Northwestern Engineering Co. v. Ellerman

23 N.W.2d 273, 71 S.D. 236, 1946 S.D. LEXIS 27
CourtSouth Dakota Supreme Court
DecidedJune 3, 1946
DocketFile No. 8805.
StatusPublished
Cited by4 cases

This text of 23 N.W.2d 273 (Northwestern Engineering Co. v. Ellerman) is published on Counsel Stack Legal Research, covering South Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Northwestern Engineering Co. v. Ellerman, 23 N.W.2d 273, 71 S.D. 236, 1946 S.D. LEXIS 27 (S.D. 1946).

Opinion

SICKEL, J.

This is an action to recover damages for breach of contract. In March, 1942, the Northwestern Engineering Company, plaintiff planned to bid on the main con *238 tract for the construction of the Rapid City Army Air Base. It proposed the subletting of Section 4, Schedule 3 of the government specifications to Ellerman and McLain, a partnership, defendants. An agreement was entered into between plaintiff and defendants whereby defendants agreed to enter into a contract for the performance of the work and the furnishing of materials required by that section and schedule for the sum of $79,098.26 contingent on the acceptance of the plaintiff’s bid on the main contract by the Army. Before the letting plaintiff and defendants modified this subcontract by increasing the consideration therefor in the sum of $6,000. Thereafter, plaintiff became the successful bidder at the letting of the main contract. Defendants refused to enter into a performance contract, and so notified the plaintiff. Thereafter plaintiff relet the same work to the Northern Construction Company for the sum of $92,573.79. The contract was performed by the Northern Construction Company and the consideration was paid in full. On June 13, 1942, plaintiff brought this action against the defendants to recover damages resulting from the breach of the contract. Plaintiff claims it has been damaged in the sum of the difference between the amount for which the defendants agreed to do the work and the amount which the plaintiff paid the Northern Construction Company for doing it. Defendants filed a motion to dismiss plaintiff’s complaint on the ground that the complaint failed to state a cause of action. This motion was sustained in the circuit court, but on appeal this court held that the contract was valid and enforceable, 69 S. D., 397 10 N. W.2d 879. The case was then tried to a jury who returned a verdict for defendant, and plaintiff appealed.

At the trial the allegations of the complaint as to the execution and delivery of the agreement Exhibit 1 as modified, and the consideration therefor were sustained by the evidence. Respondents offered testmony to show oral negotiations preceding and accompanying the execution of that agreement in an attempt to prove that such an agreement was not intended by the parties to be a binding obligation. The circuit court ruled that this defense had not been proved by competent testimony, and declined to submit it to *239 the jury. Therefore, the decision of this court on the former appeal, to the effect that the original agreement as modified was a valid and binding obligation to enter into a performance contract, remains the law of the case.

Respondents claimed at the trial, and introduced evidence tending to show, that the performance contract submitted by appellant contained provisions which placed upon respondents obligations not included in the original agreement, and not within the contemplation of the parties when the original agreement was made; that respondents refused to sign the performance agreement for these reasons. This original agreement is an agreement to enter into a contract for the performance of the work and the furnishing of material described or referred to therein, on terms consistent with the provisions of that agreement. Insistence by either party upon the introduction into the supplemental contract of terms not reasonably within the contemplation of the parties when the original agreement was made, constitutes a breach of the original agreeement. Likewise, the refusal by either party to execute a proposed supplemental-contract containing only such terms as were reasonably within the contemplation of the parties, constitutes a breach of the original agreement. Commissioners of Highland County v. Rhoades, 26 Ohio St. 411; Lewis v. Brass, 3 Q. B. D. 667; 9 C. J., Building and Construction Contracts, § 10. The evidence in the case required that these questions be decided by the court or submitted to the jury at the former trial.

Appellant claims that the court erred in denying its motion for a directed verdict. It is the appellant’s contention that the undisputed evidence shows that the respondents agreed to do the work and furnish the materials called for by the agreement, for the sum of $85,935.42; that respondents failed and refused to perform any part of the contract; that the cost to appellant of securing the performance of the contract by. another concern was $92,573.79; that the appellant has therefore been damaged in the sum of $6,638.37 and is entitled to judgment therefor. Respondents claim that the measure of damages is the difference between the contract price and the fair, reasonable cost of having the work done.

*240 SDC 37.1801 contains the following provision:

“For the breach of an obligation arising from contract, the measure of damages, * * * is the amount which will compensate the party aggrieved for all the detriment proximately caused thereby, or which, in the ordinary course of things, would be likely to result therefrom. * * *”

This is also the rule at common law. Hayes v. Cooley, 13 N. D. 204, 100 N. W. 250.

When there is a total failure of performance of a contract of this character, the amount which will compensate the party aggrieved, under the rule stated in the above statute, is the difference between the contract price and the actual and necessary cost of complete performance. Anderson v. Nordstrom, 60 Minn. 231, 61 N. W. 1132; Grady v. Sullivan, 112 Mich. 458, 70 N. W. 1040; Doherty v. Detroit Fidelity & Surety Co., 240 Mich. 36, 214 N. W. 833; Baumann v. City of West Allis, 187 Wis. 506, 204 N. W. 907; Johnson v. Yogel, 208 Iowa 44, 222 N. W. 864; Elmohar v. People’s Surety Co., 217 N. Y. 289, 111 N. E. 821; American Surety Co. v. Gonzales Water Power Co., Tex. Civ. App., 211 S. W. 251; Smith v. Brocton Preserving Co., 251 App. Div. 102, 296 N. Y. S. 281; Carrig v. Gilbert-Varker Corporation, 314 Mass. 351, 50 N.. E.2d 59, 147 A. L. R. 927; 25 C. J. S., Damages, § 79.

There is no dispute as to the amount of the consideration which was to be paid to respondents for the performance of the work, nor as to the amount paid by appellant to the Northern Construction Company for performance of the same obligation. Appellant’s damage is the amount of the excess, unless the amount paid to the Northern Construction Company was unnecessarily high. The amount so paid out would be unnecessarily high if the terms of the contract with Northern Construction Company imposed burdens upon the contractor which respondents were not obliged to bear under their original agreement.

This brings us to the question of mitigation of damages. It is generally held that in actions for damages arising out of a breach of contract, in which plaintiff has proved his damages, the burden of proving that the damages *241 would have been lessened by reasonable diligence on the part of the claimant is on the party whose wrongful act caused the damages. Rich v. Daily Creamery Co., 296 Mich. 270, 296 N. W. 253, 134 A. L. R. 232, and Annotation 243, 254; Hoehne Ditch Co. v. John Flood Ditch Co., 76 Colo. 500, 233 P. 167; United States v. Harris, 9 Cir.,

Related

Renner Elevator Co. v. Schuer
267 N.W.2d 204 (South Dakota Supreme Court, 1978)
Brook v. Oberlander
199 N.E.2d 613 (Appellate Court of Illinois, 1964)
Kowing v. Williams
67 N.W.2d 780 (South Dakota Supreme Court, 1954)

Cite This Page — Counsel Stack

Bluebook (online)
23 N.W.2d 273, 71 S.D. 236, 1946 S.D. LEXIS 27, Counsel Stack Legal Research, https://law.counselstack.com/opinion/northwestern-engineering-co-v-ellerman-sd-1946.