Odom v. Ohio Dept. of Transp.

2009 Ohio 7193
CourtOhio Court of Claims
DecidedDecember 23, 2009
Docket2009-07130-AD
StatusPublished

This text of 2009 Ohio 7193 (Odom v. Ohio Dept. of Transp.) is published on Counsel Stack Legal Research, covering Ohio Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Odom v. Ohio Dept. of Transp., 2009 Ohio 7193 (Ohio Super. Ct. 2009).

Opinion

[Cite as Odom v. Ohio Dept. of Transp., 2009-Ohio-7193.]

Court of Claims of Ohio The Ohio Judicial Center 65 South Front Street, Third Floor Columbus, OH 43215 614.387.9800 or 1.800.824.8263 www.cco.state.oh.us

THAINE P. ODOM

Plaintiff

v.

OHIO DEPARTMENT OF TRANSPORTATION

Defendant

Case No. 2009-07130-AD

Clerk Miles C. Durfey

MEMORANDUM DECISION

{¶ 1} On July 20, 2009, at approximately 3:30 p.m., plaintiff, Thaine P. Odom, was traveling north on Interstate 75 “just after the Monroe exit” in Warren County, when his automobile struck a “deep 3-5" hole in the road” causing rim damage to the vehicle. Plaintiff implied that the damage to his car was proximately caused by negligence on the part of defendant, Department of Transportation (ODOT), in failing to maintain the roadway free of defects such as potholes. Plaintiff filed this complaint seeking to recover damages in the amount of $271.15, the cost of a replacement rim. The $25.00 filing fee was paid and plaintiff requested reimbursement of that cost along with his damage claim. {¶ 2} Defendant explained that the roadway area where plaintiff’s incident occurred was within the limits of a working construction project under the control of ODOT contractor, John R. Jurgensen Company (Jurgensen). Defendant related that the particular construction project “dealt with grading, draining, paving with asphalt concrete on I-75, interchange construction of SR 122 and bridge replacements at several locations in Warren County.” According to defendant, the construction project limits “corresponds to state mileposts 32.10 to 40.50" on Interstate 75 and plaintiff’s damage incident occurred “between mileposts 39.20 to 39.45 which is within the project limits.” Defendant asserted that this particular construction project was under the control of Jurgensen and consequently ODOT had no responsibility for any damage or mishap on the roadway within the construction project limits. Defendant argued that Jurgensen, by contractual agreement, was responsible for maintaining the roadway within the construction zone. Therefore, ODOT contended that Jurgensen is the proper party defendant in this action. Defendant implied that all duties such as the duty to inspect, the duty to warn, the duty to maintain, and the duty to repair defects were delegated when an independent contractor takes control over a particular section of roadway. Furthermore, defendant contended that plaintiff failed to introduce sufficient evidence to prove his damage was proximately caused by roadway conditions created by ODOT or its contractors. All construction work was to be performed in accordance with ODOT requirements and specifications and subject to ODOT approval. Also evidence has been submitted to establish that ODOT personnel were present on site conducting inspection activities. {¶ 3} For plaintiff to prevail on a claim of negligence, he must prove, by a preponderance of the evidence, that defendant owed him a duty, that it breached that duty, and that the breach proximately caused his injuries. Armstrong v. Best Buy Company, Inc., 99 Ohio St. 3d 79, 2003-Ohio-2573,¶8 citing Menifee v. Ohio Welding Products, Inc. (1984), 15 Ohio St. 3d 75, 77, 15 OBR 179, 472 N.E. 2d 707. Plaintiff has the burden of proving, by a preponderance of the evidence, that he suffered a loss and that this loss was proximately caused by defendant’s negligence. Barnum v. Ohio State University (1977), 76-0368-AD. However, “[i]t is the duty of a party on whom the burden of proof rests to produce evidence which furnishes a reasonable basis for sustaining his claim. If the evidence so produced furnishes only a basis for a choice among different possibilities as to any issue in the case, he fails to sustain such burden.” Paragraph three of the syllabus in Steven v. Indus. Comm. (1945), 145 Ohio St. 198, 30 O.O. 415, 61 N.E. 2d 198, approved and followed. This court, as trier of fact, determines questions of proximate causation. Shinaver v. Szymanski (1984), 14 Ohio St. 3d 51, 14 OBR 446, 471 N.E. 2d 477. {¶ 4} Defendant had the duty to maintain its highways in a reasonably safe condition for the motoring public. Knickel v. Ohio Department of Transportation (1976), 49 Ohio App. 2d 335, 3 O.O. 3d 413, 361 N.E. 2d 486. However, defendant is not an insurer of the safety of its highways. See Kniskern v. Township of Somerford (1996), 112 Ohio App. 3d 