Oenga v. United States

97 Fed. Cl. 80, 2011 U.S. Claims LEXIS 70, 2011 WL 446728
CourtUnited States Court of Federal Claims
DecidedFebruary 8, 2011
DocketNo. 06-491L
StatusPublished
Cited by13 cases

This text of 97 Fed. Cl. 80 (Oenga v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Oenga v. United States, 97 Fed. Cl. 80, 2011 U.S. Claims LEXIS 70, 2011 WL 446728 (uscfc 2011).

Opinion

ORDER ON MOTIONS FOR RECONSIDERATION AND FOR ENTRY OF JUDGMENT

NANCY B. FIRESTONE, Judge.

In the opinion issued following trial in this case, Oenga v. United States, 96 Fed.Cl. 479 (2010), the court held that the plaintiffs (“Oengas”) are entitled to damages for the defendant’s (“government’s”) breach of trust stemming from the unauthorized use of the plaintiffs’ native allotment by the defendant-intervenors (collectively referred to as “BPX” for the sake of simplicity). The court held that damages should be measured as fair annual rental for these unauthorized uses, which is properly calculated using the cost savings methodology presented by the plaintiffs’ expert, Dr. Thomas Power:

[Tjhese calculations shall be based on the cost savings provided by the allotment as compared to construction of a bypass drill pad, using $5.3 million in 1988 dollars as the cost of such an alternative, a 7% nominal discount rate, and the 2.88% average [Consumer Price Index (“CPI”)] as discussed by Dr. Power. The plaintiffs shall then allocate the total savings based on the percentage shares of Heald Point production for Lisburne, West Niakuk, and Raven. The plaintiffs are entitled to the entirety of the cost savings attributable to oil produced from these areas during time periods this court has found to be outside the scope of the lease and within this court’s jurisdiction.

Id. at 547. The court allowed the parties to submit their proposed calculations according to these criteria and set a schedule for briefing on any motions for reconsideration.

All of the parties have submitted proposed damages calculations and motions for reconsideration. The defendant-intervenors have also filed a motion for clarification. The court shall address each of these motions for reconsideration and for clarification, plus additional issues raised in the parties’ briefs regarding their proposed damages calculations.

I. MOTIONS FOR RECONSIDERATION AND CLARIFICATION

A. Standard of Review

The applicable standards for reconsideration are set forth in Rule 59(a) of the Rules of the Court of Federal Claims (“RCFC”). RCFC 59(a) provides that reconsideration or rehearing may be granted as follows:

[83]*83(A) for any reason for which a new trial has heretofore been granted in an action at law in federal court; (B) for any reason for which a rehearing has heretofore been granted in a suit in equity in federal court; or (C) upon the showing of satisfactory evidence, cumulative or otherwise, that any fraud, wrong, or injustice has been done to the United States.

RCFC 59(a)(1). Put another way, “the court may grant a motion for reconsideration when there has been an intervening change in the controlling law, newly discovered evidence, or a need to correct clear factual or legal error or prevent manifest injustice.” Young v. United States, 94 Fed.Cl. 671, 674 (2010) (citing RCFC 59(a)(1); Bd. of Trs. of Bay Med. Ctr. v. Humana Military Healthcare Servs., Inc., 447 F.3d 1370, 1377 (Fed.Cir.2006); Fla. Power & Light Co. v. United States, 66 Fed.Cl. 93, 96 (2005)). “The decision whether to grant reconsideration lies largely within the discretion of the [trial] court.” Yuba Natural Res., Inc. v. United States, 904 F.2d 1577, 1583 (Fed.Cir.1990). “The court must consider such motion with ‘exceptional care.’ ” Henderson Cnty. Drainage Dist. No. 3 v. United States, 55 Fed.Cl. 334, 337 (2003) (quoting Fru-Con Constr. Corp. v. United States, 44 Fed.Cl. 298, 300 (1999), aff'd, 250 F.3d 762 (Fed.Cir.2000)). “A motion for reconsideration is not intended, however, to give an ‘unhappy litigant an additional chance to sway* the court.” Matthews v. United States, 73 Fed.Cl. 524, 525 (2006) (quoting Froudi v. United States, 22 Cl.Ct. 290, 300 (1991)). In that connection, a motion for reconsideration “does not provide an occasion for a party ‘to raise arguments it could have properly raised previously, but did not.’” Four Rivers Invs., Inc. v. United States, 78 Fed.Cl. 662, 664 (2007) (quoting Browning Ferris Indus., Inc. & Subsidiaries v. United States, No. 05-738T, 2007 WL 1412087, at *1 (Fed.Cl. May 10, 2007)). “Motions for reconsideration must be supported ‘by a showing of extraordinary circumstances which justify relief.’ ” Caldwell v. United States, 391 F.3d 1226, 1235 (Fed.Cir.2004) (quoting Fru-Con Constr., 44 Fed.Cl. at 300).

