Nova Contracting, Inc. v. City Of Olympia

CourtCourt of Appeals of Washington
DecidedApril 18, 2017
Docket48644-0
StatusUnpublished

This text of Nova Contracting, Inc. v. City Of Olympia (Nova Contracting, Inc. v. City Of Olympia) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nova Contracting, Inc. v. City Of Olympia, (Wash. Ct. App. 2017).

Opinion

Filed Washington State Court of Appeals Division Two

April 18, 2017

IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON

DIVISION II NOVA CONTRACTING, INC., a Washington No. 48644-0-II Corporation,

Appellant,

v. UNPUBLISHED OPINION

CITY OF OLYMPIA, a Washington Municipal Corporation,

Respondent.

MAXA, A.C.J. – Nova Contracting, Inc. appeals the trial court’s summary judgment

dismissal of its claim that the City of Olympia breached the implied duty of good faith and fair

dealing in its administration and termination of a construction contract between the City and

Nova. Nova also appeals the trial court’s award of liquidated damages to the City on the City’s

counterclaim for breach of contract.

We hold that the trial court erred in granting summary judgment in favor of the City on

Nova’s duty of good faith and fair dealing claim because Nova presented sufficient evidence to

create a genuine issue of material fact that the City prevented Nova from attaining its justified

expectations under the contract. As a result, we also vacate the trial court’s award of liquidated

damages and reasonable attorney fees to the City. However, because the liquidated damages

issue may arise again on remand, we consider the enforceability of the liquidated damages No. 48644-0-II

clause. We hold that the trial court did not err in ruling on summary judgment that the liquidated

damages clause is enforceable if the City prevails on its breach of contract claim on remand.

Accordingly, we reverse the trial court’s summary judgment dismissal of Nova’s claim

for breach of the duty of good faith and fair dealing, vacate the trial court’s award of liquidated

damages and reasonable attorney fees to the City, and remand for further proceedings consistent

with this opinion.

FACTS

Project Award

In early 2014, the City published an invitation for bids to replace a culvert that conveyed

a creek underneath a paved bike trail. In May 2014, the City accepted Nova’s bid, although

Nova alleges that some City staff wanted another contractor to get the bid and were looking for

reasons to reject the bid. The parties executed a contract that incorporated the project’s plans

and specifications, Nova’s bid proposal, and the Washington State Standard Specifications for

Road, Bridge, and Municipal Construction.1

The contract required that Nova send several submittals for the City’s engineer to

approve before construction could begin, including a detailed description of the work, a bypass

pumping plan, a work area excavation plan, and an access and haul route plan. The contract also

required the City’s engineer to approve other submittals before the work outlined in those

submittals could proceed. The contract provided that the City would review these submittals,

1 The record does not contain the entire contract, including many of the project-specific plans and specifications. In addition, on summary judgment the parties submitted only portions of the standard specifications.

2 No. 48644-0-II

that the City’s decisions would be final, and that Nova would bear all risk and cost of work

delays caused by non-approval of any submittals.

Under the contract, Nova was required to complete the work within 45 working days

after the City issued a notice to proceed. The contract stated that Nova would be liable for

liquidated damages of $939.46 per day if it failed to complete the project on time.

Problems with Submittal Process

On August 11, 2014, the City issued a notice to proceed. Nova’s initial schedule

indicated that Nova intended to mobilize to the construction site on August 12. But Nova could

not mobilize as scheduled because of delays in the submission and approval of Nova’s

submittals. On August 19, the City sent Nova an email stating that it was clear that Nova would

be unable to meet the project schedule and requesting a revised schedule.

The parties continued to have problems as the City rejected many submittals, in some

cases rejecting re-submittals as well. Nova claimed that the City had been improperly rejecting

submittals and that it could not meet the project schedule as a result. The City expressed

concerns about the lack of sufficient information in several of Nova’s submittals. By September,

key submittals remained unapproved. Nova provided several submittals on September 4 that the

City rejected.

