Ohio Bell Telephone Co. v. Public Utilities Commission

3 N.E.2d 475, 131 Ohio St. 539, 131 Ohio St. (N.S.) 539, 6 Ohio Op. 191, 1936 Ohio LEXIS 258
CourtOhio Supreme Court
DecidedJuly 22, 1936
Docket24694, 24695, 25023 and 25065
StatusPublished
Cited by7 cases

This text of 3 N.E.2d 475 (Ohio Bell Telephone Co. v. Public Utilities Commission) is published on Counsel Stack Legal Research, covering Ohio Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ohio Bell Telephone Co. v. Public Utilities Commission, 3 N.E.2d 475, 131 Ohio St. 539, 131 Ohio St. (N.S.) 539, 6 Ohio Op. 191, 1936 Ohio LEXIS 258 (Ohio 1936).

Opinion

By the Couet.

Valuation Including Peice Teends.

As of the date certain of June 30, 1925, the commission fixed the tentative valuation of the company’s property at $104,282,735. Subsequently this was reduced $10,575,247. Item by item the company complains about the commission’s figures such as those relating to right of way, land, buildings, central office equipment, distributing system, undistributed construction costs, going concern value and construction work in progress. However, a laborious study of the superabundant record of approximately 70,000 pages discloses a sharp conflict of competent evidence on every point, and under such circumstances this court cannot properly hold that the findings of the commission are against the weight of the evidence. Illustrative of this fact is the matter of intangible, undistributed construction expenditures. One witness expressed tfie *582 opinion that the allowance for this item should be approximately $19,088,000; another that it should be $18,525,000; another that it should be $16,000,000; and still another that it should be $12,000,000. The commission after hearing and seeing the witnesses allowed $12,650,143. Certainly this court is at least in no better position to appraise the value of this conflicting testimony.

It is contended that there was failure to consider certain vital elements in determining questions of valuation. For instance, the claim is made that the commission excluded from the property value money necessarily invested in construction work which was in progress, in an average annual amount of $3,000,000 for the nine-year period.

The commission held that no allowance could be included for this work in determining value for rate-making purposes, because the property was not complete and ready for service and therefore not used and useful property in the service of the public within the meaning of Sections 499-8, 499-9, 614-20 and 614-23, General Code. An allowance was made, however, for the item of interest during construction, which fully and adequately compensated the company for the use of its capital which was invested in unfinished construction work, and the amount of allowance so made entered into the rate base which was fixed by the commission. Furthermore, allowance was made for capital so invested as soon as the new construction came into use, and provision was also made for the capitalization of materials used in construction and inventories on hand before they were used in the process of construction.

It is also contended that no consideration was given to the cost of property and the cost of reproduction of property. It may be conceded that such costs are relevant facts to be considered in determining values. Los Angeles Gas & Electric Corp. v. Ry. Comm. of Cali *583 fornia, 289 U. S., 287, 306, 77 L. Ed., 1180, 53 S. Ct., 637.

In support of its contention that cost of property was ignored, the company offered a table which purports to show cost of the company’s intrastate property aside from construction work in progress, and similar facts. But there is nothing in the record to show that the evidence so offered was not considered, along with the other evidence in the case relating to cost, in determining the rate basis.

As to the claim that the commission- did not consider cost of reproducing property, the record discloses that evidence was adduced relating thereto and there is entire absence of a showing anywhere in the record that the commission failed to give proper consideration to such evidence bearing upon the question of expense of reproducing essential property.

A careful consideration of all claims of the company relating to alleged omissions or failure to consider certain elements of value discloses that the contentions are not borne out by the record. In fact, it appears that the commission determined its rate base from all the evidence before it, including that relating to these alleged ignored items, and thus reached the conclusion it did relative to the basic valuation fixed for determining a fair and reasonable rate.

Likewise the company strenuously complains because, although neither side introduced evidence of price trends, the commission took judicial notice of such trends; but even a casual examination of the decisions of the United States Supreme Court unquestionably discloses definite and repeated sanction of this principle.

In the case of Central Kentucky Natural Gas Co. v. Railroad Commission of Kentucky, 290 U. S., 264, 78 L. Ed., 307, 54 S. Ct., 154, Mr. Justice Stone stated that one ground for reversal of the judgment of the lower court was its exclusion “from consideration the *584 profound changes in values, costs of service, consumption- of commodities and reasonable return on invested capital which we judicially know took place during the period of more than five years while the case was pending before the Commission and the Court.” Then in the ninth paragraph of the headnotes of that case, as reported in 78 L. Ed., appears the statement that “judicial notice may be taken of changes in values, cost of service, consumption of commodities and reasonable return on invested capital which have taken place during the period while a case was pending before the Utilities Commission and the Court.”

In the later case of Dayton Power & Light Co. v. Public Utilities Commission of Ohio, 292 U. S., 290, 78 L. Ed., 1267, 54 S. Ct., 647, Mr. Justice Cardozo said that “in view of business conditions, of which we take judicial notice, * * * the rate allowed was adequate.” Then in the twenty-fourth paragraph of the headnotes of that case in 78 L. Ed., it is stated that “the Supreme Court of the United States takes judicial notice of business conditions.”

In the Dayton case, supra, Mr. Justice Cardozo cites the case of Atchison, Topeka & Santa Fe Ry. Co. v. United States, 284 U. S., 248, 76 L. Ed., 273, 52 S. Ct., 146, in which Mr. Chief Justice Hughes said that “There can be no question as to the change in conditions upon which the new hearing was asked. Of that change we may take judicial notice.” Then in the second paragraph of the headnotes of the case in 76 L. Ed., appears the statement that “the Court may take judicial notice of a general economic depression. ’ ’

In view of these authorities it is readily apparent that the commission committed no error in this respect.

Operating Expenses.

In the matter of operating expenses, the commission apparently accepted and applied the testimony of the company in the consideration and determination pf *585 most of the items involved. That was true as to the very important item covering cost of current maintenance, including salaries, in which there was no reduction whatever from the claims of .the company.

We shall refer particularly to the amount urged by the company for allowance for license contract services. These charges were seriously challenged by the commission.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Cleveland v. Public Utilities Commission
209 N.E.2d 424 (Ohio Supreme Court, 1965)
Baltimore Gas & Electric Co. v. McQuaid
152 A.2d 825 (Court of Appeals of Maryland, 1959)
In Re New England Tel. & Tel. Co.
66 A.2d 135 (Supreme Court of Vermont, 1949)
Dworken v. Public Utilities Commission
12 N.E.2d 490 (Ohio Supreme Court, 1938)

Cite This Page — Counsel Stack

Bluebook (online)
3 N.E.2d 475, 131 Ohio St. 539, 131 Ohio St. (N.S.) 539, 6 Ohio Op. 191, 1936 Ohio LEXIS 258, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ohio-bell-telephone-co-v-public-utilities-commission-ohio-1936.