propositions presented by this controversy, the establishment of both of which is on the plaintiff, and they must be cleared of all doubt before specific performance should be granted.

1st. Is the center line of the railroad track as now located on the original Wharton line or substantially so ?

2d. If it is materially off of that line, did the defendant agree to the change and thereby agree that the whole right of way' should be shifted so as to make the center line of the track as now constructed the center of such right of way ?

As to the first proposition there can be no doubt. The vast-preponderance of’ evidence, the confessions and admissions of the plaintiff by record and outside of the record fully establishes the fact that in the construction of the road the Whatron line [503]*503was virtually abandoned, not only so, but that .the road, to some extent at least was constructed outside of the right of way, as it would have been had the Wharton line been adhered to. It is true that there is some evidence to the contrary, and certain surveyors in the employ of the plaintiff, by reliance on what they call the slope notes have endeavored to'show that the Wharton line has not been materially departed from. But the solemn admissions of the plaintiff in its confession of judgment, its condemnation proceedings in its original and amended bills in this case, in its failure to produce the original plats of the right of way as made by its surveyor, showing a decisive weakness, where the law requires it to be strong, the evidence of one of the original surveyors, sustained by the preponderance of the oral testimony, places the matter bej'ond doubt or quibble. Nor is the plaintiff any stronger on the other proposition. It shows no contract, agreement or arrangement on the part of the defendant to permit the location of the road to change the center line of the right of way and thus shift the whole right of way. In other words, the right of way as granted was not movable, but was solid to the center of the earth. The plaintiff had the right to place its track in the center or either side thereof in so long as it did not interfere with the defendant's gravel bank,- and in case it did, it was the plaintiff's duty to protect it from washing by stone wall or otherwise. This provision was undoubtedly intended to be a limitation as to cuts and fills and was a restriction in so far as said gravel bank was concerned.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State Ex Rel. Queen v. Sawyers
133 S.E.2d 257 (West Virginia Supreme Court, 1963)
Smith v. Smith
291 P. 298 (Utah Supreme Court, 1930)
Chesapeake & Ohio Canal Co. v. Great Falls Power Co.
129 S.E. 731 (Supreme Court of Virginia, 1925)
Middleton v. Bowyer
83 S.E. 723 (West Virginia Supreme Court, 1914)
Custer v. Hall
76 S.E. 183 (West Virginia Supreme Court, 1912)
Snyder v. Charleston & Southside Bridge Co.
63 S.E. 616 (West Virginia Supreme Court, 1909)
Cole v. Birmingham Union Railway Co.
143 Ala. 427 (Supreme Court of Alabama, 1904)
Uhl v. Ohio River Railroad
41 S.E. 340 (West Virginia Supreme Court, 1902)

Cite This Page — Counsel Stack

Bluebook (online)
40 S.E. 407, 50 W. Va. 499, 1901 W. Va. LEXIS 139, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ohio-river-railroad-v-johnson-wva-1901.