Notice of Default and Termination

On September 4, the City sent Nova a letter stating that the City considered Nova to be in

default on the contract for several reasons, including: (1) Nova’s failure to mobilize to the site,

(2) the lapse of 17 out of 45 total working days, (3) Nova’s failure to provide an updated project

schedule, (4) Nova’s repeated failure to provide satisfactory versions of several submittals, and

3 No. 48644-0-II

(5) the City’s concern that Nova would not complete the project within the time remaining. The

letter concluded that the cumulative effect of these problems constituted a material default under

the contract. The City stated that Nova had 15 days to cure the default by providing acceptable

submittals, submitting an updated schedule, and showing that the project could be completed in

the original time frame.

Also on September 4, Nova mobilized to the work site. But on September 8, the City

delivered a stop work order to the site. The City’s reasons for the stop work order included

Nova’s failure to notify the City before beginning any work, as required by the contract; Nova’s

attempts to gain access to the project site and its entry to the site without prior approval; and

placement of equipment on the site without approval for use of that equipment.

Nova expressed surprise at the City’s action. Nova pointed out that the City’s first

ground for default was Nova’s failure to mobilize to the site, but that the City simultaneously

demanded that Nova remove its equipment from the site. In multiple letters sent on September 9,

Nova protested the default and responded in detail to the City’s grounds for default.

On September 18, the City rejected Nova’s protest. The City stated that the contract

would be terminated unless Nova met the requirements in the September 4 default letter by

September 19. In another letter dated September 18, the City responded to Nova’s protest of the

default. On September 19, Nova sent a lengthy letter contesting the City’s grounds for

terminating the contract.

On September 24, the City sent Nova a letter terminating the contract. The letter asserted

that Nova had “chosen to assert protests and excuses rather than provide the requested

documents and assurances.” Clerk’s Papers (CP) at 215.

4 No. 48644-0-II

Nova’s Lawsuit

Nova filed a lawsuit against the City, asserting that the City had breached the parties’

contract. Among other allegations, Nova claimed that the City’s handling of Nova’s submittals

both imposed requirements that were not part of the project’s specifications and delayed Nova’s

performance so that the project could not be timely completed. The City counterclaimed that

Nova had breached the contract by failing to complete the project and therefore was liable for

liquidated damages.

The City moved for summary judgment, arguing that it properly terminated the contract

for default, that Nova was liable for liquidated damages for failing to complete the project on

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Nelson v. McGoldrick
896 P.2d 1258 (Washington Supreme Court, 1995)
Best v. United States National Bank
739 P.2d 554 (Oregon Supreme Court, 1987)
Blakely v. Housing Authority
505 P.2d 151 (Court of Appeals of Washington, 1973)
Watson v. Ingram
881 P.2d 247 (Washington Supreme Court, 1994)
Wallace Real Estate Investment Inc. v. Groves
881 P.2d 1010 (Washington Supreme Court, 1994)
Badgett v. Security State Bank
807 P.2d 356 (Washington Supreme Court, 1991)
Elcon Construction, Inc. v. Eastern Washington University
273 P.3d 965 (Washington Supreme Court, 2012)
Edmonson v. Popchoi
256 P.3d 1223 (Washington Supreme Court, 2011)
Minnick v. CLEARWIRE US LLC
275 P.3d 1127 (Washington Supreme Court, 2012)
McKee v. AT & T CORP.
191 P.3d 845 (Washington Supreme Court, 2008)
Zuver v. Airtouch Communications, Inc.
103 P.3d 753 (Washington Supreme Court, 2004)
Rekhter v. Department of Social & Health Services
323 P.3d 1036 (Washington Supreme Court, 2014)
Zuver v. Airtouch Communications, Inc.
153 Wash. 2d 293 (Washington Supreme Court, 2004)
McKee v. AT&T Corp.
164 Wash. 2d 372 (Washington Supreme Court, 2008)
Keck v. Collins
357 P.3d 1080 (Washington Supreme Court, 2015)
Sutton v. Tacoma School District No. 10
324 P.3d 763 (Court of Appeals of Washington, 2014)
Romney v. Franciscan Medical Group
186 Wash. App. 728 (Court of Appeals of Washington, 2015)
Johnson v. Yousoofian
930 P.2d 921 (Court of Appeals of Washington, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
Nova Contracting, Inc. v. City Of Olympia, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nova-contracting-inc-v-city-of-olympia-washctapp-2017.