Ohio One Contrs. & Developers L.L.C. v. Am. Steel City Indus. Leasing Inc.

2013 Ohio 5851
CourtOhio Court of Appeals
DecidedDecember 31, 2013
Docket2013-T-0023
StatusPublished

This text of 2013 Ohio 5851 (Ohio One Contrs. & Developers L.L.C. v. Am. Steel City Indus. Leasing Inc.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ohio One Contrs. & Developers L.L.C. v. Am. Steel City Indus. Leasing Inc., 2013 Ohio 5851 (Ohio Ct. App. 2013).

Opinion

[Cite as Ohio One Contrs. & Developers L.L.C. v. Am. Steel City Indus. Leasing Inc., 2013-Ohio-5851.]

IN THE COURT OF APPEALS

ELEVENTH APPELLATE DISTRICT

TRUMBULL COUNTY, OHIO

OHIO ONE CONTRACTORS AND : OPINION DEVELOPERS LLC, : Plaintiff-Appellant, : CASE NO. 2013-T-0023 - vs - : AMERICAN STEEL CITY INDUSTRIAL LEASING INC., :

Defendant-Appellee. :

Civil Appeal from the Trumbull County Court of Common Pleas, Case No. 2008 CV 03160.

Judgment: Affirmed.

Joseph R. Spoonster, Fortney & Klingshirn, 4040 Embassy Parkway, Suite 280, Akron, OH 44333 (For Plaintiff-Appellant).

Kevin P. Murphy and Matthew G. Vansuch, Harrington, Hoppe & Mitchell, Ltd., 108 Main Avenue, S.W., #500, P.O. Box 1510, Warren, OH 44481 (For Defendant- Appellee).

COLLEEN MARY O’TOOLE, J.

{¶1} Appellant, Ohio One Contractors and Developers LLC, appeals from the

February 7, 2013 judgment of the Trumbull County Court of Common Pleas, overruling

its objections and adopting a magistrate’s decision.

{¶2} On December 1, 2007, appellant entered into a contract, comprised of two

agreements, with appellee, American Steel City Industrial Leasing Inc., for the purchase of four brake presses.1 The first agreement, titled “Purchase Order,” was for $16,000.

The second agreement, titled “Shipping & Equipment to Load,” was for $8,000.

Consistent with the “Purchase Order,” appellee wrote a check to appellant for $16,000.

However, prior to the remittance of the check, appellee began to question whether

appellant owned the brake presses. As a result, appellee stopped payment on the

check. Appellee requested proof of ownership from appellant, and notified appellant of

its intent to rescind the contract when it stopped payment. Appellant failed to produce

any proof of ownership before it scrapped the presses. The scrapped presses yielded a

profit to appellant in the amount of $14,267.86.

{¶3} On November 12, 2008, appellant filed a complaint for breach of contract

against appellee, requesting damages in the amount of $13,166, plus interest and

costs. The next month, appellee filed an answer. Motion practice ensued, mediation

was conducted, and various continuances were granted.

{¶4} A trial was ultimately held before a magistrate on October 12, 2012. On

December 7, 2012, the magistrate issued a decision, finding that there were two

separate contracts. The magistrate further found that the “Purchase Order” contract

between the parties was void because appellant did not have any ownership interest in

the brake presses it purported to sell to appellee on December 1, 2007. Thus, the

magistrate recommended that judgment be rendered in favor of appellee.

{¶5} Appellant filed timely objections to the magistrate’s decision but did not file

a transcript of the proceedings. Appellant subsequently filed a reply in support of its

objections. Thereafter, appellee filed a response.

1. Actually, the contracts at issue are dated November 31, 2007. The trial court took the liberty of converting that date to December 1, 2007 to avoid confusion, as the month of November has only 30 days.

2 {¶6} Following a hearing, the trial court overruled appellant’s objections and

adopted the magistrate’s decision on February 7, 2013. Appellant filed a timely appeal

and raises a single assignment of error for our review:

{¶7} “The trial court’s decision adopting the magistrate’s decision is against the

manifest weight of the evidence, is contrary to the law, and is an abuse of discretion.”

{¶8} Appellant presents the following four issues under its sole assignment of

error:

{¶9} “[1.] The determination that Ohio One validly rescinded the purchase

agreement is against the manifest weight of the evidence, is contrary to the law, and is

an abuse of discretion.

{¶10} “[2.] The determination that there were two separate contracts and that

American Steel could only be found in breach of the ‘Purchase Order’ is against the

manifest weight of the evidence, is contrary to the law, and is an abuse of discretion.

