Northwestern Bell Telephone Co. v. Woodmen of the World Life Insurance

199 N.W.2d 729, 189 Neb. 30, 1972 Neb. LEXIS 653
CourtNebraska Supreme Court
DecidedAugust 4, 1972
Docket38289
StatusPublished
Cited by33 cases

This text of 199 N.W.2d 729 (Northwestern Bell Telephone Co. v. Woodmen of the World Life Insurance) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Northwestern Bell Telephone Co. v. Woodmen of the World Life Insurance, 199 N.W.2d 729, 189 Neb. 30, 1972 Neb. LEXIS 653 (Neb. 1972).

Opinion

C. Thomas White, District Judge.

The plaintiff sued in the district court on two causes of action: On a contract to indemnify and on a breach of contract to construct. The cause was tried to a jury, and the jury found for the plaintiff on a combined verdict in the amount of $74,554.75. Plaintiff appeals and defendant cross-appeals.

The plaintiff is a corporation engaged in the operation of telephone and related communication facilities, in interstate and intrastate commerce. Its rates are generally fixed by the Federal Communications Commission and other state agencies. Its business records are kept in a form and according to detailed standards fixed by the Federal Communications Commission. The regulations prescribed formulas for cost allocation of all services, labor, materials, and overhead, primarily for the purpose of determining rates.

The defendant is' a fraternal benefit society with its principal activity the issuance of contracts of insurance on its members.

*32 This action concerns the construction of the Woodmen of the World Building on Block 116 of the Original City of Omaha, Nebraska. Block 116 is bounded on the north by Douglas Street, on the south by Farnam Street, on the west by 18th Street, and on the east by 17th Street. As part of the original plat and dedication, an alley existed in Block 116, running east and west between 17th and 18th Streets. The alley was 20 feet in width, 264 feet long, and buried beneath it were a sewer and electric power cables and conduits containing telephone facilities belonging to the plaintiff.

The defendant, prior to the contract in question, owned the entire south half of Block 116. and parts of several lots to the north of the alley, and held an option to purchase the remaining portions of the alley from other owners of property in Block 116, so that in the event of vacation of the alley, defendant would own the entire vacated alley. It was the plan of the defendant to build and it ultimately did build an office building on the south half of Block 116 and the vacated alley.

As a condition for the vacation of the alley, the planning commission of the City of Omaha required defendant to make provisions for the maintenance of the utility services then in the alley. The contract in suit was a result of that requirement.

The contract was entered into on May 24, 1966. After recitation of the above facts, the contract required defendant to build an underground tunnel to house the utility lines of the plaintiff and the Omaha Public Power District, according to specifications attached to the contract. The contract provided that the costs of the moving of the utilities in the tunnel would be borne by the defendant, and that the defendant “. . . agrees to and does hereby indemnify the . . . Telephone Company against all damages to their utility facilities located in the alley, . . . and for liability to the customers . . . for refunds or for interruption of service, caused by Woodmen’s excavation and construction activities and by *33 the acts and omissions of Woodmen’s architects or contractors.”

The defendant started construction of its building and the plaintiff moved its telephone lines to an uncompleted tunnel. On May 7, 1968, while the construction activities of the defendant were in progress, a fire started in the tunnel damaging and destroying a number of cables carrying local and distance call lines of the plaintiff. The plaintiff made emergency repairs to the cables, and was required to make refunds to customers who were denied the use of the facilities for periods ranging from 24 to 36 hours. Ultimately the tunnel was completed to specifications.

At the date of the fire the construction site was under the control and occupied by the defendant and its architects and contractors. The fire was extensively investigated and the probable cause as testified to by the investigators was a spark from a cutting torch which dropped through openings at the top of the tunnel or the dropping of a lighted cigarette or cigar at the point of the fire. The evidence disclosed no other possible cause or causes. At the conclusion of the evidence, the court directed a verdict of liability on the indemnity portion of the contract and submitted to the jury the issue of a breach of the agreement to construct a tunnel. The jury returned a verdict of $74,544.74 on all causes of action.

The plaintiff asserts seven assignments of error, but simply stated, they involve three issues: (1) The court should have directed a verdict and entered judgment for the amount the plaintiff’s evidence proved as repairs and refunds; (2) the court should have directed a verdict on the alleged failure of defendant to protect the plaintiff’s facilities and its failure to construct an enclosed tunnel; and (3) the court should have allowed interest from the date of the presentation of the repair statement on June 29, 1969.

The Federal Communications Commission is given *34 the authority to prescribe a uniform system of accounting for telephone companies, including the disbursements and receipts of money. 47 U. S. C. A., § 220, p. 122. The plaintiff cites a number of cases dealing with the validity of the regulations adopted, but the same are not in point here.

The plaintiff’s evidence of the damages on behalf of itself and A. T. & T., an associated company, generally was that of the accounting personnel. The various witnesses testified in detail as to methods of allocation of direct cost, its method of determining allocation of overhead, vehicle expense, pension and other costs, and the amount of refunds. The plaintiff' introduced evidence that the bookkeeping procedures were those specified and required by the Federal Communications Commission. Under the formula the plaintiff offered evidence tending to show damages in the amount of $100,225.83. The evidence as to amount was not substantially controverted.

The trial court instructed the jury after directing a verdict on the indemnity contract, that in considering the amount of the plaintiff’s damages, the jury “may consider” certain elements of damages, to-wit, “the fair and reasonable costs of labor and material plus a reasonable overhead,” and credit and refunds to customers.

The court further instructed the jury that it “may consider” records kept according to a method required by the Federal Communications Commission as a proper measure of plaintiff’s damage, and further the jury was not bound by a bookkeeping system of the plaintiff'.

Wisconsin Telephone Co. v. Reynolds, 2 Wis. 2d 649, 87 N. W. 2d 285, is cited as authority for the proposition that in an action by a telephone company against a grading contractor for damage to an underground cable, the company’s accounting records relating to cost of repair, which records were in the form prescribed by the Federal Communications Commission, indicated actual cost of the repair.

*35 Baltimore & Ohio R. R. Co. v. Commercial Transport, Inc., 273 F. 2d 447, held that a jury could compute damages for repair overhead on the basis of a formula utilized by railroads in charging one another for repairs.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Weyh v. Gottsch
303 Neb. 280 (Nebraska Supreme Court, 2019)
Slaymaker v. Breyer
607 N.W.2d 506 (Nebraska Supreme Court, 2000)
Blue Valley Cooperative v. National Farmers Organization
600 N.W.2d 786 (Nebraska Supreme Court, 1999)
Lackman v. Rousselle
585 N.W.2d 469 (Nebraska Court of Appeals, 1998)
Life Investors Insurance Co. of America v. Citizens National Bank
392 N.W.2d 771 (Nebraska Supreme Court, 1986)
Bank of Valley v. Shunk
302 N.W.2d 711 (Nebraska Supreme Court, 1981)
Curt's Trucking Co. v. City of Anchorage
578 P.2d 975 (Alaska Supreme Court, 1978)
WOODMEN OF WORLD LIFE IS v. PETER KIEWIT SONS'CO.
241 N.W.2d 674 (Nebraska Supreme Court, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
199 N.W.2d 729, 189 Neb. 30, 1972 Neb. LEXIS 653, Counsel Stack Legal Research, https://law.counselstack.com/opinion/northwestern-bell-telephone-co-v-woodmen-of-the-world-life-insurance-neb-1972.