B. Plaintiffs’ Motion for Reconsideration

The plaintiffs have filed a motion for reconsideration arguing that the court should reverse its ruling following trial that the cost savings provided by the Oenga allotment should be compared to BPX’s alternative cost of building a bypass road adjacent to Heald Point. The plaintiffs argue that such a bypass road was not a legally viable option for BPX because it would have blocked the plaintiffs’ access to the water along the western side of Heald Point. The plaintiffs thus argue that the court must select the plaintiffs’ preferred alternative, the subsea pipeline, for use in the cost savings analysis.

The defendant and defendant-intervenors contend that a bypass road would not have blocked the plaintiffs littoral access, as it could have been constructed to allow for a channel between the allotment and the bypass road, or, if there were no channel, the plaintiffs could access the water by crossing the bypass road. Further, the defendant-intervenors argue that the plaintiffs’ littoral rights are not such that they could have prevented the state from allowing BPX to fill the tidelands adjacent to the allotment.

The court declines to reconsider its decision, which was based on the evidence and testimony presented at trial that the bypass road alternative presented a viable alternative for BPX to the use of the plaintiffs’ allotment. The court heard the plaintiffs make this argument previously and, while the court did not explicitly discuss the issue of littoral access in the opinion, the court implicitly rejected the plaintiffs’ argument when stating that “the court finds that this [bypass road] alternative would have been a real option for BPX given its exploration of a bypass road alternative in conjunction with the planned causeway.” Oenga, 96 Fed.Cl. at 544. As the defendant-intervenors correctly point out, testimony showed that BPX had alternative ways of constructing the bypass road that would have allowed the plaintiffs to continue enjoying access to the water on the western side of their allotment. Of course, the court noted that raising tidelands in this manner would have posed some regulatory hurtles for BPX, as discussed infra [84]*84Part I.C.2 in the context of the cost of an alternative facility site. However, the court does not agree with the plaintiffs either as a matter of fact or as a matter of law that construction of a parallel bypass road would have been foreclosed, making it inappropriate for the court to use the cost of such an alternative in the cost savings approach to calculating damages in this case. Accordingly, the plaintiffs’ motion for reconsideration is DENIED.

C.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Peretz v. United States
Federal Claims, 2020
Hymas v. United States
Federal Claims, 2019
Menendez v. United States
Federal Claims, 2018
Lucier v. United States
Federal Claims, 2018
Baley v. United States
134 Fed. Cl. 619 (Federal Claims, 2017)
Klamath Irrigation v. United States
134 Fed. Cl. 619 (Federal Claims, 2017)
Nie v. United States
Federal Claims, 2016
Ogunniyi v. United States
Federal Claims, 2016
Fillmore Equipment of Holland, Inc. v. United States
105 Fed. Cl. 1 (Federal Claims, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
97 Fed. Cl. 80, 2011 U.S. Claims LEXIS 70, 2011 WL 446728, Counsel Stack Legal Research, https://law.counselstack.com/opinion/oenga-v-united-states-uscfc-2011.