Ohio Gas Co. v. Blaze Bldg. Corp., Unpublished Decision (6-4-2004)

2004 Ohio 2881
CourtOhio Court of Appeals
DecidedJune 4, 2004
DocketCourt of Appeals No. WM-03-019, Trial Court No. 02-CI-086.
StatusUnpublished
Cited by5 cases

This text of 2004 Ohio 2881 (Ohio Gas Co. v. Blaze Bldg. Corp., Unpublished Decision (6-4-2004)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ohio Gas Co. v. Blaze Bldg. Corp., Unpublished Decision (6-4-2004), 2004 Ohio 2881 (Ohio Ct. App. 2004).

Opinion

DECISION AND JUDGMENT ENTRY
{¶ 1} Blaze Building Corporation, Rodette Drilling, Mark Ogg and Williams Ogg appeal the judgment of the Williams County Court of Common Pleas in favor of appellee, Ohio Gas Company. Because we conclude that there was some competent, credible evidence to support the trial court's decision, we affirm.

{¶ 2} Blaze Building Corporation contracted to construct improvements to tollbooth facilities at Exit 21 of the Ohio Turnpike in Williams County, Ohio. It awarded a subcontract to Mark Ogg d.b.a. Rodette Drilling to install new underground sewer lines. Mark Ogg subcontracted the job to his brother, William Ogg dba Advanced Technology Drilling. Appellants contacted the Ohio Utility Protection Service ("OUPS") to have all underground facilities marked in the area to be excavated. OUPS notified Ohio Gas Company, who sent out a service technician, Jason Rockey, to locate any gas lines in the area. A six-inch high pressure gas main ran through the area, underneath the turnpike in a north-south direction. South of the turnpike, the gas line turned to the west. On May 24 or 25, 2001, Rockey marked what he believed was the six-inch line with yellow paint and flags.

{¶ 3} On May 29, 2001, the day before the excavation, appellants had been informed by Rockey that they needed to locate a six to eight-inch pipe. Appellants dug an inspection hole where they believed the new sewer line would cross the gas line. A three-inch pipe was found approximately five feet down. After digging another two feet down, appellants still did not locate the six-inch line. Appellants assumed that the six-inch pipe was deeper than seven feet and that it was safe to proceed because the sewer line was going to be installed at a depth of approximately three feet. Appellants told Rockey that they had located the line. Rockey looked in the inspection hole but did not see either the three-inch or six-inch pipe because dirt had fallen into the hole.

{¶ 4} On May 30, 2001, appellants began the horizontal drill to install the sewer line. They had planned to drill 500 feet of the total 1,700 feet project that day. Appellants started drilling to the west of the inspection hole and proceeded about 300 feet east of the hole with a ditch witch that had a boring head with a diameter of four inches. The boring head was replaced with a reamer to widen the drill hole to a diameter of eight inches. A reamer is cone-shaped and has teeth all along its slope and tapers from eight inches at the rear to a four-inch nose. Appellants watched as the reamer was pulled west through the inspection hole. Shortly after the reamer cleared the inspection hole, the machine began to chatter. Thinking they had hit a rock, appellants continued to pull the reamer. Almost immediately, water and dirt began to shoot out from the ground, and the smell of gas was prevalent. It was discovered that the reamer had gouged and punctured the six-inch pipe that appellants had not located. Instead of being deeper than the three-inch pipe as assumed, the six-inch pipe was approximately one foot shallower. Ohio Gas was notified and repaired the six-inch pipe.

{¶ 5} On April 30, 2002, Ohio Gas filed a complaint against appellants to recover the cost of the repair to the six-inch pipe. The case was tried to the bench on May 5, 2003. The trial court found that appellants had violated their duties under R.C.3781.30(C) and (D) when it continued boring/reaming after striking an underground object within the "notice zone" and awarded Ohio Gas $25,905 in damages.

{¶ 6} Appellants present the following assignment of error on appeal:

{¶ 7} "The trial court erred in finding defendants were negligent and that their negligence was the sole proximate cause of the damages sustained by Ohio Gas."

{¶ 8} In their appellate brief, appellants present four issues for this court to consider:

{¶ 9} whether the trial court erred in finding that appellants were obligated to locate the six-inch line; (2) whether the trial court erred in finding that the widest part of the back reamer struck the six-inch pipe before the nose struck where the pipe was ruptured;

{¶ 10} whether the trial court erred in finding appellants negligent when they complied with all the requirements of R.C.3781.25 et seq.; and (4) whether the trial court erred in not finding Ohio Gas negligent when it failed to correctly mark the six-inch pipe and failed to indicate its depth.

{¶ 11} To establish actionable negligence, one must show in addition to the existence of a duty, a breach of that duty and injury resulting proximately therefrom. Mussivand v. David (1989), 45 Ohio St.3d 314, 318, citing Di Gildo v. Caponi (1969), 18 Ohio St.2d 125. In Ohio, there is a nondelegable duty imposed on one excavating below ground to inform himself as to whether "underground utility facilities" (i.e. pipes, lines, and the like), exist so as to avoid damaging them. GTE North, Inc.v. Carr (1993), 84 Ohio App.3d 776, 779. R.C. 3781.25 et seq. sets forth a statutory scheme to safeguard underground utility facilities in private improvement projects. Excavators are responsible for notifying OUPS of the location of an excavation site and the date of the excavation at least two days but not more than ten days before an excavation. R.C. 3781.28(A). Once a contractor notifies OUPS of the location of a proposed excavation, it fulfills its duty to inform itself of the location of the underground utility facilities. Ohio Edison Co. v. WartkoConstr. (1995), 103 Ohio App.3d 177, 180. OUPS then sends notice to each utility with an underground facility in the area. R.C.3781.28(B).

{¶ 12} When notice from OUPS is received, the owner of the underground utility facility has the burden to supply the contractor with accurate information regarding the approximate location of the pipe or line. East Ohio Gas Co. v. KenmoreConstr. Co., Inc. (Mar. 28, 2001), 9th App. Nos. 19567 and 19790. R.C. 3781.29 requires a utility to locate and mark the approximate location of its underground utility facilities at the excavation site within 48 hours of receiving notice. If the utility cannot accurately mark the approximate location, it shallmark the approximate location to the best of its ability, notify the excavator that the markings may not be accurate, and provide additional guidance as needed. Id. (Emphasis added.) "Approximate location" is defined as "the site of the underground utility facility including the width of the underground utility facility plus eighteen inches on each side of the facility." R.C.3781.25(D).

{¶ 13} R.C. 3781.30 provides the duty of the contractor during the excavation:

{¶ 14} "When making excavations, the excavator shall do all of the following:

{¶ 15}

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Columbia Gas of Ohio, Inc. v. Lucas Cty. Sanit. Engineers
2017 Ohio 4108 (Ohio Court of Appeals, 2017)
Boyd v. Moore
919 N.E.2d 283 (Ohio Court of Appeals, 2009)
Opincar v. F.J. Spanulo Construction, 91255 (12-4-2008)
2008 Ohio 6286 (Ohio Court of Appeals, 2008)
Ohio Energy Assets, Inc. v. Grange Ins., 06ap-907 (6-5-2007)
2007 Ohio 2732 (Ohio Court of Appeals, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
2004 Ohio 2881, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ohio-gas-co-v-blaze-bldg-corp-unpublished-decision-6-4-2004-ohioctapp-2004.