Odyssey Contracting Corp. v. J.F. White Contracting Co.

94 N.E.3d 435, 92 Mass. App. Ct. 1107, 2017 WL 4414100, 2017 Mass. App. Unpub. LEXIS 867
CourtMassachusetts Appeals Court
DecidedOctober 5, 2017
Docket16–P–1749
StatusPublished

This text of 94 N.E.3d 435 (Odyssey Contracting Corp. v. J.F. White Contracting Co.) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Odyssey Contracting Corp. v. J.F. White Contracting Co., 94 N.E.3d 435, 92 Mass. App. Ct. 1107, 2017 WL 4414100, 2017 Mass. App. Unpub. LEXIS 867 (Mass. Ct. App. 2017).

Opinion

This appeal arises out of disputes between a painting subcontractor, Odyssey Contracting Corporation (Odyssey), and the general contractor, White-Skanska-Consigli, JV (WSC),3 related to the construction and renovation of the Longfellow Bridge between Boston and Cambridge. WSC moved to compel arbitration of all claims in Odyssey's first amended complaint, which alleged breach of contract, beach of the covenant of good faith and fair dealing, fraud, fraudulent inducement, and violations of G. L. c. 93A. In a written memorandum of decision, a Superior Court judge allowed the motion in large part, concluding that the terms of the subcontract gave WSC the option to elect to submit any dispute to arbitration. However, as to two of the issues in dispute, (1) "winter payment terms," and (2) "ARG payment percentages," the judge concluded that WSC had expressly waived its right to elect arbitration. On appeal pursuant to G. L. c. 251, § 18(a )(1), WSC challenges the denial of its motion to compel arbitration as to those issues. We reverse.

Background. We briefly summarize the facts relevant to that motion.

Odyssey entered into a subcontract with WSC to provide labor and materials for the painting work on the Longfellow Bridge. The subcontract provided that WSC had "the option, at its election, to submit any dispute to arbitration." The subcontract further provided that, before a dispute could be arbitrated or litigated, the parties would conduct a "principal's [sic ] meeting" and make good faith efforts to resolve the dispute. The parties also agreed that if the principals' meeting did not resolve the dispute, they would submit the dispute to mediation.

Multiple disputes between the parties arose. On August 12, 2014, Odyssey sent WSC a letter which stated:

"Having failed to reach an agreement on the two issues on the agenda, and your lack of interest in discussing the winter costs, this will confirm that we agreed to waive the mediation step set forth in the Subcontract and proceed directly to arbitration. Attached is our memo summarizing the meeting and requesting confirmation that WSC will elect to arbitrate as it has previously for [other] claims."

The letter went on to discuss an additional dispute about extra winter weather costs and how they should be calculated. The letter further provided: "In the event that you are not interested in settling the winter costs then we request your concurrence to skip the intermediate steps and proceeding [sic ] to arbitration for all our claims."

WSC responded in a letter dated August 14, 2014:

"As requested by you WSC is willing to skip mediation on the two items we have had a Principals meeting on, Winter Payment terms per our January 20th agreement & ARG payment percentages by specification section 961 rather than section 960. As we discussed in the meeting, these are contract interpretation issues and should be resolved through litigation, if necessary, in Suffolk Superior Court, Boston, Massachusetts. We will not elect arbitration on these issues. Moreover, we will require a Principals meeting and mediation on all future claims."

Despite originally proposing that the parties bypass mediation, Odyssey ultimately insisted on mediating the relevant claims. When mediation failed, Odyssey filed its complaint against WSC in Superior Court.4 In response, WSC filed a motion to compel arbitration pursuant to the provisions of the subcontract. Odyssey opposed the motion, arguing that WSC waived its right to arbitration in the August 14 letter.

The judge concluded that WSC had "waived arbitration only with respect to the two issues identified in its August 14, 2014 letter to Odyssey: 'Winter Payment terms per our January 20th agreement & ARG payment percentages by specification section 961 rather than section 960.' ... [A]ll other issues besides the two for which arbitration was expressly waived in the August 14, 2014 letter, must be submitted to arbitration."

