Occidental Chemical Corp. v. OHM Remediation Services Corp.

175 F.R.D. 431, 45 ERC (BNA) 1821, 1997 U.S. Dist. LEXIS 13457, 1997 WL 557563
District Court, W.D. New York·Decided June 25, 1997·No. No. 94-CV-959S(H)·Published·Cited by 20 cases

Opinion

DECISION AND ORDER

HECKMAN, United States Magistrate Judge.

This case has been referred to the undersigned by Hon. William M. Skretny for all pretrial matters, including the hearing and disposition of non-dispositive motions, in accordance with 28 U.S.C. § 636(b)(1)(A). Defendant has moved to compel the production of documents as to which plaintiff has assert[433] ed attorney-client privilege and/or work product protection. What follows is this court’s ruling on certain issues which the parties agree will significantly narrow the discovery dispute addressed by defendant’s pending motion.

BACKGROUND

As discussed in this court’s prior decisions, the original complaint in this action was filed on December 30,1994, and an amended complaint was filed on March 3, 1995. Plaintiff seeks damages for defendant’s alleged breach of a written contract for environmental cleanup at the Little Niagara River inlet to the Durez Inactive Hazardous Waste Disposal Site (the “Durez Inlet”). Jurisdiction is based on diversity of citizenship. According to the complaint, the cleanup was mandated by a partial consent judgment approved by Hon. John T. Curtin in State of New York v. Occidental Petroleum, 83-CV-552C (W.D.N.Y. (Third Consent Judgment and Order, dated October 21, 1993)). Plaintiff alleges that on October 6, 1993, the parties executed a written contract which provided that defendant would complete its work on the remediation project by May 27, 1994. Plaintiff alleges that defendant’s performance of the work was late and incomplete, causing plaintiff to incur damages in the amount of over $8.8 million.

On April 6,1995, defendant filed its answer to the amended complaint and asserted several counterclaims. The counterclaims seeks over $9 million in damages for breach of contract and warranty, based on the claim that plaintiff misrepresented or failed to disclose material conditions, characteristics and specifications of the work to be performed at the Durez Inlet (Item 6). On July 18, 1995, plaintiff filed its reply to defendant’s counterclaims (Item 13). The parties have engaged in extensive discovery during the course of this litigation, and the court has issued several rulings and amended scheduling orders.

The current discovery dispute involves defendant’s request for production of documents which was served on July 24,1995. In response to this request, plaintiff produced numerous documents and withheld numerous others as to which it asserted attorney-client privilege or work product protection. After the exchange of privilege and objection logs, and after meetings between counsel, oral argument of defendant’s motion to compel was heard by the undersigned on May 23, May 30, and June 11, 1997. The parties agree that the current dispute will be significantly narrowed by a decision from this court on the following issues:

1. Whether documents sent to or prepared by Rust Environment and Infrastructure, Inc. (“Rust”) (formerly, Dunn Geoscience Corp. (“Dunn”)) during the performance of its duties as plaintiffs consulting engineer for the Durez Inlet project (ie., documents dated from approximately late 1992 through April, 1995; see Item 94), are protected from disclosure' as material prepared in anticipation of litigation under Rule 26(b)(3) of the Federal Rules of Civil Procedure.
2. Whether Rust documents generated during the performance of Rust’s duties as plaintiffs engineering consultant for the design of the Durez site remediation plan (ie., documents dated from approximately July, 1990 through June, 1992; see Item 86, Ex. A), are protected from disclosure by the attorney-client privilege.
3. The date on which plaintiff reasonably anticipated that litigation with defendant over the Durez Inlet project was imminent.

DISCUSSION

I. Documents Pertaining to Rust’s Work as Consultant During the Durez Inlet Project: Material Prepared in Anticipation of Litigation.

According to plaintiffs counsel, Rust was originally retained under an agreement with plaintiffs former outside counsel, White-man, Osterman & Hanna, to be the engineering consultant for design and development of the cleanup of the Durez site, including the Durez Inlet project. Rust was subsequently retained by plaintiff, under a separate agreement, to be the engineering consultant for the actual performance of the work on the [434] Durez Inlet project. Neither retainer agreement has been provided to the court, and the motion papers do not otherwise specify the scope of Rust’s duties as consultant on either the design phase or the project phase, or the intent of the parties to those agreements as to the confidentiality of the information exchanged or documents produced.