{¶11} “[3.] The determination that the ‘Purchase Order’ contract was void is

against the manifest weight of the evidence, is contrary to the law, and is an abuse of

discretion.

{¶12} “[4.] The determination that Ohio One failed to mitigate its damages is

against the manifest weight of the evidence, is contrary to the law, and is an abuse of

discretion.”

{¶13} For ease of discussion, we will address appellant’s issues in a

consolidated fashion.

{¶14} A trial court’s decision to adopt, reject, or modify a magistrate’s decision is

reviewed for abuse of discretion. In re Gochneaur, 11th Dist. Ashtabula No. 2007-A-

3 0089, 2008-Ohio-3987, ¶16. Regarding this standard, we recall the term “abuse of

discretion” is one of art, connoting judgment exercised by a court which neither

comports with reason, nor the record. State v. Ferranto, 112 Ohio St. 667, 676-678

(1925). An abuse of discretion may be found when the trial court “applies the wrong

legal standard, misapplies the correct legal standard, or relies on clearly erroneous

findings of fact.” Thomas v. Cleveland, 176 Ohio App.3d 401, 2008-Ohio-1720, ¶15

(8th Dist.2008).

{¶15} Civ.R. 53(D)(3)(b) states in part:

{¶16} “(iii) An objection to a factual finding, whether or not specifically

designated as a finding of fact under Civ.R. 53(D)(3)(a)(ii), shall be supported by a

transcript of all the evidence submitted to the magistrate relevant to that finding or an

affidavit of that evidence if a transcript is not available. * * *

{¶17} “(iv) Except for a claim of plain error, a party shall not assign as error on

appeal the court’s adoption of any factual finding or legal conclusion, whether or not

specifically designated as a finding of fact or conclusion of law under Civ.R.

53(D)(3)(a)(ii), unless the party has objected to that finding or conclusion as required by

Civ.R. 53(D)(3)(b).”

{¶18} In this case, the record reflects that appellant timely objected to the

magistrate’s decision. However, no transcript or affidavit was filed with the objections.

Appellant, as the objecting party, had a duty to provide a transcript or affidavit. In re

O’Neal, 11th Dist. Ashtabula No. 99-A-0022, 2000 Ohio App. LEXIS 5460, *7 (Nov. 24,

2000). Appellant failed to meet this burden. Given the language of Civ.R. 53 (D)(3)(b)

and the fact that appellant failed to provide the trial court with either a transcript or

4 affidavit, it can only appeal questions of law. See Weisberg v. Sampson, 11th Dist.

Portage No. 2005-P-0042, 2006-Ohio-3646, ¶30; Grenga v. Ohio Edison Co., 7th Dist.

Mahoning No. 03 MA 41, 2004-Ohio-822, ¶11. Therefore, any claimed errors in the

magistrate’s factual determinations are waived. Id. Thus, the question then is whether

appellant’s “manifest weight” argument presents a question of law or fact.

{¶19} Appellant’s first three issues center around the December 1, 2007

contract, comprised of two agreements. “If the contract is clear and unambiguous, its

interpretation is a matter of law, and there is no issue of fact to determine.” Carskadon

v. Avakian, 5th Dist. Delaware No. 11CAG020018, 2011-Ohio-4423, ¶22, citing Inland

Refuse Transfer Co. v. Browning-Ferris Industries of Ohio, Inc., 15 Ohio St.3d 321, 322

(1984), citing Alexander v. Buckeye Pipe Line Co., 53 Ohio St.2d 241 (1978).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Carskadon v. Avakian
2011 Ohio 4423 (Ohio Court of Appeals, 2011)
In Re Gochneaur, 2007-A-0089 (7-25-2008)
2008 Ohio 3987 (Ohio Court of Appeals, 2008)
Weisberg v. Sampson, Unpublished Decision (7-14-2006)
2006 Ohio 3646 (Ohio Court of Appeals, 2006)
Thomas v. City of Cleveland
892 N.E.2d 454 (Ohio Court of Appeals, 2008)
Grenga v. Ohio Edison Company, Unpublished Decision (2-17-2004)
2004 Ohio 822 (Ohio Court of Appeals, 2004)
Ohio Historical Society v. General Maintenance & Engineering Co.
583 N.E.2d 340 (Ohio Court of Appeals, 1989)
State v. Ferranto
148 N.E. 362 (Ohio Supreme Court, 1925)
Alexander v. Buckeye Pipe Line Co.
374 N.E.2d 146 (Ohio Supreme Court, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
2013 Ohio 5851, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ohio-one-contrs-developers-llc-v-am-steel-city-ind-ohioctapp-2013.