O'GRADY v. City of Hoover

519 So. 2d 1292, 1987 WL 39416
Supreme Court of Alabama·Decided December 31, 1987·No. 86-1243·Published·Cited by 6 cases

Opinions

[EDITORS' NOTE: THIS PAGE CONTAINS HEADNOTES. HEADNOTES ARE NOT AN OFFICIAL PRODUCT OF THE COURT, THEREFORE THEY ARE NOT DISPLAYED.] *Page 1294

This is an appeal from a judgment entered in a statutory validation proceeding initiated by the City of Hoover, Alabama (the "City"), pursuant to the provisions of Ala. Code (1975), §§ 6-6-750 et seq., to validate general obligation warrants in the principal amount of $12,150,000. The petition was filed against the taxpayers and citizens of the City, and an answer was filed by the district attorney. Joe M. O'Grady and Daniel R. Farnell also responded by filing an answer entitled "Showing of Cause." Pursuant to an order of the trial court, O'Grady and Farnell were named intervenors and parties defendant in the validation proceeding.

The validation hearing was held before the Honorable Marvin Cherner in the Circuit Court of Jefferson County on May 7 and 8, 1987. After receiving briefs from attorneys for both sides, the trial court rendered its "Findings of Fact, Conclusions of Law and Final Judgment," in which it validated and confirmed the warrants and all agreements and proceedings initiated by the City. The district attorney participated in the proceedings below, but did not join the appellants in this appeal.

The underlying facts are undisputed. On April 6, 1987, the elected officials of the City of Hoover adopted Ordinance No. 87-602 authorizing the issuance of general obligation warrants in the principal amount of $12,150,000. These funds were to be donated to the Public Park and Recreation Board of the City of Hoover (the "Park Board") and were to be used by the Park Board for the acquisition and construction of a public park, athletic field and stadium, and related improvements. The Park Board is a public corporation, and, as the owner of the stadium, it entered into a lease agreement permitting the Birmingham Baseball Club, Inc. (the "Barons"), to use the stadium for playing baseball during the minor league baseball season for ten years with an option to renew the lease for an additional five-year period.

Additionally, the Park Board and the Barons have entered into a management agreement for the stadium to be utilized for other recreational, charitable, and civic events. Under this agreement, the Barons will have sole use of the stadium for the management and conducting of events other than the playing of professional baseball. The lease and the management agreement were executed contemporaneously, and when read together provide for a year-round lease with a duration of ten years with an option to renew for an additional five-year period.

The trial court made the following pertinent findings of fact:

"11. The Warrants will be issued to provide funds for the acquisition and construction of public park and recreational facilities, specifically a public park, athletic field and stadium and related improvements (the 'Project') to be owned by The Public Park and Recreation Board of the City of Hoover. . . . The Board will acquire and construct the Project in the City with the funds provided by the City.

". . .

"13. The Board will own the Project and will lease the same to Birmingham Baseball Club . . . to play baseball during *Page 1295 baseball season pursuant to a lease agreement . . . between the Board and the Baseball Club.

"14. The Board will own the Project and will operate the same for other public events pursuant to a management agreement . . . between the Board and the Baseball Club . . .

". . .

"17. There is sufficient evidence to support the findings and determinations of the Governing Body contained in the Authorizing Ordinance. There is no evidence of fraud, collusion or unfair dealing in connection with any of the aforesaid documents or proceedings. Neither the size of the stadium nor any other evidence offered establishes any abuse of discretion by the elected officials in carrying out their duties."

From these findings, the trial court reached the following conclusions of law:

"1. All actions and things required under the provisions of the Validation Act to be had and done in this proceeding preliminary to the making of the findings of fact, conclusions of law and judgment of this Court herein contained, have been had and done in the manner provided by the Validation Act. The City and the Governing Body have power to institute and conduct this proceeding and have duly authorized the same.

". . .

Free access — add to your briefcase to read the full text and ask questions with AI

O'GRADY v. City of Hoover, 519 So. 2d 1292, 1987 WL 39416 (Ala. 1987).

519 So. 2d 1292 (O'GRADY v. City of Hoover) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

In Re Jefferson County, Ala.
469 B.R. 92 (N.D. Alabama, 2012)
Guarisco v. City of Daphne
825 So. 2d 750 (Supreme Court of Alabama, 2002)
Dothan Area Chamber of Commerce v. Shealy
561 So. 2d 515 (Supreme Court of Alabama, 1990)
Orange v. Bailey
548 So. 2d 424 (Supreme Court of Alabama, 1989)
Wilson v. City of Bessemer
547 So. 2d 868 (Supreme Court of Alabama, 1989)