Northwest Thresher Co. v. Kubicek

118 N.W. 94, 82 Neb. 485, 1908 Neb. LEXIS 293
Nebraska Supreme Court·Decided October 22, 1908·No. No. 15,315·Published·Cited by 4 cases

Opinion

Fawcett, C.

Plaintiff instituted this suit in the district court for Saline county to foreclose a chattel mortgage, and for judgment upon three promissory, notes described in said mortgage, which it claims were given to it by defendant Matej Kubieek in settlement for a traction engine and sundry attachments, which plaintiff claims said defend-. ant Matej Kubieek and his son, Joe Kubieek, had ordered from plaintiff on June 9, 1904, in a written order, which provided for the delivery of said engine and attachments on board the cars at Crete, Nebraska. The defendants allege substantially that within two weeks subsequent to the giving of such order, and before the same had been accepted by plaintiff, they countermanded said order, but that, regardless of such countermand, plaintiff shipped said engine to Crete; that when it arrived at Crete defendants refused to accept it; that thereupon plaintiff sent one of its representatives, one J. F. Hennessy, to Crete, to attempt to make 'delivery of such engine; that defendants refused to receive the engine; that after somewhat extended negotiations it was agreed between Hennessy and defendants that Hennessy was to . unload the engine and attachments, put them together, and deliver them to defendants on the farm of Matej Kubieek, about four and a half miles southwest of Crete; that, in consideration of that agreement, defendant Matej Kubieek [487] paid the freight on the engine, and signed the notes and mortgage in controversy; that said Hennessy thereupon proceeded to and did unload the engine from the car, attached the necessary parts thereto, and, in company with another employee of plaintiff, started with said engine for the farm of defendants; that when said Hennessy had proceeded about three-quarters of a mile from Crete, while attempting to cross a bridge, the bridge gave way and precipitated the engine and the two men who were upon it into the ditch below, a fall of about 18 feet, killing Hennessy and slightly injuring his companion; that on the next day Mr. E. W. Chambers, general manager of plaintiff for the state of Nebraska, called upon defendants and informed them of the accident which had happened on the previous evening; that Chambers then agreed that plaintiff would extricate the engine from the ditch, take it Jack to Crete, replace all broken parts, make .the engine as good as ever, and deliver it to defendants upon their farm within five days thereafter; that in accordance with that agreement plaintiff did remove the engine from the ditch to Crete and expend considerable time, much more than five days, in trying to restore the engine to its former condition, but utterly failed to succeed in so doing; that plaintiff has never delivered the engine or any of the attachments to defendants as agreed, but at all times has had and still has possession of the same.

Plaintiff denies that Mr. Chambers ever made any such an agreement, and alleges that the only agreement he made was that, in consideration of the unfortunate circumstances, he would, as a matter of accommodation to defendants, and at plaintiff’s expense, restore the engine to its former condition as soon as possible, and that when this was done defendants were to go to Crete and get the engine. Plaintiff also denies that Hennessy ever made the agreement claimed by defendants about delivering the engine to defendants’ farm, and alleges that, if he did make such agreement, he had no authority so to do, and that plaintiff was not bound thereby. Plaintiff also al[488] leges that it had accepted the order of defendants before it received any notice of an intention on the part of defendants to countermand the same.

The case was tried to the court, and a decree entered, in which the court found “for the defendants, and finds that the plaintiff has the property in controversy in its possession and ever has had, and the defendants or either of them never had possession thereof, and the foreclosure of the chattel mortgage in question is not plaintiff’s remedy,” and dismissed plaintiff’s action without prejudice.

The principal questions involved, and the ones upon which the case must turn, are: (1) Did the defendants countermand their order of June 9 in apt time? If so, then the shipping of the engine and attachments, as was done, was without authority on plaintiff’s part. (2) Did Hennessy agree to unload the engine and deliver it to defendants on defendants’ farm? (3) Did Hennessy have authority to make such an agreement. We will consider these questions in the order named.

Free access — add to your briefcase to read the full text and ask questions with AI

Northwest Thresher Co. v. Kubicek, 118 N.W. 94, 82 Neb. 485, 1908 Neb. LEXIS 293 (Neb. 1908).

118 N.W. 94 (Northwest Thresher Co. v. Kubicek) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Pribil v. Ruther
262 N.W.2d 460 (Nebraska Supreme Court, 1978)
Stebel v. United States
69 F. Supp. 221 (Court of Claims, 1947)
Courtney Shoe Co. v. E. W. Curd & Son
134 S.W. 146 (Court of Appeals of Kentucky, 1911)