Nunlist v. Keleher

246 P. 904, 31 N.M. 358
CourtNew Mexico Supreme Court
DecidedApril 29, 1926
DocketNo. 2980.
StatusPublished
Cited by6 cases

This text of 246 P. 904 (Nunlist v. Keleher) is published on Counsel Stack Legal Research, covering New Mexico Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nunlist v. Keleher, 246 P. 904, 31 N.M. 358 (N.M. 1926).

Opinion

OPINION OF THE COURT

B1CKLEY, J.

The appellant (plaintiff) commenced suit against appellees (defendants.) to recover balance due on a written contract to furnish labor'and materials to do the steam heating in defendants’ building as per plans and specifications prepared by the contractor for the sum of $2,348. The contract was made by written proposal, which included standard conditions printed on the back thereof, together with a'written addition to paragraph 7 thereof, among which were the following:

“No. 1. Payments are to be made monthly on a basis of 90 per cent, of the value of the labor and materials furnished during the preceding thirty days. The remaining 10 per cent to be paid on completion of the contract.
“No. 7. If the work covered by this proposal includes the installation of material and apparatus under specifications made by others, the performance liability is not assumed by the contractor. Should the contractor guarantee temperatures or operation of this system and tests be required, such tests shall be made by the contractor under standards established by the American Society of Heating and Ventilating Engineers.
“No. 8. If upon completion of the work covered by this proposal, weather or other conditions over which the contractor has no control do not permit of a proper test, this shall not be considered a sufficient reason for withholding payment * * *.
“Addition to No. 7. Contractor will furnish written guaranty that plant will heat the rooms in which radiators are located to seventy degrees when the outside temperature is zero, allowing for one change of air in the room per hour.”

The complaint alleges, that plaintiff had performed all the conditions of the contract on his part to be performed; that defendants had paid $1,300 on the contract, leaving due thereon $1,048, which had been demanded but payment thereof refused. By answer the defendants admitted the execution of the contract; denied that plaintiff had performed all the conditions hereof; admitted that $1,048 remains owing, due, and unpaid; denied generally all the allegations of the complaint. The defendants also set up a cross-complaint, in which it was alleged that the equipment furnished did not supply the amount of radiation called for; that the plaintiff “promised to furnish a written guaranty that the heating plant would heat the rooms in which the radiators were located to 70° when the outside temperature was zero, allowing for one change of air in the rooms per hour; that the said contractor failed and refused to furnish such written guaranty, but that said plant never at any time heated the rooms in which the radiators were located to 70° when the outside temperature was zero, allowing for one change of air in the rooms per hour, but, on the contrary, the said heat was entirely inadequate and insufficient and did not heat the rooms of the said school to anything like 70° when the outside temperature was zero, without allowing for one change of air in the rooms per hour”; that the radiation was inadequate and incomplete' and unsatisfactory: that due to the failure, neglect, and refusal of the plaintiff to install said plant according to his contract and according to the plans and specifications provided for, and because of defective workmanship and inferior steam engineering, the defendants were obliged to repair the equipment and install other equipment, and by reason whereof the defendants were damaged in the amount of $1,500, for which they prayed judgment. Plaintiff replied by way of denial of new matter stated in the answer, and answered, denying the allegations of the cross-complaint.

The case proceeded to trial before a jury. The plaintiff introduced testimony to establish the performance of the covenants of the contract on his part to be performed. Testimony was introduced concerning the manner of installation of the plant, its efficiency, the amount of payment on the contract price, the balance due for which demand had been made and payment refused. Plaintiff also testified that on August 20, 1923, prior to bringing suit, he had signed up a separate written guaranty and left same with his attorney for the use of the defendants, but it appeared by the admissions of the parties that this paper was not delivered to the defendants until after suit was commenced. The separate written guaranty employed exactly the language of condition “Addition to No. 7.” No objection was made to the form or sufficiency of the writing except as hereafter stated.

At the close of plaintiff’s case, defendants moved for a directed verdict upon the ground that the plaintiff’s evidence showed that one term of the written contract which he alleged in his complaint had been performed as a matter of fact was. not performed except at a time after the institution of the suit, such term or covenant being the agreement to furnish a guaranty in writing as to the temperature procurable by the heating plant. The defendants claimed and now claim that this covenant concerning the temperature procurable' by the plant was not furnished prior to the suit, and that it was a dependent covenant, and that suit could not be maintained on the contract until such alleged dependent covenant had been complied with by the plaintiff. The trial court adopted the defendants’ view o£ th.e matter and directed a verdict in favor of the defendants.

Appellant assigns errors, which are grouped under the following points:

(a) The furnishing of the written guaranty is, not a condition precedent to the right of plaintiff to recover.

(b) Appellant actually furnished the written guaranty prior to the suit.

(c) The written guaranty was a useless and unnecessary thing since the contract itself was the guaranty, and, as the evidence showed that the plant came up to the specifications called for, the guaranty then became useless.

The agreement was a “Uniform Contract Form for the Heating Contractor, Adopted 1920 by the National Trade Extension Bureau.” Printed on the back thereof are “Standard Conditions Adopted by the National Trade Extension Bureau for Steam, Hot Water, and Better Heating Intallations. ” The evidence shows that at the instance of the defendants, there was written thereon by their agent the clause designated “Addition to No. 7.” Beneath these printed and written conditions is a place designated for the signature of the contractor and the owner. The record does not show signatures of the parties at this place. The contract provides:

"This proposal is for immediate ■ acceptance and includes the standard conditions printed on the back hereof which are hereby made a part of this proposal * *

The acceptance of the defendants, was as follows:

"The foregoing proposal including the iDrinted and written conditions on the back hereof is hereby accepted as a contract * *

As we construe the contract, there was furnished by the contractor a written guaranty that the plant would heat the rooms to 70° under the conditions named in “Addition to No.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Arrow Gas Company of Dell City, Texas v. Lewis
377 P.2d 655 (New Mexico Supreme Court, 1962)
Kelso v. Kelso
124 F. Supp. 294 (W.D. Oklahoma, 1954)
Price v. Van Lint
120 P.2d 611 (New Mexico Supreme Court, 1941)
Walters v. United States Fidelity & Guaranty Co.
288 P. 1044 (New Mexico Supreme Court, 1930)

Cite This Page — Counsel Stack

Bluebook (online)
246 P. 904, 31 N.M. 358, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nunlist-v-keleher-nm-1926.