October Twenty-Four, Inc. v. Planning & Zoning Commission

646 A.2d 926, 35 Conn. App. 599, 1994 Conn. App. LEXIS 319
CourtConnecticut Appellate Court
DecidedAugust 23, 1994
Docket12655
StatusPublished
Cited by13 cases

This text of 646 A.2d 926 (October Twenty-Four, Inc. v. Planning & Zoning Commission) is published on Counsel Stack Legal Research, covering Connecticut Appellate Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
October Twenty-Four, Inc. v. Planning & Zoning Commission, 646 A.2d 926, 35 Conn. App. 599, 1994 Conn. App. LEXIS 319 (Colo. Ct. App. 1994).

Opinion

Foti, J.

The plaintiff appeals from the judgment rendered in favor of the defendants, the planning and zoning commission of the town of Plainville (commission) and Tomasso Brothers, Inc. (Tomasso). Tomasso filed an application with the commission for site plan approval of an office park. The commission granted the site plan application and the plaintiff, October Twenty-Four, Inc., appealed to the Superior Court. Tomasso moved to dismiss the appeal, and the Superior Court granted the motion. On appeal, the plaintiff claims that the trial court improperly (1) decided that General Statutes § 8-7d (b), rather than General Statutes § 8-7d (a), governed the commission’s consideration of Tomasso’s site plan application, (2) failed to find waiver or estoppel on the part of Tomasso, and (3) failed to consider the constitutionality of General Statutes § 8-7d. We affirm the judgment of the trial court.

The following facts are relevant to this appeal. On December 26,1991, Tomasso filed an application with the commission for site plan approval of an office park in the technical park zone of Plainville. The application was officially received by the commission at its next regularly scheduled meeting on January 14, 1992. On February 11,1992, the commission voted to hold a public hearing on Tomasso’s site plan application. The hearing began on February 25,1992, and was continued to March 10 and 24,1992. The commission approved the site plan on May 12,1992. Notice of the approval was published in a newspaper.

The plaintiff, which owns property adjacent to Tomasso’s property, appealed from the commission’s decision to the Superior Court. Tomasso moved to dismiss the appeal on the ground that its site plan was approved by operation of law on March 20, 1992. It argued that, because the commission failed to act within sixty-five days of the receipt of the application, the plaintiff’s appeal was rendered untimely and moot. The [601]*601trial judge initially denied Tomasso’s motion to dismiss and deferred ruling on the issue of automatic approval. The plaintiff’s appeal was reviewed at a hearing on April 29, 1993, and the trial court granted Tomasso’s motion to dismiss pursuant to General Statutes § 8-8 (j).1 The court ruled that (1) the commission had violated the sixty-five day time for decision imposed by General Statutes § 8-7d (b), resulting in the automatic approval of Tomasso’s application on March 20, 1992, and (2) there was no evidence in the record to support a finding of waiver or estoppel by Tomasso. The plaintiff now appeals that judgment of dismissal.

I

The first issue raised by the plaintiff is whether subsection (a) or (b) of General Statutes § 8-7d governs the time constraints for decision on a site plan application where no public hearing is required but the commission decides to hold a discretionary hearing. Both this court and our Supreme Court have held that § 8-7d (b) governs the time constraints for decisions on site plan applications where no public hearing is required. SSM Associates Ltd. Partnership v. Plan & Zoning Commission, 211 Conn. 331, 559 A.2d 196 (1989); Carr v. Woolwich, 7 Conn. App. 684, 510 A.2d 1358, cert. denied, 201 Conn. 804, 513 A.2d 698 (1986), overruled on other grounds, 225 Conn. 432, 632 A.2d 1007 (1993); see footnote 2.

General Statutes § 8-7d, generally, sets mandatory time limits on the review of site plan applications. Section 8-7d (a) sets the time constraints for the render[602]*602ing of decisions on zoning applications in which a public hearing is required.2 Section 8-7d (b) provides that “[wjhenever the approval of a site plan is the only-requirement to be met or remaining to be met under the zoning regulations for a proposed building, use or structure, a decision on an application for approval of such site plan shall be rendered within sixty-five days after receipt of such site plan.” Local zoning regulations determine if a public hearing is required for review of a particular application. If no public hearing is required, the time constraints of subsection (b), rather than those of subsection (a), control. Carr v. Woolwich, supra, 7 Conn. App. 699.

