Oehm v. Michigan-Wisconsin Pipe Line Co.

199 F.2d 253, 1 Oil & Gas Rep. 1596, 1952 U.S. App. LEXIS 3320
CourtCourt of Appeals for the Seventh Circuit
DecidedOctober 10, 1952
Docket10559
StatusPublished
Cited by1 cases

This text of 199 F.2d 253 (Oehm v. Michigan-Wisconsin Pipe Line Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Seventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Oehm v. Michigan-Wisconsin Pipe Line Co., 199 F.2d 253, 1 Oil & Gas Rep. 1596, 1952 U.S. App. LEXIS 3320 (7th Cir. 1952).

Opinion

MAJOR, Chief Judge.

Plaintiffs initiated this suit, entitled “Complaint in Ejectment,” in the State Court of Indiana to recover possession of real estate and damages for its detention which, upon defendant’s motion, was removed to the United States District Court. Defendant by answer denied the material allegations of the complaint and that plaintiffs were entitled to the relief sought. Defendant, also by its counterclaim, demanded specific performance of an agreement, alleged to have been made by plain *254 tiffs, to convey to the defendant a right-of-way across plaintiffs’ property for the installation and maintenance of defendant’s gas pipe line.

The District Court, after trial and on November 19, 1951, made its findings of fact, conclusions of law and rendered a memorandum opinion. In conformity with such findings and conclusions, the court, on December 3, 1951, entered its judgment and decree, by which it was adjudicated that defendant was not entitled to any relief under its counterclaim and that plaintiffs were not entitled to ejectment as sought in their complaint. The judgment provided, however, that unless the defendant “shall within thirty days from the entry of this decree agree with the plaintiffs upon the compensation to be paid, and shall pay it, for an easement or right-of-way in, over, and across the property of plaintiffs in which the twenty-two inch steel pipe line of defendant is installed and for which the defendant has not seured an easement or right-of-way from plaintiffs under the instrument dated July 27, 1949, or shall, within said thirty days begin a proceeding in Eminent Domain for the acquisition of an easement or right-of-way for such pipe line as installed, and upon final judgment shall pay the amount of such compensation fixed without delay, then the plaintiffs herein may apply to this court for a mandatory injunction against the defendant’s continuing to maintain and operate such gas pipe line.” From this judgment the appeal comes to this court.

Defendant, Michigan-Wisconsin Pipe Line ' Company, a Delaware corporation, is a natural gas company as defined in Section 2 of the Natural Gas Act of June 21, 1938, 52 Stat. 821, 15 U.S.C. § 717(a) (6). The Federal Power Commission, November 30, 1946, issued to it a certificate of public convenience and necessity under Section 7(c) of said Natural Gas Act, 15 U.S.C.A. § 717 f(c) and pursuant thereto the defendant constructed, at a cost exceeding $52,000,000, a gas pipe line for the transmission of natural gas from a point in Hansford County, Texas, through the states of Texas, Oklahoma, Kansas, Nebraska, Missouri, Iowa, Illinois, Indiana, and to a point near Big Rapids, Michigan, and a branch from Sandwich, Illinois into Wisconsin, for the transportation and sale of natural gas in interstate commerce and resale for ultimate public consumption for domestic, commercial, industrial and other uses.

In the spring of 1949, defendant negotiated with Mr. Oehm, one of the plaintiffs (plaintiffs are husband and wife), for the purchase of a right-of-way across farm land owned by plaintiffs for a twenty-two inch pipe line as a part of said natural gas transmission pipe line system and, failing to agree, the defendant, on July 9, 1949, filed its complaint in an Indiana State Court for the condemnation of a right-of-way easement across plaintiffs’ land. The right-of-way sought consisted of a strip of land seventy-five feet in width, which was meticulously described. (We see no occasion to set forth this lengthy description.)

On July 25, 1949, Mr. Oehm in writing agreed to enter into an agreement with defendant for a consideration of $8,000, allowing the defendant “to construct a pipe line across his property in accordance with description in complaint.” (Obviously, this refers to the complaint in the condemnation suit.) On July 27, 1949, an instrument was signed by plaintiffs, in which receipt of the sum of $7,662.00 was acknowledged, in full payment and satisfaction of all damages incident to or in connection with the construction of the pipe line to be laid over certain land of the plaintiffs, the description being that contained in a second instrument executed concurrently with the first and designated as a right-of-way contract. This second agreement was signed by plaintiffs and, for the defendant, by Walter Gillice. By this second agreement plaintiffs acknowledged payment by the defendant in the sum of $338.00, as the consideration for the grant and conveyance by the plaintiffs to the defendant of the right to construct, maintain and operate a gas pipe line across and upon certain described land. The description therein set forth is the same as that contained in defendant’s condemnation suit filed in the State Court of Indiana, as well as that in *255 the two instruments executed by plaintiffs, heretofore referred to. Thus, as shown by these two instruments executed on July 27, 1949, plaintiffs were paid by the defendant the sum of $7,662.00 for damages and $338.00 for the right-of-way, or a total of $8,000.00, the consideration named in plaintiffs’ agreement of July 25, 1949.

A further statement of the controverted issues will show the reason for the somewhat detailed narration of the occurrences of July 27, 1949, and prior thereto. On the face of these instruments, it is obvious that defendant acquired an easement on a strip of land meticulously and certainly described therein, which was the same land sought to be condemned by its suit in the State Court. Defendant, however, did not install its pipe line on the strip of land thus acquired but upon a right-of-way, different in part, which it claims to have acquired by a contract dated August 31, 1949. (About one-third of defendant’s pipe line was installed on the right-of-way acquired by the contract of July 27, 1949, and about two-thirds on a different right-of-way.) This asserted agreement will be subsequently discussed and is mentioned here only for the purpose of showing that the instant controversy arises from the fact that the defendant in the installation of its pipe line utilized a right-of-way different and other than that which it acquired on July 27, 1949. Whether it was justified in so doing is also a matter for subsequent consideration.

As noted, defendant, by the instruments of July 27, 1949, acquired an easement over a definitely described strip of land. It is not discernible from the record why defendant failed to utilize the easement thus acquired but instead laid its pipe line elsewhere. No claim is made that there was a mutual mistake in the description contained in the July 27 instrument and it must be assumed, so we think, that subsequent to the time of acquiring the easement therein set forth, defendant changed its mind as to the location of its line. Defendant contends, however, that the right-of-way contract dated July 27, 1949 is not binding upon it because its name was signed to the contract, without authority, by Walter Gillice. This asserted lack of authority was first raised by defendant in its counterclaim and denied by plaintiffs in their answer. No proof was offered on the issue of Gillice’s authority and, in our view, none was needed because his act was plainly ratified by the defendant. As already shown, plaintiffs agreed, for a designated consideration, to convey to defendant an easement over a certain described right-of-way which defendant had sought to acquire by condemnation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Rizza Chevrolet, Inc.
9 F. Supp. 2d 908 (N.D. Illinois, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
199 F.2d 253, 1 Oil & Gas Rep. 1596, 1952 U.S. App. LEXIS 3320, Counsel Stack Legal Research, https://law.counselstack.com/opinion/oehm-v-michigan-wisconsin-pipe-line-co-ca7-1952.