Ohio Farmers Insurance v. Commercial Center Contractors Corp.

676 N.E.2d 928, 111 Ohio App. 3d 551, 1996 Ohio App. LEXIS 2299
CourtOhio Court of Appeals
DecidedJune 7, 1996
DocketNo. 95 CA 24.
StatusPublished
Cited by2 cases

This text of 676 N.E.2d 928 (Ohio Farmers Insurance v. Commercial Center Contractors Corp.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ohio Farmers Insurance v. Commercial Center Contractors Corp., 676 N.E.2d 928, 111 Ohio App. 3d 551, 1996 Ohio App. LEXIS 2299 (Ohio Ct. App. 1996).

Opinion

*553 Wolff, Judge.

Ohio Farmers Insurance Company (“OFIC”) appeals from a judgment of the Champaign County Court of Common Pleas, which granted summary judgment in favor of appellee, NationsBank.

The facts of the case are as follows.

In 1987, Urbana Shopping Center Associates, Ltd. (“Urbana Associates”), undertook to construct a shopping center in Urbana. To that end, Urbana Associates gave a promissory note for a construction loan from NationsBank 1 in the amount of $3.9 million. Commercial Centers Contractors Corporation (“Commercial”) was an affiliate of Urbana Associates. NationsBank appears to have disbursed the loan proceeds to Commercial.

Commercial contracted with Carnegie Construction, Inc. (“Carnegie”) for construction of the shopping center. Commercial also entered into a surety agreement with OFIC by which OFIC issued a payment and performance bond on the project. NationsBank was listed, along with Commercial, as an obligee on OFIC’s payment and performance bond. NationsBank’s note was secured by a mortgage on the property, which was properly recorded.

In 1988, Carnegie indicated that it was unable to complete performance on its construction contract. As a result, Commercial demanded that OFIC complete construction of the shopping center pursuant to its surety bond. OFIC subsequently completed the construction of the center at a cost of $348,310.06. OFIC unsuccessfully demanded payment from Commercial for the work it had performed. On January 23, 1990, OFIC filed a mechanic’s lien on the property in the amount of $287,093.90 for those portions of its expenditures which qualified under the mechanic’s lien statute. See R.C. 1311.02.

NationsBank had advanced $3,468,294.47 in principal to Commercial under the promissory note, and on February 20, 1991, Commercial repaid $400,000 of the amount advanced. NationsBank did not distribute the remainder of the construction loan due to Commercial’s subsequent default.

OFIC filed suit against Commercial, NationsBank, Urbana Associates, and other interested parties seeking to recover the cost of completing the contract, or $348,310.06. OFIC argued that it should be allowed to collect from NationsBank for its payments under the performance bond on a theory of unjust enrichment and that, due to NationsBank’s unjust enrichment, OFIC’s mechanic’s lien should be given priority over NationsBank’s mortgage lien for purposes of distributing *554 foreclosure proceeds. NationsBank answered and moved for partial summary judgment against OFIC. OFIC also moved for summary judgment against NationsBank.

In a judgment entry filed on November 1, 1995, the trial court ordered foreclosure of the property due to Urbana Associates’ failure to pay on Nations-Bank’s note and granted NationsBank’s motion for summary judgment. The trial court found that OFIC had a valid mechanic’s lien on the property in the amount of $287,093.90, but that OFIC’s mechanic’s lien did not have priority over NationsBank’s mortgage lien in distribution of the foreclosure proceeds. It implicitly rejected OFIC’s unjust enrichment claims against NationsBank. The trial court did enter judgment for OFIC against Commercial for the full value of the services and supplies provided under the surety bond.

OFIC asserts four assignments of error on appeal:

“I. Unpaid persons supplying labor and material to a construction project have a right to recover under a theory of unjust enrichment, which right is prior to the right of the construction lender.”

OFIC argues that its mechanic’s lien should have been given priority over NationsBank’s mortgage lien in order to prevent NationsBank’s unjust enrichment. OFIC claims that NationsBank was unjustly enriched because it obtained a mortgage on a completed shopping center, in part at OFIC’s expense, yet it had not disbursed loan proceeds to the full extent of its loan commitment. OFIC implies that NationsBank led it to believe that NationsBank would pay OFIC for the work necessary to complete the project, and that OFIC would not have completed the project but for those assurances.

The priority to be given to competing secured interests is clearly prescribed by statute. R.C. 1311.14 states that “the lien of a mortgage given in whole or in part to improve real estate * * * shall be prior to all mechanic’s, materialmen’s and similar liens * * * that are filed for record after said improvement mortgage is filed for record * * OFIC concedes that its lien is in the nature of a mechanic’s lien. Neither the statute nor any cases provide for an exception to the priorities set forth therein based upon the theory of unjust enrichment.

OFIC relies upon numerous cases in which subcontractors who had failed to properly file or otherwise obtain mechanic’s liens were nonetheless allowed to recover under the theory of unjust enrichment. See, e.g., Banks v. Cincinnati (1986), 31 Ohio App.3d 54, 31 OBR 94, 508 N.E.2d 966; Kazmier v. Thom (1978), 63 Ohio App.2d 29, 17 O.O.3d 237, 408 N.E.2d 694. These cases, however, involved recovery from the owner of the property. OFIC has not cited any cases which allow a mechanic’s lienholder priority over a mortgagee which has recorded *555 its mortgage lien prior to the filing of the mechanic’s lien, and we are not inclined to provide for that right. Accord First Natl. Bank v. Bolin (May 11, 1994), Summit App. No. 16405, unreported, 1994 WL 175728.

OFIC also contends that NationsBank “let OFIC complete the project while OFIC relied upon payment from the loan proceeds” and that it “agreed to perform with the understanding that it would be paid from the proceeds of the construction loan.” In its second amended complaint, OFIC alleged that Nations-Bank “knew that OFIC was expending substantial funds to complete performance” of the construction project, but it did not allege that, in completing the. project, it relied upon any assurances of payment from NationsBank. Rather, OFIC’s complaint stated that it had relied upon Commercial’s assurance that OFIC would be paid from the balance of the loan commitment. In its motion for summary judgment, OFIC admitted that representatives of Urbana Associates and Commercial had told OFIC that payment for completion of the work would come from the loan proceeds. OFIC did not allege that a representative of NationsBank made such assurances. Therefore, OFIC did not create a genuine issue of material fact as to whether NationsBank had made false assurances that it would pay OFIC’s expenses in completing Carnegie’s contract. NationsBank is not responsible for the assurances others made regarding how the loan proceeds would be distributed. Moreover, we note that OFIC did not gratuitously agree to complete the contract after Carnegie’s default. Pursuant to its performance bond, for which it presumably had been paid a premium, it was contractually obligated to do so.

OFIC’s first assignment of error is overruled.

“II.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
676 N.E.2d 928, 111 Ohio App. 3d 551, 1996 Ohio App. LEXIS 2299, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ohio-farmers-insurance-v-commercial-center-contractors-corp-ohioctapp-1996.