The issue before us is precisely the same as in Consumers’ Counsel v. Pub. Util. Comm. (1984), 10 Ohio St. 3d 49 (hereinafter “Consumers’ Counsel”) and Cincinnati Bell Tel. Co. v. Pub. Util. Comm. (1984), 12 Ohio St. 3d 280, 287-288 (hereinafter “Cincinnati Bell”). For the following reasons, we reaffirm our prior position and reverse the order of the Public Utilities Commission.
In order for this court to determine if there has been an abuse of discretion we must first understand why the commission’s prior order, on the same subject matter, in In re Extension of F.C.C. First Report and Order (July 31, 1981), case No. 81-828-TP-ORD (“1981 order”), is no longer controlling. A few simple sentences in the commission’s order in [22]*22this case would have sufficed in this regard. An even simpler response could have been a reopening and modification of the 1981 order to create a case by case approach for expensing Class A telephone carrier station connections. This was never done.
The commission states in its order in the present case:
“The issue really is how should these test year expenses be treated given the previously authorized phase-in treatment prescribed by this Commission. We believe that it is only logical to adopt the 100 percent ex-pensing treatment given the fact that we are setting rates prospectively and that the company will be actually expensing such costs on its books during the time these rates will be in effect.” Although the “previously authorized phase-in treatment prescribed by this Commission” is mentioned, the commission does not specifically address or overrule its 1981 order. No explanation is given for changing the expensing levels during the test year to conform with the utility’s in-house accounting methodology.
More importantly, no explanation is given why the purpose underlying the 1981 order’s gradual four year phase-in approach is now better served by flash-cut expensing. As Roger Montgomery, a staff witness, pointed out in his testimony, “[t]he intent of the phase-in periods was to reduce the impact of the added revenue requirement to the ratepayers that would occur if a Class A telephone carrier were to ‘flash cut’ this station connection ex-pensing accounting change, the FCC ordered the phase-in methodology. However, this accounting change will not affect customer rates until there is a rate case which recognize [sic] it.” (Emphasis added.) Now, the commission has imposed the full brunt of the flash-cut expense on consumers without justifying its rationale for the burden.1
We concluded, in Consumers’ Counsel, supra, that the commission has [23]*23the discretion to modify the accounting treatment of station connections expenses. We will not allow the commission to arbitrarily change expensing levels unless the commission explains why its 1981 order and the rationale behind gradual phase-in should be overruled. Articulating the reasons for an order without reference to the prior order gives no context to the subsequent order and makes ascertaining an abuse of discretion virtually impossible. Consumers who rely on commission directives are unable to understand why the basis for the 1981 order, the ostensible protection of consumers for four years with a gradual phase-in of station connections expenses, must now give way to utility convenience rather than need.
A separate issue is raised by Ohio Bell which argues that this court may not interfere with commission actions that recognize and give effect to averred federally preempted station connections expensing levels. Unfortunately for Ohio Bell, this court has never accepted the preemption argument on the station connections issue (see Cincinnati Bell, supra, concurring opinion by Celebrezze, C.J.). Additionally, the federal courts are not in agreement on this issue. In the most recent decision, New England Tel. & Tel. Co. v. Pub. Util. Comm, of Maine (C.A. 1, 1984), 742 F.2d 1, the First Circuit Court of Appeals held Section 401(b) (of Title 47, U.S. Code) of the Federal Communications Act of 1934 (Section 151 et seq., Title 47, U.S. Code) does not include rulemaking decisions (specifically, In re Amendment of Part 31, First Report and Order [1981], 85 F.C.C.2d 818) in its definition of “order.” Southwestern Bell Tel. Co. v. Arkansas Pub. Serv. Comm. (C.A. 8, 1984), 738 F.2d 901.
If, arguendo, preemption were applicable, Ohio Bell’s argument would still be moot since this court’s position has only embraced the FCC’s original four year phase-in position. It was the FCC, not this court or the state legislature, which delegated application of station connections ex-pensing levels to the state utility commissions. Both methods in issue — the flash-cut and the four year phase-in — conform with the FCC’s First Report and Order. It should parenthetically be noted that the commission has taken care to specifically disavow itself from intervening-appellee’s preemption argument.
At some point the United States Supreme Court will address the problems of FCC preemption in view of the difficulties arising from the breakup of AT&T. In the meantime, pending specific resolution of the preemption question, we will not abdicate our state constitutional and statutory responsibilities.
Accordingly, because the commission has not justified its overruling of its 1981 order, although given ample warning to do so by our prior decision, we reverse the order of the commission.
Order reversed.