O. F. Mehurin & Son v. Stone

37 Ohio St. (N.S.) 49
CourtOhio Supreme Court
DecidedJanuary 15, 1881
StatusPublished

This text of 37 Ohio St. (N.S.) 49 (O. F. Mehurin & Son v. Stone) is published on Counsel Stack Legal Research, covering Ohio Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
O. F. Mehurin & Son v. Stone, 37 Ohio St. (N.S.) 49 (Ohio 1881).

Opinion

Boynton, Oh. J.

If from the conceded facts, the verdict and judgment ought to have been for the defendant, it is immaterial whether the instructions to the jury were correct or erroneous. Barth v. Clise, 12 Wall. 401. The contract required the excavation for the foundation, to be of- the depth of two feet under the whole vault, filled with lime or other good stone well cemented together so as to make a good substantial foundation for the vault.” This, we think, is the plain meaning of'the language as understood by the parties. That such excavation, and the foundation thus provided for, were not made, was conceded at the trial. It also appeared that the spaee in the front wall between the block of marble which was to bear the inscription, and the roof of the vault was filled with [55]*55four pieces of marble. The contract stipulated for but one. Here was a very material deviation from tbe terms of the agreement, and a deviation of such a character as to show a substantial non-compliance by the plaintiffs with the stipulation of the contract. Had these facts appeared on the face of the pe-' tition the case would have been so fatally defective as to have entitled the defendant to judgment on the pleadings:. Being admitted at the trial the same result must follow. The performance by the plaintiffs of the stipulations on their part is a condition precedent to payment by the defendant. The first installment was not to be paid until the vault was completed. Substantial completion is indispensable to the right to call upon the defendant to perform the stipulation to pay. No recovery can be had upon a quantum meruit, because, where the contract is express, none can be implied relating to the same subject matter. The principle that conditions precedent to the right to compensation for labor done, or materials furnished, must be substantially performed, in order to put the other party in default, is of universal application, admitting of no exceptions. But technical or unimportant omissions or deviations will not defeat recovery. In the case of Goldsmith v. Hand, 26 Ohio St. 101, the plaintiff’s recovery was sustained on the groundthat the work had been substantially completed according to the terms of the contract.

The judge in his opinion employs language which would lead to the inference that a different rule from the one above stated prevails in regard to building contracts, as respects the performance by the builder; and he cites in support of that view, Hayward v. Leonard, 7 Pick. 181. This case, however, in view of its peculiar facts, is not understood by the supreme judicial court of Massachusetts, as laying down any rule peculiar to building contracts. In Olmstead v. Beale, 19 Pick. 528, after stating the general rule to be, that, where under the contract, performance by one party is to precede payment by the other, no recovery could be had either upon the contract, or upon an implied assumpsit, where the precedent conditions were not performed, the court say, The cases of Hayward v Leonard, 7 Pick. 181, and Smith v. First Congr. Meeting-house [56]*56in Lowell, 8 Pick. 178, are neither incompatible with, nor exceptions to the rule. It will be found in these and other similar cases, that there was an express or implied assent to the deviations from the contract, or a substantial performance of it. The equitable principle which governs them, and which itself is of recent introduction, only extends to unimportant, accidental and unintentional deviations, which, from the differences of opinion, that so often exist, in relation to the exact requisition in the details of a special contract, had become indispensable to the administration of justice in such eases. Rut where there is an important and voluntary deviation or omission from the contract, the doctrine of Faxon v. Mansfield, 2 Mass. 147, will apply, and the contractor can have no remedy for the materials furnished and the services performed.” Indeed, it was said in Hayward v. Leonard, that, “ when we speak of the law allowing the party to recover on- a quantum meruit, or quantum valebant, where there is a special contract, we mean to confine ourselves to cases in which there is an honest intention to go by the contract, and a substantive execution of it, but some comparatively slight deviations as to some particulars provided for.” The right of the contractor to recover, upon failure to perform, in a case where performance was a condition of payment, by making a compensatory allowance for the loss to the owner resulting from non-performance by the contractor, was denied by the court of appeals of New York, in the very well considered case of Smith v. Brady, 17 N. Y. 173. It was there held that, “when, in a contract for the erection of a building on the land of another, performance is to precede payment and is a condition thereof, the builder having substantially failed to perform on his part, can recover nothing for his labor and materials, notwithstanding the owner has chosen to occupy and enjoy the erection.”

Comstock, J., in announcing the judgment of the court, said: “ The right to recover in such case has never been referred to any doctrine peculiar to such contract. On the contrary, if wo look at the adjudged cases, we shall find that the right, whenever asserted by judicial tribunals, has been supposed to result from a general doctrine applicable as well to other [57]*57contracts,” . . . and that “ there can be no injustice in imputing to the contractor a knowledge of'what his contract requires, nor in holding him to substantial performance.” . . . “ If he fails to perform when the requirement is plain, and when he can perform if he will, lie has no right to call upon the courts to make a new contract for him; nor ought he to complain if the law leaves him without a remedy.” The doctrine of this case 'was affirmed in Glacius v. Black, 50 N. Y. 145, where it was said, that although technical, inadvertent and unimportant omissions or defects, would not defeat recovery, substantial performance must be shown.

In the present case the deviation from the contract above mentioned cannot be regarded as slight or non-substantial. The defendant, as' the contract must be construed unaided by any light that extrinsic proof may have thrown around it, stipulated for a solid bed of stone, well cemented together, for a foundation for the vault; and for its front he stipulated for a marble slab or block for the space immediately below the roof, that would materially add to its beauty if not to its strength and durability. To the fulfillment of these stipulations he was clearly entitled. It is quite immaterial whether in the judgment of the plaintiffs or others, the structure, as ¿ompleted, was as durable as the one contracted for or not. It was the right of the defendant to consult his own judgment and taste and to provide for the construction of a vault that would best accord therewith; and having provided by the specifications of his contract for a foundation of a given character, and for one block of marble to fill the gable of the vault, he was entitled to a substantial compliance by the plaintiffs with the terms agreed upon, before he could be called upon to pay any part of the agreed compensation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Barth v. Clise
79 U.S. 400 (Supreme Court, 1871)
Pugh v. McCormick
81 U.S. 361 (Supreme Court, 1872)
Smith v. . Brady
17 N.Y. 173 (New York Court of Appeals, 1858)
Glacius v. . Black
50 N.Y. 145 (New York Court of Appeals, 1872)
Faxon v. Mansfield
2 Mass. 147 (Massachusetts Supreme Judicial Court, 1806)
Harrison v. Bailey
99 Mass. 620 (Massachusetts Supreme Judicial Court, 1868)
Palmer v. Sawyer
114 Mass. 1 (Massachusetts Supreme Judicial Court, 1873)

Cite This Page — Counsel Stack

Bluebook (online)
37 Ohio St. (N.S.) 49, Counsel Stack Legal Research, https://law.counselstack.com/opinion/o-f-mehurin-son-v-stone-ohio-1881.