Northwest Environmental Defense Center v. Wood

947 F. Supp. 1371, 27 Envtl. L. Rep. (Envtl. Law Inst.) 20668, 1996 U.S. Dist. LEXIS 18518, 1996 WL 718165
CourtDistrict Court, D. Oregon
DecidedMarch 5, 1996
Docket95-1994-HO
StatusPublished
Cited by13 cases

This text of 947 F. Supp. 1371 (Northwest Environmental Defense Center v. Wood) is published on Counsel Stack Legal Research, covering District Court, D. Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Northwest Environmental Defense Center v. Wood, 947 F. Supp. 1371, 27 Envtl. L. Rep. (Envtl. Law Inst.) 20668, 1996 U.S. Dist. LEXIS 18518, 1996 WL 718165 (D. Or. 1996).

Opinion

ORDER

HOGAN, Chief Judge.

Plaintiffs bring this action challenging the Army Corps of Engineers’ decision to issue a permit allowing Hyundai Electronics of America to fill 10.4 acres of wetlands to accommodate a semiconductor fabrication plant in Eugene, Oregon. Plaintiffs argue that the issuance of .the permit violates the Clean Water Act, 33 U.S.C. § 1344, and that the Army Corps of Engineers’ decision not to prepare an Environmental Impact Statement with regard to the issuance of the permit violates the National Environmental Policy Act, 42 U.S.C. § 4321, et seq. Plaintiffs seek a preliminary injunction against the filling of the subject wetlands or, alternatively, a permanent injunction pending compliance with applicable laws and regulations (# 15). Defendants and defendant-intervenor Hyundai have filed cross-motions for summary judgment (# 30, # 32) as well as a motion to limit review to the administrative record (#29).

FACTS

Hyundai Electronics of America (Hyundai) entered into a contract with D.A.G. Trusts Partnership (DAG) to purchase a 205-acre parcel of land located in the Willow Creek Industrial Park in west Eugene. The Willow Creek site contains approximately 63.6 acres of wetlands. It is zoned for special light industrial use in the Eugene-Springfield Metropolitan General Plan. The site is within the area governed by the West Eugene Wetlands Plan (WEWP) but is not specifical *1375 ly addressed in the WEWP. The site is scheduled for inclusion in the "WEWP by July 31,1996. AR, vol. 1 at 22-23. 1

The Hyundai/DAG contract is contingent on DAG obtaining necessary permits, including a wetlands fill permit as required under the Clean Water Act (CWA). DAG submitted its initial application for such a permit to the Portland district of the United States Army Corps of Engineers (the Corps) on June 5, 1995, seeking approval to fill 34.7 of the 63.6 acres of wetlands.

The initial permit application sought to develop the semiconductor facility in three phases. Phase I consisted of a clean room manufacturing area, office space, central utilities, interior chemical storage and distribution, exterior bulk liquid gas storage, and parking. Phase II included facilities similar to those in phase I. Phase III would probably include facilities similar to phases I and II and would probably be comparable in size to phases I and II combined. AR, vol. 1 at 21.

The Corps solicited public comment through issuance of public notice on June 30, 1995. AR, vol. 1 at 52. The comment period was initially scheduled to end July 25, 1995, but was extended to September 5,' 1995. Public hearings were held August 16, 1995, and August 24, 1995. Colonel Timothy L. Wood, district engineer for the Corps, indicated at the August 24 hearing that “[a]ddi-tional information will be considered in the evaluation process up until the final decision is made.” AR, vol. 9 at 4296. During the process, the Corps received over 1200 letters as well as testimony from approximately 200 individuals. AR, vol. 1 at 50. A substantial amount of information, from both Hyundai and the public, was received after the official close of the public comment period. As all project changes subsequent to the close of the public comment period resulted in “reductions to wetland fills or potential impacts,” the Corps determined that “reinitia-ti[on] [of] the public review process ... is not required.” AR, vol. 1 at 52.

