Nurmi v. Beardsley

278 N.W. 805, 284 Mich. 165, 1938 Mich. LEXIS 480
CourtMichigan Supreme Court
DecidedApril 4, 1938
DocketDocket No. 47, Calendar No. 39,737.
StatusPublished
Cited by2 cases

This text of 278 N.W. 805 (Nurmi v. Beardsley) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nurmi v. Beardsley, 278 N.W. 805, 284 Mich. 165, 1938 Mich. LEXIS 480 (Mich. 1938).

Opinion

Chandler, J.

On September 5, 1931, the plaintiff entered into a contract with the defendants, husband and wife, who were the owners of a lot in the city of Jackson, to construct thereon a house and garage. The plaintiff, and his wife, who assisted him in the supervision of the work, were experienced builders who had together during a period of six or seven years prior to the date of the contract erected some 20 or 30 residences in the better residential sections of the city of Jackson. The essential parts of the contract provided for the erection for the owners on the lot of a house and garage as per plans and specifications attached to the contract for which plaintiff was to receive the sum of $13,675 payable as follows: 85 per cent, of material and labor on the job at the end of each month was to be paid for on or before the 5th of the following month, the balance in full 10 days after completion. Any changes, alterations or additions to the plans were to be paid for as extras in the amount agreed upon at the time such alterations or additions were ordered. The work *168 was to be performed in a good workmanlike manner and the buildings completed on or before June 1, 1932. The contract provided that if plaintiff did not proceed with necessary promptness that the defendants might cancel the same by 10 days’ written notice, finish the buildings and hold plaintiff liable for any additional cost in so doing; further, that should the defendants at any time make default in the payment of any sums provided for, “then in that case said contractor may, at his option, rescind this contract and recover for the value of the work and materials performed and furnished up to the time of such default, or should he so desire, he may continue the work and recover the contract price therefor at the completion thereof.”

Shortly after the execution of the contract the plaintiff proceeded with the work until on or about December 29, 1931, when he was ordered by defendants to discontinue construction until further notice. The principal dissension between the parties at that time seems to have been the interpretation of one of the specifications relative to sheathing. The parties met and discussed this difficulty and it is claimed by plaintiff, and so found by the trial court, that plaintiff offered to supply the sheathing demanded by the defendants. Later, defendants served a notice upon plaintiff, bearing date of January 8, 1932:

“Please take notice that the undersigned hereby cancels the contract entered into on the 5th day of September, 1931, with you for the construction of a house and garage on lot 5, block 18, Shoemaker’s addition to the city of Jackson according to the recorded plat thereof.
"Said cancellation to have effect 10 days after the service upon you of this written notice.
“The reasons for cancellation are as follows:
“1st. That the work on said buildings has not been done in a workmanlike manner.
*169 “2d. That you have not proceeded with the construction of the buildings with necessary promptness.
“3d. You have failed to comply with the requirements of the specifications for the construction of the house and garage, which said specifications are a part of the said contract.
“4th. Because you have not paid bills for material promptly upon receipt of money for the payment of said bills from us.
“5th. Because bills rendered by you for labor and material were inflated.
“6th. Because you have installed in said house defective material at a lower quality than that paid for by us.
“Ruth R. Beardsley,
“William J. Beardsley.”

Under date of January 13,1932, the plaintiff wrote to the defendants as follows:

“Your notice under date of January 8, 1932, has been handed to me, purporting to cancel the contract entered into on the 5th day of September, 1931, for the construction of a house and garage on lot 5, block 18, Shoemaker’s addition to the city of Jackson according to the recorded plat thereof,
“You state as your reasons for cancellation, first, that the work on said building has not been done in a workmanlike manner. I earnestly request that you state in detail wherein the work has not been done in a workmanlike manner. Second, you state that I have not proceeded with the construction of the building with necessary promptness. I earnestly request that you set forth wherein the construction has been delayed, and especially wherein it has been delayed to your detriment. Third, you state that I have failed to comply with the requirements of the specifications for the construction of the house and garage. I earnestly request that you set forth in detail and with particularity wherein I have failed *170 to comply with the requirements of the specifications for the construction of the house and garage. Fourth, you state I have not paid bills promptly for material upon receipt of money for the payment of bills. I earnestly request that you specify with particularity what bills for materials have not been paid for promptly upon receipt of money for the payment of said bills. Fifth, you state that bills rendered by me for labor and material were inflated. I request that you set forth with particularity which bills for labor, or material, or both, are alleged to be inflated and in what amounts. Sixth, you state that there has been installed in said house defective material at a lower quality than that paid for by you. I request that you set forth with particularity and detail what materials, if any, set forth in said house are defective materials and of lower quality than that paid for, and wherein the quality is deficient.
“I regret that any dissatisfaction has arisen and assure you of my willingness to make any changes or alterations within reason that you might request or desire, whether the same are covered by the contract or not. Prior to the date of cancellation, as set forth in your notice, we request the information as herein set forth.
“Victor Nurmi.”

At the time plaintiff was stopped from the performance of further work under his contract, upwards of 50 per cent, of the work to be done and materials furnished had been performed and furnished by plaintiff, the details of which will later be discussed. Certain changes had been made in the contract requiring extra work and materials in the amount of approximately $600, about which there appears to be no controversy. On January 15th, the plaintiff gave to defendants a sworn statement of the names of subcontractors and materialmen on the *171 job and tbe amounts owing to each, and on the same date filed a claim of lien against the property in the office of the register of deeds for the county of Jackson, subsequently filing his bill of complaint in the circuit court to foreclose said lien.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bryan Gallagher v. Northland Farms LLC
Michigan Court of Appeals, 2015
Ebling v. Masco Corporation
261 N.W.2d 74 (Michigan Court of Appeals, 1977)

Cite This Page — Counsel Stack

Bluebook (online)
278 N.W. 805, 284 Mich. 165, 1938 Mich. LEXIS 480, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nurmi-v-beardsley-mich-1938.