In this case, the property that is the subject of Tomasso’s site plan application is located in a technical park zone. The Plainville zoning regulations do not mandate public hearings for site plan applications in a technical park zone. The zoning regulations provide in relevant part: “All buildings and uses of land within a technical park zone shall be subject to the site plan provisions and guides to the Commission of Article 6. The Commission may hold a public hearing on the proposed site plan ... if, in its judgment, the nature of the site plan is such that the public should have an opportunity to be heard.” Plainville Zoning Regulations §551. Since no public hearing was required under the Plainville zoning regulations, General Statutes § 8-7d (b) governs the time constraints for decision by the commission on Tomasso’s site plan application.

[603]*603The plaintiff relies on the fact that although the Plain-ville zoning regulations do not mandate public hearings for site plan applications in a technical park zone, the commission has the authority, under § 551 of the regulations, to hold a public hearing if it deems necessary. The commission did hold such a hearing on Tomasso’s site plan application, and the plaintiff argues that once the commission voted to hold this hearing it was, in effect, required. Since it was required, the plaintiff argues that the applicable statute would be § 8-7d (a). Because the commission acted within the time constraints required by § 8-7d (a), there could be no automatic approval of Tomasso’s application. We are not persuaded by this argument.

According to the plain language of § 8-7d (a), it applies only to situations where a public hearing “is required.” The statute makes no reference to situations where public hearings are not required but are held at the discretion of the zoning commission. “We are constrained to read a statute as written . . . and we may not read into clearly expressed legislation provisions which do not find expression in its words. . . .’’(Citations omitted; internal quotation marks omitted.) Ghent v. Planning Commission, 219 Conn. 511, 515, 594 A.2d 5 (1991). Under the Plainville zoning regulations, no public hearing was required for review of Tomasso’s site plan application. The fact that the commission decided to hold a discretionary hearing did not transform a permissive regulation into a mandatory one.

Because no public hearing was required, the time constraints of General Statutes § 8-7d (b), and not § 8-7d (a), applied to the commission’s actions. The trial court correctly ruled that the commission was required to render a decision on the application within sixty-five days of its receipt on January 14, 1992. The deadline for rendering a decision was March 20, 1992. A decision was not rendered until May 12,1992. General Stat[604]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Thomas J. White v. City of Bridgeport
675 F. App'x 86 (Second Circuit, 2017)
Kauai Springs, Inc. v. Planning Commission
312 P.3d 283 (Hawaii Intermediate Court of Appeals, 2013)
R & R Pool & Patio, Inc. v. Zoning Board of Appeals
925 A.2d 417 (Connecticut Appellate Court, 2007)
Clifford v. PLAN. AND ZON. COM'N OF ANSONIA
908 A.2d 1049 (Supreme Court of Connecticut, 2006)
Kelo v. City of New London, No. 557299 (Mar. 13, 2002)
2002 Conn. Super. Ct. 3063 (Connecticut Superior Court, 2002)
Frumento v. City of West Haven, No. 417928 (Nov. 17, 2000)
2000 Conn. Super. Ct. 14177 (Connecticut Superior Court, 2000)
Trustees v. Historic Dist. Comm., No. Cv 980169262 (Sep. 18, 2000)
2000 Conn. Super. Ct. 11526 (Connecticut Superior Court, 2000)
Bolotin v. Historic Dist. Comm., Westport, No. Cv 98 0169262 (Sep. 18, 2000)
2000 Conn. Super. Ct. 11359 (Connecticut Superior Court, 2000)
Center Shops of East Granby, Inc. v. Planning & Zoning Commission
727 A.2d 807 (Connecticut Appellate Court, 1999)
Center Shops v. Planning and Zoning, No. Cv-97-569643-S (Nov. 17, 1997)
1997 Conn. Super. Ct. 11310 (Connecticut Superior Court, 1997)
Scaringe v. Planning Commission, No. Cv 371937 (Jun. 6, 1996)
1996 Conn. Super. Ct. 4697 (Connecticut Superior Court, 1996)
Newington Ch. H. v. Comm. on H. H. Care, No. Cv930531494s (Feb. 10, 1995)
1995 Conn. Super. Ct. 1372 (Connecticut Superior Court, 1995)
State v. Cook
653 A.2d 829 (Connecticut Appellate Court, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
646 A.2d 926, 35 Conn. App. 599, 1994 Conn. App. LEXIS 319, Counsel Stack Legal Research, https://law.counselstack.com/opinion/october-twenty-four-inc-v-planning-zoning-commission-connappct-1994.