189, 678 N.E. 2d 273; Rhodus v. Ohio Dept. of Transp. (1990), 67 Ohio App. 3d 723, 588 N.E. 2d 864. The duty of ODOT to maintain the roadway in a safe drivable condition is not delegable to an independent contractor involved in roadway construction. ODOT may bear liability for the negligent acts of an independent contractor charged with roadway construction. Cowell v. Ohio Department of Transportation, Ct. of Cl. No. 2003-09343-AD, jud, 2004-Ohio-151. Despite defendant’s contentions that ODOT did not owe any duty in regard to the construction project, defendant was charged with duties to inspect the construction site and correct any known deficiencies in connection with the particular construction work. see Roadway Express, Inc. v. Ohio Dept. of Transp. (June 28, 2001), Franklin App. 00AP-1119. {¶ 5} Alternatively, defendant denied that neither ODOT nor Jurgensen had any notice of the particular pothole prior to plaintiff’s property damage event. Defendant pointed out that ODOT records “indicate no calls or complaints were received regarding the pothole in question prior to (plaintiff’s) incident. Evidence from another claim, 2009- 07288-AD, establishes the particular damage-causing pothole was present on the roadway at 11:00 a.m. on July 19, 2009. Defendant argued that plaintiff has failed to produce any evidence to prove the pothole that his car struck was attributable to any conduct on either the part of ODOT or Jurgensen. Defendant submitted a letter from Jurgensen Project Manager, Jason M. Mudd, who recalled an ODOT representative notified Jurgensen of a pothole at milepost 38.0 on Interstate 75 on July 22, 2009. This pothole was subsequently repaired according to Jurgensen records. {¶ 6} In order to find liability for a damage claim occurring in a construction area, the court must look at the totality of the circumstances to determine whether ODOT acted in a manner to render the highway free from an unreasonable risk of harm for the traveling public. Feichtner v. Ohio Dept. of Transp. (1995), 114 Ohio App. 3d 346, 683 N.E. 2d 112. In fact, the duty to render the highway free from an unreasonable risk of harm is the precise duty owed by ODOT to the traveling public under both normal traffic and during highway construction projects. See e.g. White v. Ohio Dept. of Transp. (1990), 56 Ohio St. 3d 39, 42, 564 N.E. 2d 462. {¶ 7} In order to prove a breach of the duty to maintain the highways, plaintiff must prove, by a preponderance of the evidence, that defendant had actual or constructive notice of the precise condition or defect alleged to have caused the accident. McClellan v. ODOT (1986), 34 Ohio App. 3d 247, 517 N.E. 2d 1388. Defendant is only liable for roadway conditions of which it has notice but fails to reasonably correct. Bussard v. Dept. of Transp. (1986), 31 Ohio Misc. 2d 1, 31 OBR 64, 507 N.E. 2d 1179. {¶ 8} Generally, in order to recover in a suit involving damage proximately caused by roadway conditions including potholes, plaintiff must prove that either: 1) defendant had actual or constructive notice of the pothole and failed to respond in a reasonable time or responded in a negligent manner, or 2) that defendant, in a general sense, maintains its highways negligently. Denis v. Department of Transportation (1976), 75-0287-AD. There is no evidence that defendant had actual notice of the pothole condition. Therefore, in order to recover plaintiff must produce evidence to prove constructive notice of the defect or negligent maintenance.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Toth, Unpublished Decision (5-3-2006)
2006 Ohio 2173 (Ohio Court of Appeals, 2006)
Knickel v. Department of Transportation
361 N.E.2d 486 (Ohio Court of Appeals, 1976)
McClellan v. Ohio Department of Transportation
517 N.E.2d 1388 (Ohio Court of Appeals, 1986)
Kniskern v. Township of Somerford
678 N.E.2d 273 (Ohio Court of Appeals, 1996)
Rhodus v. Ohio Department of Transportation
588 N.E.2d 864 (Ohio Court of Appeals, 1990)
Feichtner v. Ohio Department of Transportation
683 N.E.2d 112 (Ohio Court of Appeals, 1995)
In Re Estate of Fahle
105 N.E.2d 429 (Ohio Court of Appeals, 1950)
Stevens v. Industrial Commission
61 N.E.2d 198 (Ohio Supreme Court, 1945)
Bussard v. Ohio Department of Transportation
507 N.E.2d 1179 (Ohio Court of Claims, 1986)
Shinaver v. Szymanski
471 N.E.2d 477 (Ohio Supreme Court, 1984)
Menifee v. Ohio Welding Products, Inc.
472 N.E.2d 707 (Ohio Supreme Court, 1984)
White v. Ohio Department of Transportation
564 N.E.2d 462 (Ohio Supreme Court, 1990)
Armstrong v. Best Buy Co.
788 N.E.2d 1088 (Ohio Supreme Court, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
2009 Ohio 7193, Counsel Stack Legal Research, https://law.counselstack.com/opinion/odom-v-ohio-dept-of-transp-ohioctcl-2009.