Norton v. Sinkhorn

50 A. 506, 63 N.J. Eq. 313, 18 Dickinson 313, 1901 N.J. LEXIS 191
CourtSupreme Court of New Jersey
DecidedNovember 15, 1901
StatusPublished
Cited by5 cases

This text of 50 A. 506 (Norton v. Sinkhorn) is published on Counsel Stack Legal Research, covering Supreme Court of New Jersey primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Norton v. Sinkhorn, 50 A. 506, 63 N.J. Eq. 313, 18 Dickinson 313, 1901 N.J. LEXIS 191 (N.J. 1901).

Opinion

The opinion of the court was delivered by

Depue, Ci-iief-Justice.

The-facts of this case are so fully set out in the opinion of Vice-Chancellor Grey that a brief statement is all that will be necessary here. Briefly, the case is this: The defendants, Sink-horn & Company, entered into a contract with the board of chosen freeholders of the county of Mercer on the 24th of March, 1900, for the grading and macadamizing of a public road in the county of Mercer. The firm entered upon the performance of the contract and completed it on or about the 27th of October, 1900. The bill charges that, under the contract, the sum of $3,000 was due and payable by the board of freeholders upon the completion and acceptance of the work of macadamizing said road. It also charges that between September 1st. 1900, and October ’28th, 1900, the complainant, Norton, performed labor for the said Sinkhorn & Company in and about the work of macadamizing and grading said road and towards the completion and performance of said contract with the board of freeholders, by furnishing to them teams and drivers and carting stone and other materials, and that he sold and delivered to Sinkhorn & Company certain materials which were used in the performance and completion of the road, under said contract, to the amount of $862.50. The bill further charges that on or about the 29th of October, 1900, and within fifteen days after the completion of said work, the complainant filed with the director of the board of freeholders, and with the collector and financial officer of said county, a notice that the complainant claimed a lien on the moneys in the hands or under the control of the board of freeholders of the county of Mercer, due or to [316]*316grow due under said contract, pursuant to an act entitled “An act to secure the payment" of laborers, mechanics, merchants, traders and persons employed upon or furnishing materials toward the performing of any work in public improvements in cities, towns, townships and other municipalities in this state,” approved March 30th, 1892. Gen. Stat. p. 2078. No answer was filed by the county, and the balance due to Sinldiorn & Company from the county is not disputed.

The defendants filed an answer, in the course of which they set up an abatement of the amount alleged to be due from their firm to the complainant, reducing it to the sum of $259.20, because, the defendants aver, that they were obliged to pay the sum of $684 for demurrage to the Pennsylvania Railroad Company, by reason of carloads of stone shipped by the defendants to Windsor and liighistown, in the county of Mercer, and which, by the terms of the contract between the complainant and the defendants, the complainant was obliged to haul and distribute upon said road, but which the complainant allowed to remain at the said stations for an undue length of time, thereby subjecting the said carloads of stone to the charge for demurrage aforesaid, which the defendants, as the shippers of the same, were obliged to pay. The answer further sets out that the complainant agreed with the defendants to cart said stone in quantities of two hundred tons per day, and by reason of said complainant carting less than two hundred tons per day, as aforesaid, the said claim for demurrage arose, which said claim the defendants would not have been obliged to pay but for the default and neglect of the complainant to perform his contract in that behalf, &c.

. The same facts are set out in the answer, .by way of a cross-bill, which concludes with a prayer that an account may be taken between the complainant and the defendants, and that, by the order and decree of the court of chancery, the complainant may be decreed to pay to the defendants the true balance and amount owing from him to them, and also for other and further relief.

On notice an order was made by the court of chancery that so much of the answer filed by the defendants as claimed a reduc[317]*317tion from the amount claimed by the complainant for materials furnished and labor performed, &c., on account of the demurrage alleged to have been paid by the defendants on carloads of stone, be and the same was thereby stricken out of said answer, and further, that the answer by way of cross-bill be dismissed. From this order this appeal was taken.

The construction of this statute is settled by the opinion of this court in Delafield Construction Co. v. Sayre, 31 Vr. 449. This court there held that suits to ascertain and enforce the liens given by the act in question must be brought in the court of chancery. The reasoning upon which that decision was based was that, in such a case, “the court is to determine the validity of each lien claim, the amount due upon it and the amount due to the contractor from the municipality, and is to render judgment directing the municipality to pay over to the several lienors the sums found to be due to them respectively, so far as the fund will go, according, to the priority prescribed by the act. * * There is no provision [in this statute] for a personal judgment against the contractor as a debtor, but the right of the claimants to obtain such judgment against him in other actions is expressly preserved.” It was for this reason that this court held that suits under this act were cognizable only in the court of chancery. In other words, the proceeding is in rem—a controversy over a particular fund, involving only the amount due to the contractor from the municipality for the work done and the amount due to the lien claimants respectively. Section 8 of the act makes this construction clear. It provides that the court “shall determine the validity of the lien, the amount due from the debtor to the contractor under his contract, and from the contractor to the respective claimants, and shall render judgment directing that the city, town, township or other municipality shall pay over to the claimants for the work done and the materials furnished in the execution of said contract or contracts, whose claims ox liens it shall hold to be valid and just, in the order of their priority as determined b3r said court, to the extent of the sum found due to said claimants from the contractor, so much of said funds or money which may be due from the city, town, township or other municipality [318]*318to tlae contractor, under his contract, against which the lien is filed, as will satisfy their liens or claims, with interest and costs, to the extent of the amount due from said city, town, township or other municipality to said contractor.” Gen. Siat. p. 2079. The questions raised in this case are controlled by this statute. Where the amount due to the contractor is undisputed, the sole questions for adjudication is the amount due to the lien claimants respectively from the contractor. When that has been ascertained, then the function of the court is to apportion the amount due the contractor among the lien claimants in the proper proportion, provided the fund under the control of the court is sufficient to answer that purpose; if not sufficient, then pro rata until the fund in hand is exhausted. At this stage the jurisdiction of the court under the statute ends. No personal judgment, either for or against a lien claimant, can be given; nor does the statute provide for a judgment against a municipality in case the amount due to the contractor exceeds the sums due to the lien claimants.

By statute, a set-off, with respect to the rights and liabilities of the parties to the suit, is considered as a cross-action brought by the defendant. Practice act § 131/.J Gen. Stat. p. 2555.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

MECHANICAL DEVICES CO., INC. v. General Builders, Inc.
99 A.2d 605 (New Jersey Superior Court App Division, 1953)
Benton Holden v. Central R.R. Co. of N.J.
194 A. 805 (New Jersey Court of Chancery, 1937)
Commonwealth Quarry Co. v. Gougherty
148 A. 356 (New Jersey Court of Chancery, 1930)
Curtiss-Warner Corp. v. Thirkettle
134 A. 299 (New Jersey Court of Chancery, 1926)
Waterworks Equipment Co. v. McGovern
126 A. 411 (New Jersey Court of Chancery, 1924)

Cite This Page — Counsel Stack

Bluebook (online)
50 A. 506, 63 N.J. Eq. 313, 18 Dickinson 313, 1901 N.J. LEXIS 191, Counsel Stack Legal Research, https://law.counselstack.com/opinion/norton-v-sinkhorn-nj-1901.