Discussion. 1. Standard of review. General Laws c. 251, § 18(a )(1), authorizes an appeal directly from the denial of a motion to compel arbitration. See Joulé, Inc. v. Simmons, 459 Mass. 88, 92 (2011). Generally, we review a judge's order on a motion to compel arbitration de novo. See Miller v. Cotter, 448 Mass. 671, 676 (2007) (enforceability of arbitration agreement); Warfield v. Beth Israel Deaconess Med. Ctr., Inc., 454 Mass. 390, 395 (2009) (arbitrability of statutory employment discrimination claims); Joulé, Inc. v. Simmons, supra (impact of arbitration clause on Massachusetts Commission Against Discrimination proceedings); Machado v. System4 LLC, 471 Mass. 204, 208 (2015) (enforceability of arbitration clause by nonsignatory).

However, we review a determination of waiver for abuse of discretion. Martin v. Norwood, 395 Mass. 159, 162 (1985) ("An appellate court, reviewing a judge's finding that a party has waived arbitration, must determine whether, in light of the strong ... policy favoring arbitration, the judge abused his discretion"); Chamberland v. Arbella Mut. Ins. Co., 91 Mass. App. Ct. 680, 684 (2017). A judge's clear error as to application of law to the relevant facts before the court constitutes abuse of discretion. See Freedman v. Freedman, 49 Mass. App. Ct. 519, 521 (2000) ; Jaynes, petitioner, 88 Mass. App. Ct. 745, 747 (2015).

2. Waiver. An agreement to arbitrate a dispute, like any contractual provision, may be waived. See Weston Sec. Corp. v. Aykanian, 46 Mass. App. Ct. 72, 80 (1998). "Under the common law of contracts, waiver is the 'intentional relinquishment of a known right.' " BourgeoisWhite, LLP v. Sterling Lion, LLC, 91 Mass. App. Ct. 114, 119 (2017), quoting from Dynamic Mach. Works, Inc. v. Machine & Elec. Consultants, Inc., 444 Mass. 768, 771 (2005). "Waiver may be express or 'inferred from a party's conduct and the surrounding circumstances.' " BourgeoisWhite, LLP v. Sterling Lion, LLC, supra, quoting from

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Home Gas Corp. of Massachusetts, Inc. v. Walter's of Hadley, Inc.
532 N.E.2d 681 (Massachusetts Supreme Judicial Court, 1989)
Martin v. Norwood
478 N.E.2d 955 (Massachusetts Supreme Judicial Court, 1985)
Machado v. System4 LLC
471 Mass. 204 (Massachusetts Supreme Judicial Court, 2015)
Jaynes
42 N.E.3d 1158 (Massachusetts Appeals Court, 2015)
Dynamic Machine Works, Inc. v. Machine & Electrical Consultants, Inc.
831 N.E.2d 875 (Massachusetts Supreme Judicial Court, 2005)
Miller v. Cotter
448 Mass. 671 (Massachusetts Supreme Judicial Court, 2007)
Warfield v. Beth Israel Deaconess Medical Center, Inc.
910 N.E.2d 317 (Massachusetts Supreme Judicial Court, 2009)
Joulé, Inc. v. Simmons
459 Mass. 88 (Massachusetts Supreme Judicial Court, 2011)
Weston Securities Corp. v. Aykanian
46 Mass. App. Ct. 72 (Massachusetts Appeals Court, 1998)
Freedman v. Freedman
730 N.E.2d 913 (Massachusetts Appeals Court, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
94 N.E.3d 435, 92 Mass. App. Ct. 1107, 2017 WL 4414100, 2017 Mass. App. Unpub. LEXIS 867, Counsel Stack Legal Research, https://law.counselstack.com/opinion/odyssey-contracting-corp-v-jf-white-contracting-co-massappct-2017.