Nunemaker v. Kulhavy

197 Iowa 962
Supreme Court of Iowa·Decided February 5, 1924·Published·Cited by 4 cases

Opinion

De Grape, J.

The issue presented on this appeal may be briefly stated as follows: Is plaintiff entitled to have his claim [963] for mechanics ’ lien established, and if so, what is the order of priority (1) as between plaintiff and a first-mortgage lien holder, and (2) as between plaintiff and a second-mortgage lien holder?

The trial court established the claim for a mechanics’ lien on the real estate involved, and determined the priority: (1) the first mortgage lien, (2) the mechanics’ lien, and (3) the second mortgage lien. In other words, plaintiff Nunemaker was unsuccessful in securing a judgment of priority of his claim for mechanics’ lien to the first-mortgage lien of defendant Moray L. Eby, and the defendant G-rande Avenue Land Company was unsuccessful in securing a judgment of priority of its second-mortgage lien to the claim of the plaintiff Nunemaker for his mechanics’ lien. Both the plaintiff Nunemaker and the defendant Grande Avenue Land Company appeal.

The facts disclose that the Grande Avenue Land Company was the owner of an addition to the city of Cedar Rapids, known as “Ridgewood,” and that, on October 9, 1919, the company entered into a contract with George W. Kulhavy for the sale to him of Lot 120 in said addition, for the sum of $1,500. A supplementary contract was entered into October 11, 1919, between said parties, which reads as follows:

‘ ‘ Party of the second part [Kulhavy] agrees to immediately commence the erection of a rockbond semi-bungalow approximately 26x36 feet with sun porch additional and two-car garage. Party of the second part will rush the house to completion as fast as consistent with good workmanship. The house and garage to cost not less than sixty-five hundred ($6,500.00) dollars, and to be of that value. Party of the first part is to furnish warranty deed to lot when required by party of the second part for loan purposes. When the deed is furnished party of the second part will execute and deliver a mortgage for the full amount of the lot running three years at 6 per cent interest, payable semiannually, which mortgage is to be subject only to a first mortgage by a building & loan association not exceeding the cost of the house.”

Thereafter, and on February 18, 1920, a contract was entered into between the plaintiff Nunemaker, a contractor, and Iva E. Kulhavy, wife of George W. Kulhavy, as follows:

“Party of the first part [Kulhavy] agrees to furnish all [964] money for labor and material as the work progresses. Party of the second part [Nunemaker] agreeds to take charge of and see that all work is done in a good and workmanlike manner. Party of the second part to receive for his services the scale of wages for each and every day that he works on the house, also two hundred ($200.00) dollars as his commission when house is completed. ’ ’

Kulhavy testified that the plaintiff knew the terms and conditions of the contract of purchase of the real estate in question, and that the contract for the erection of the residence on said lot was entered into with full knowledge on the part of Nune-maker of its terms and conditions. This is denied by Nune-maker. It further appears that, pursuant to the contract of sale between the company and Kulhavy, a deed of conveyance was executed and delivered to him, and at the same time, and as a part of the same transaction, Kulhavy signed a note and mortgage for the purchase price of the lot, in accordance with the contract, and' the deed and mortgage was filed for record November 28, 1919. It also appears that a mortgage Avas negotiated by the Kulhavys with a building and loan association, but was not consummated, for the reason that another loan was negotiated with Moray L. Eby (defendant first mortgagee) for $5,500, and the mortgage signed and recorded; but afterwards it was canceled and discharged of record by the said Eby, upon an agreement to increase the loan to $7,000, which was done, and a new mortgage executed and recorded on July 23, 1920. On the latter date, the original $1,500 purchase-money second mortgage was canceled and surrendered, and a new $1,500 mortgage and note executed in lieu thereof from the Kulhavys to the Grande Avenue Land Company, which' substituted second mortgage was filed for record.

Plaintiff, in December, 1919, commenced the construction of the residence. Before plans and specifications were prepared, plaintiff made a rough estimate as to the cost of the house then contemplated, and fixed the cost from $8,000 to $8,500. No estimate was made upon the house that was planned and constructed, and its actual cost when completed was about $13,000. There is no evidence that the cost exceeded the fair and reasonable value of the- building at the time of its construction, and [965] it included a garage in connection witb tbe bouse. Tbe $7,000 secured on tbe first mortgage by Kulbavy was used to pay plaintiff on tbe improvement. No other funds were furnished, and when Kulbavy ceased to furnish money to buy material and pay for tbe labor, plaintiff completed tbe job, a,nd when completed, in September, 1920, there was a balance of $3,329 owing for labor and material furnished by plaintiff.

At tbe outset, it may be observed that tbe property owner Kulbavy has not appealed from tbe decree entered, and tbe decree must be considered as res judicata to him.. Although the appellant Grande Avenue Land Company may not dispute the lien as established against tbe real estate, it is in a position to question tbe order of priority: that is, whether the establishment of tbe lien shall take precedence of its right and lien.

Free access — add to your briefcase to read the full text and ask questions with AI

Nunemaker v. Kulhavy, 197 Iowa 962 (iowa 1924).

197 Iowa 962 (Nunemaker v. Kulhavy) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Lackey v. Melcher
281 N.W. 225 (Supreme Court of Iowa, 1938)
Lane-Moore Lumber Co. v. Kloppenburg
215 N.W. 637 (Supreme Court of Iowa, 1927)
Queal Lumber Co. v. Lipman
206 N.W. 627 (Supreme Court of Iowa, 1925)
Lovell-Scholfield Lumber Co. v. Carter
198 Iowa 238 (Supreme Court of Iowa, 1924)