Plaintiff claims that documents dated from approximately late 1992 through April, 1995 pertaining to Rust’s performance of its duties as engineering consultant for the Durez Inlet project phase are protected from disclosure as material prepared in anticipation of litigation under Fed.R.Civ.P. 26(b)(3). That rule provides, in relevant part:

[A] party may obtain discovery of documents and tangible things otherwise discoverable ... and prepared in anticipation of litigation or for trial by or for another party or by or for that other party’s representative (including the other party’s attorney, consultant, surety, indemnitor, insurer, or agent) only upon a showing that the party seeking discovery has substantial need of the materials in the preparation of the party’s case and that the party is unable without undue hardship to obtain the substantial equivalent of the materials by other means.

Fed.R.Civ.P. 26(b)(3). The rule derives from the “attorney work product” doctrine, as explained in Hickman v. Taylor, 329 U.S. 495, 67 S.Ct. 385, 91 L.Ed. 451 (1947), which immunizes from discovery certain material gathered by attorneys for the purposes of litigation.

In determining whether this qualified protection applies, the initial inquiry is “whether, in light of the nature of the documents and the factual situation in a particular case, the document can be fairly said to have been prepared or obtained because of the prospect of litigation.” Litton Industries, Inc. v. Lehman Bros. Kuhn Loeb Inc., 125 F.R.D. 51,54 (S.D.N.Y.1989). The protection from disclosure offered by Rule 26(b)(3) “requires a more immediate showing than the remote possibility of litigation.” Garfinkle v. Arcata Nat. Corp., 64 F.R.D. 688, 690 (S.D.N.Y.1974). “Litigation must at least be a real possibility at the time of preparation or, in other words, the document must be prepared with an eye to some specific litigation.” James Julian, Inc. v. Raytheon Co., 93 F.R.D. 138, 143 (D.Del.1982).

Free access — add to your briefcase to read the full text and ask questions with AI

Occidental Chemical Corp. v. OHM Remediation Services Corp., 175 F.R.D. 431, 45 ERC (BNA) 1821, 1997 U.S. Dist. LEXIS 13457, 1997 WL 557563 (W.D.N.Y. 1997).

175 F.R.D. 431 (Occidental Chemical Corp. v. OHM Remediation Services Corp.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Scott v. Chipotle Mexican Grill, Inc.
94 F. Supp. 3d 585 (S.D. New York, 2015)
Integramed America, Inc. v. Patton
298 F.R.D. 326 (D. South Carolina, 2014)
Clinical Technology, Inc. v. NeuroTherm, Inc.
2013 Ohio 3739 (Ohio Court of Appeals, 2013)
Abbo-Bradley v. City of Niagara Falls
293 F.R.D. 401 (W.D. New York, 2013)
Santa Fe Pacific Gold Corp. v. United Nuclear Corp.
2007 NMCA 133 (New Mexico Court of Appeals, 2007)
AAB Joint Venture v. United States
75 Fed. Cl. 432 (Federal Claims, 2007)
Pacific Gas & Electric Co. v. United States
69 Fed. Cl. 784 (Federal Claims, 2006)
Hertzberg v. Veneman
273 F. Supp. 2d 67 (District of Columbia, 2003)
Perfection Corp. v. Travelers Casualty & Surety
790 N.E.2d 817 (Ohio Court of Appeals, 2003)
Viacom, Inc. v. Sumitomo Corp.
200 F.R.D. 213 (S.D. New York, 2001)
Gorman v. Polar Electro, Inc.
137 F. Supp. 2d 223 (E.D. New York, 2001)
Harris v. Provident Life & Accident Insurance
198 F.R.D. 26 (N.D. New York, 2000)
Energy Capital Corp. v. United States
45 Fed. Cl. 481 (Federal Claims, 2000)