Nwogu v. United States

497 F. App'x 952
Court of Appeals for the Federal Circuit·Decided October 31, 2012·No. 2011-5015·Unpublished·Cited by 4 cases

Opinion

PER CURIAM.

Peter C. Nwogu, doing business as Environmental Safety Consultants, Inc. (“ESCI”), appeals the United States Court of Federal Claims (“Claims Court”) decision rejecting his various claims related to two government contracts. We affirm-in-part, reverse-in-part, vacate-in-part, and remand.

I.

This case arises from two government contracts the Department of the Navy *890 (“Navy”) awarded ESCI. In the first, Contract No. N62472-90-C-5164 (“Contract I”) awarded on May 23,1991, ESCI was to remove, transport, and dispose of industrial waste sludge from two lagoons at the Naval Air Development Center in Warmin-ster, Pennsylvania. In 1995, the Navy awarded ESCI a second contract, Contract No. N62470-95-C-2399 (“Contract II”), to remove storage tanks at a facility in Yorktown, Virginia.

ESCI had difficulty completing Contract I and, in March 1992, entered into a bilateral agreement with the Navy to terminate the contract. In June of that year, ESCI filed a claim against the Government with the contracting officer (“CO”) for equitable adjustment in the amount of $150,587.95. 1 On February 2, 1994, the CO issued a Contracting Officer’s Final Decision (“COFD”) awarding ESCI $10,869.00. After a series of appeals before the Armed Services Board of Contract Appeals (“ASBCA” or “Board”), ESCI was awarded $93,989.00, plus interest, under Contract I. 2 See Envtl. Safety Consultants, Inc., ASBCA No. 53485, 05-02 BCA ¶33,-073, at 163,937-38. The Government and ESCI both appealed that award to this court in Case No.2006-1180. After the Government indicated to ESCI that the company’s appeal was likely untimely and would be opposed as such, the parties filed joint motions to voluntarily dismiss the appeals, which this court granted on March 29, 2006. Thus, ESCI’s award of $93,989.00, plus interest, under Contract I is final.

ESCI also had difficulty completing Contract II, and on June 6, 1998, a COFD terminated the contract for default. 3 A separate, December 3, 2001 COFD ruled that ESCI owed the Navy $167,691.75 in reprocurement costs and liquidated damages as a result of the default and stated that if the Government did not receive payment within 30 days, it could withhold and setoff the debts owed to ESCI to secure payment. 4 ESCI appealed the COFD’s termination of Contract II for default to the ASBCA and also claimed an equitable adjustment of $334,687.85 for breach of contract, entitlement to additional compensation, and specific performance. After a series of appeals, the ASBCA eventually dismissed with prejudice ESCI’s money claims regarding Contract II in their entirety, see Envtl. Safety Consultants, Inc., ASBCA No. 54615, 07-1 BCA ¶ 33,483, leaving only the “propriety of the termination for default” for the Board to consider, 5 see Envtl. Safety Con *891 sultants, Inc., ASBCA No. 51722, 02-2 BCA ¶ 81,951. On September 28, 2011, the ASBCA converted the Navy’s termination of Contract II for default to one of convenience to the Government. Envtl. Safety Consultants, Inc., ASBCA No. 51722, 11-2 BCA ¶ 84,848. The Government appealed that decision to this court on January 24, 2012, but on June 5, 2012, we granted the parties’ joint motion to voluntarily dismiss the appeal. Thus, it is settled that Contract II was terminated for convenience of the Government, not default.

Setoff has been a consistent issue throughout the disputes over Contracts I and II. For instance, in a June 2002 ASBCA proceeding regarding the amount owed to ESCI under Contract I, the Government notified the Board that it had a claim against ESCI under Contract II. However, the ASBCA determined the set-off issue was not “within the scope of this appeal” and therefore found it was immaterial. Envtl. Safety Consultants, Inc., ASBCA No. 53485, 02-2 BCA ¶ 31,904.

In the Claims Court case now on appeal, filed on April 28, 2009, ESCI attempted to obtain the $93,989.00 judgment, plus interest, 6 owed to it under Contract I and additionally brought a breach of contract claim and a claim for quantum meruit recovery under Contract I. Nwogu v. United States, 94 Fed.Cl. 637, 646 (2010). ESCI also alleged various discriminatory practices including claims under the Fifth (due process and takings), Thirteenth (slavery), and Fourteenth (due process and equal protection) Amendments. Id. ESCI further argued that the Government had breached an oral settlement agreement to pay ESCI the amount owed to it under Contract I in exchange for voluntarily agreeing to dismiss its appeal to this court in 2006. Id. at 655.

The Claims Court issued its decision on August 30, 2010 and dismissed ESCI’s due process, equal protection, slavery, takings, civil rights, and quantum meruit claims for lack of subject matter jurisdiction. Id. at 649-51, 661-62. Additionally, the Claims Court rejected several of ESCI’s claims as time barred. Id. at 652-53. With respect to ESCI’s breach of contract claim, the Claims Court held, among other things, that the Contract Disputes Act’s (“CDA”) 12-month statute of limitations had elapsed, id. at 652 (“The court notes that even if the plaintiffs 12-month CDA clock had begun with the conclusion of ASBCA proceedings on Contract I ... an April 28, 2009, CDA based complaint filed in [the Claims Court] would not have been timely”), and that those issues already decided by the ASBCA were barred under res judicata, id. at 655. 7 In response to ESCI’s argument that the Government breached an oral settlement agreement, the Claims Court found that “[t]he record ... is devoid of support for the sort of agreement [ESCI] conjectures. Nor is such an agreement plausible or credible.” Id. at 657.

The Claims Court also held that it lacked jurisdiction to enforce the ASBCA’s judgment in favor of ESCI under Contract *892 I, id. at 657, and that the Government “has a setoff defense against collection of [ESCI’s] ASBCA adjudicated entitlement for $93,989.00, plus interest, on Contract I,” id. at 659. It is important to note that when the Claims Court issued its opinion, ESCI’s challenge to the COFD that determined Contract II was properly terminated for default was still pending. As a result, the Claims Court reasoned that “the setoff monies owed for reprocurement costs and liquidated damages could be impacted by a decision in favor of [ESCI] ... should the Board overturn the Navy’s termination for default.” Id.

Thus, the Claims Court dismissed “all of [ESCI’s] claims” and held that “[a]t this time, the [Government] has a legitimate right to maintain a setoff defense on the award to [ESCI] on Contract I of $93,989.00, pending resolution of [ASBCA] Case No. 51722 on Contract II....” Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Nwogu v. United States, 497 F. App'x 952 (Fed. Cir. 2012).

497 F. App'x 952 (Nwogu v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Robinson v. United States
Federal Claims, 2017
Inre: Nwogu
570 F. App'x 919 (Federal Circuit, 2014)