Oatley v. Duprey

44 N.E.2d 675, 312 Mass. 281, 1942 Mass. LEXIS 828
CourtMassachusetts Supreme Judicial Court
DecidedOctober 28, 1942
StatusPublished
Cited by7 cases

This text of 44 N.E.2d 675 (Oatley v. Duprey) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Oatley v. Duprey, 44 N.E.2d 675, 312 Mass. 281, 1942 Mass. LEXIS 828 (Mass. 1942).

Opinion

Cox, J.

This action of contract was referred to an auditor whose findings of fact were to be final. We are concerned only with the third count of the plaintiff’s declaration in which he alleges, in substance, that at the request of the defendant he acted as builder and contractor in the erection of a building, and that he is entitled to the fair value of the services rendered. The auditor found that he was entitled to recover on this count, but that he had ■failed to prove the allegations in counts 1 and 2 of the declaration to the effect that the compensation for his services had been definitely agreed upon. The trial judge denied the defendant’s motion for judgment, and allowed that of the plaintiff. The defendant appealed.

The order denying the defendant’s motion for judgment was not appealable. It was not an “order decisive of the case.” Lawrence v. Old Silver Beach, Inc. 303 Mass. 377, 378. The report of the auditor, whose findings of fact were to be final, is equivalent to a case stated, and the order for judgment for the plaintiff upon it is properly here on appeal. It was the duty of the judge to order the judgment required by the facts found. In addition to allowing the plaintiff’s motion for judgment, the judge found for the plaintiff. See Pittsley v. Allen, 297 Mass. 83, 85. The evidence is not reported, and it is for this court to take the report on its face in accordance with the well established rule. Lewis v. Conrad & Co. Inc. 311 Mass. 541, 543.

The auditor found that the defendant asked the plaintiff if he would construct a building for him similar to one he had just built. The plaintiff submitted a plan and estimate of cost which were rejected by the defendant, who then sought bids from other contractors, none of which was accepted. The defendant then submitted to the plaintiff a plan and specifications drawn by architects. . They went over'the matter and “found” that if the details of the plan [283]*283and specifications were carried out in the entirety, the cost would be about $20,000. The plaintiff was asked if he could reduce this cost and replied that he thought he could save $5,000. The defendant then said, “go ahead with it,” and authorized the plaintiff to proceed at once with the work. The parties had a conversation as to what the charges for the plaintiff’s services “should” be. The defendant suggested that the work be started on a day basis, and to this the plaintiff agreed. The plaintiff “explained” and outlined that day work in this case meant a weekly wage of $45 plus ten per cent of the total cost of all work and construction supervised by him. During this conversation the plaintiff submitted another figure for all construction work, which the defendant rejected. He agreed, however, to pay a weekly wage of $45 to the plaintiff as “supervisor and foreman,” with the understanding that no foreman should be employed on the job. The plaintiff endeavored to procure a written contract from the defendant embodying the weekly wage of $45, together with the “cost plus 10% proposition.” But the evidence did not “reveal” that the parties entered into any oral or written agreement on the “cost plus 10% part of the proposition or that the defendant ever agreed or assented to the cost plus 10% phase of the transaction.”

The plaintiff proceeded “as authorized” by the defendant with the work of construction, hired all help, purchased materials (which were paid for by the defendant), complied generally with the architects’ plan and specifications and acted in a supervisory capacity in all details of the work. He advised, used his skill for the benefit of the defendant, and accompanied him in the purchase of materials and sought advantageous prices. He also kept a record of costs of all materials and labor, and submitted accurate accounts that were acceptable and satisfactory to the defendant, who requested and required the plaintiff to devote his time exclusively to the construction of the building, to use his own judgment and discretion in procuring and using materials, new and second hand, when adaptable and advisable, with the view of expediting construction and lowering costs. [284]*284The plaintiff devoted all his time to the construction work, the cost of which amounted to approximately $14,400. He had nothing to do with the installation of the electric wiring, plumbing, grading or the interior finishing, and the report does not disclose the cost of these items. The plaintiff received a weekly wage of $45 “for services rendered” during the period of construction, and these payments were for his services “as supervisor and foreman.” He carried on and completed the work in accordance with the plan and specifications, devoted his whole time to arranging, planning and supervising the work, at no time receiving any suggestions or instructions from the architects, and completed the building in workmanlike manner, within a reasonable time, fully acceptable and satisfactory to the defendant.

Other findings are that the knowledge and skill displayed by the plaintiff in the “manner of construction and completion” of the building enhanced the defendant’s interest to an extent that entitles the plaintiff to further reasonable compensation, in addition to the $45 a week, and that the plaintiff has not been fully compensated for the fair value of the services rendered at the “request, knowledge and consent” of the defendant; that the services that were rendered by the plaintiff “exceeded” the duties of supervisor and foreman, for which he received $45 per week, and, upon evidence submitted as to a reasonable and fair compensation in “such cases and particularly in the instant case,” that the plaintiff was entitled to three and one half per cent of the total cost of construction.

The evidence is not reported, and the subsidiary findings must stand. We are of opinion that in so far as any of the auditor’s conclusions of fact are reachable by inference from those subsidiary findings, if at all, they must also stand. See Lewis v. Conrad & Co. Inc. 311 Mass. 541, 543.

Although the defendant authorized the plaintiff to proceed at once with the work when the latter told him that he thought he could save $5,000, the only definite agreement for compensation that was made was that the plaintiff was to receive a weekly wage of $45 for acting as super[285]*285visor and foreman. The plaintiff was unable to secure a written contract from the defendant that would embrace further compensation, and although there were “considerable discussions, talk, explanation and suggestions between the plaintiff and defendant” relative to the plaintiff’s receiving the cost plus ten per cent “as an additional compensation for services,” nothing ever resulted except that the plaintiff went on with the work and rendered services in addition to those of “supervisor and foreman.”

We think it sufficiently appears that the plaintiff did render additional services in such circumstances that he is entitled to recover for their value. The defendant contends that everything that the plaintiff did was comprehended within the definite agreement between the parties whereby the plaintiff was to act as supervisor and foreman. Facts otherwise are found, however. We think this is a case where the plaintiff rendered services of value to the defendant for the payment of which there was an express agreement only in part. When the plaintiff told the defendant he thought he could save $5,000 in the construction, he was told to “go ahead with it” and authorized to proceed at once with the work.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McQueen v. True Partners Consulting, LLC
28 Mass. L. Rptr. 411 (Massachusetts Superior Court, 2011)
Cape Painting & Carpentry, Inc. v. Maher
2009 Mass. App. Div. 22 (Mass. Dist. Ct., App. Div., 2009)
Chas. T. Main, Inc. v. Massachusetts Turnpike Authority
196 N.E.2d 821 (Massachusetts Supreme Judicial Court, 1964)
Kent v. Pallatroni
147 N.E.2d 176 (Massachusetts Supreme Judicial Court, 1958)
Glazer v. Lerman
116 N.E.2d 569 (Massachusetts Supreme Judicial Court, 1953)
Medlinsky v. Premium Cut Beef Co.
57 N.E.2d 31 (Massachusetts Supreme Judicial Court, 1944)
Weiss v. Balaban
53 N.E.2d 83 (Massachusetts Supreme Judicial Court, 1944)

Cite This Page — Counsel Stack

Bluebook (online)
44 N.E.2d 675, 312 Mass. 281, 1942 Mass. LEXIS 828, Counsel Stack Legal Research, https://law.counselstack.com/opinion/oatley-v-duprey-mass-1942.