On December 20, 1995, the Corps issued wetlands fill permit number 95-00482, signed by Colonel Wood. In the decision document allowing' the permit, the Corps determined that the project purpose was to construct “a large semiconductor facility in the Eugene area.” AR, vol. 1 at 21. The Corps also found that ■

while the project is not water-dependent and includes the placement of fill in ... wetlands, it has been clearly demonstrated that there are no available, practicable alternatives having less adverse impact on the aquatic ecosystem and without other significant adverse environmental consequences that do not involve discharges into “waters of the United State's” or at other locations within these waters.

AR, vol. 1 at 62.

Finally, the Corps found that issuance of the permit was not contrary to the public interest and would not have a significant impact on the human environment, especially given the limitations and conditions imposed by the permit. AR, vol. 1 at 63-63; 65-70.

The permit limited and conditioned the project in. certain respects. It was issued only after Hyundai withdrew the phase III proposal and, thus, only authorized the first two phases. AR, vol. 1 at 22. The amount of wetlands to be filled was accordingly reduced from 34.7 to 10.4 acres. In addition, the permit required Hyundai to restore 13 acres of wetlands and enhance 6.9 acres of wet prairie lands. AR, vol. 1 at 29. The permit included 46 general and special conditions. AR, vol. 1 at 65-70.

DISCUSSION

I. Standards of Review

The Corps’ decisions to issue the wetlands fill permit and to forego an Environmental Impact Statement are subject to an arbitrary and capricious standard of review under the Administrative Procedure Act, 5 U.S.C. § 706. See also Marsh v. Oregon Natural Resources Council, 490 U.S. 360, 373-74, 109 S.Ct. 1851, 1859, 104 L.Ed.2d 377 (1989) (arbitrary and capricious standard applies to agency findings which involve agency expertise). Under this standard, an agency *1376 decision must be upheld unless it is “arbi-. trary, capricious, an abuse of discretion, or otherwise not in accordance with law.” 5 U.S.C. § 706(2). Although “inquiry into the facts is to be searching and careful, the ultimate standard of review is a narrow one. The court is not empowered to substitute its judgment for that of the agency.” Citizens to Preserve Overton Park, Inc. v. Volpe, 401 U.S. 402, 416, 91 S.Ct. 814, 828, 28 L.Ed.2d 186 (1971). The agency’s action may not be set aside so long as it has a “rational basis.” Bowman Transp., Inc. v. Arkansas-Best Freight System, Inc., 419 U.S. 281, 290, 95 S.Ct. 438, 444, 42 L.Ed.2d 447 (1974); Friends of the Earth v. Hintz, 800 F.2d 822, 831 (9th Cir.1986).

Summary judgment is appropriate “if the pleadings, depositions, answers to interrogatories, and admissions on file, together with affidavits, if any, show there is no genuine issue as to any material fact.” Fed.R.Civ.P.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Town of Abita Springs v. U.S. Army Corps of Engineers
153 F. Supp. 3d 894 (E.D. Louisiana, 2015)
John Jones, III v. National Marine Fisheries Serv
741 F.3d 989 (Ninth Circuit, 2013)
Gouger v. US Army Corps of Engineers
779 F. Supp. 2d 588 (S.D. Texas, 2011)
Florida Clean Water Network, Inc. v. Grosskruger
587 F. Supp. 2d 1236 (M.D. Florida, 2008)
Sierra Club v. United States Army Corps of Engineers
450 F. Supp. 2d 503 (D. New Jersey, 2006)
Great Rivers Habitat v. US Army Corps of Enginr.
437 F. Supp. 2d 1019 (E.D. Missouri, 2006)
Pennsylvania Trout v. Department of Environmental Protection
863 A.2d 93 (Commonwealth Court of Pennsylvania, 2004)
Alliance for Legal Action v. United States Army Corps of Engineers
314 F. Supp. 2d 534 (M.D. North Carolina, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
947 F. Supp. 1371, 27 Envtl. L. Rep. (Envtl. Law Inst.) 20668, 1996 U.S. Dist. LEXIS 18518, 1996 WL 718165, Counsel Stack Legal Research, https://law.counselstack.com/opinion/northwest-environmental-defense-center-v-wood-ord-1996.