Northwest Electric Co. of Ohio v. A.P. O'Horo Co. (In Re Northwest Electric Co. of Ohio)

84 B.R. 400, 1988 WL 26515
CourtUnited States Bankruptcy Court, W.D. Pennsylvania
DecidedMarch 28, 1988
Docket19-20782
StatusPublished
Cited by6 cases

This text of 84 B.R. 400 (Northwest Electric Co. of Ohio v. A.P. O'Horo Co. (In Re Northwest Electric Co. of Ohio)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, W.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Northwest Electric Co. of Ohio v. A.P. O'Horo Co. (In Re Northwest Electric Co. of Ohio), 84 B.R. 400, 1988 WL 26515 (Pa. 1988).

Opinion

OPINION

WARREN W. BENTZ, Bankruptcy Judge.

Issue

The issue is the date of transfer in this preference action brought under § 547 of the Bankruptcy Code.

*401 Facts

These three cases have a common factual background and a common issue and will therefore be discussed together. The plaintiff-debtor, Northwest Electric Company of Ohio (“Northwest”), was the electrical contractor on the Trumbull County, Ohio, Mosquito Creek Waste Water Treatment Plant. Trumbull County was the owner. All payments for work performed came from the Ohio Water Development Authority (“Authority”), a quasi-governmental agency formed by the State of Ohio to fund local waste water projects. Defendants, Ohio Edison Company (“Edison”) and A.P. O’Horo Company (“O’Horo”) were subcontractors under Northwest on the project.

Northwest became delinquent in its payments to both subcontractors and on May 19, 1986, Northwest executed an assignment in favor of Edison and on July 15, 1986, Northwest executed an assignment in favor of O’Horo. Northwest’s assignment to Edison purported to assign to Edison Northwest’s claim against Trumbull County for payment for future work to be performed by Northwest up to the $115,000 then owed by Northwest to Edison. The assignment to O’Horo contained similar terms, the amount owed to O’Horo being $54,765. Trumbull County and the Authority both were notified of the assignments and accepted same. Thus, both Edison and O’Horo considered themselves to be secured in that they would receive, up to the amounts owed them, future payments for future work performed by Northwest on the project.

Each assignment was an assignment of the entire account, but provided that it shall become null and void upon full payment of amounts due to O’Horo or Edison, respectively.

On December 5,1986, Northwest filed its Chapter 11 proceeding.

On account of work performed by Northwest on the Mosquito Creek Project during late September and the months of October and November, 1986, the Authority made the following payments pursuant to the assignments:

November 5, 1986- $24,986.81 to Edison

November 5, 1986- $ 4,240.55 to O’Horo

December 17, 1986-$ 5,922.96 to O’Horo

(Other payments were made earlier, but were for work performed outside the preference period and were not attacked by the debtor.)

The debtor brought the within adversary proceedings to recover the above payments, asserting that they are preferences under § 547 of the Bankruptcy Code. The debtor also asserts that the December 17, 1986 payment to O’Horo, having been made after the filing of the Chapter 11 petition, is recoverable under § 549.

Discussion

Northwest makes four arguments:

(1) Edison does not have a mechanic’s lien on the fund from which it was paid, because it did not file a sworn and itemized statement in accordance with the Ohio Mechanic’s Lien Law, and the Mechanic’s Lien Law is the exclusive method by which Edison could obtain a lien.

(2) Edison is not a secured creditor under the Ohio Uniform Commercial Code, because it failed to file financing statements with the appropriate public offices.

(3) The transfer did not take place on May 19,1986 (the date of the assignment to Edison) or July 15, 1986 (the date of the assignment to O’Horo) because Northwest had not yet acquired the right to payment of the proceeds assigned because its contractual obligations prerequisite to such payments had not yet been completed; and that the transfer in fact took place on the date of payment, i.e., November 5, 1986 and December 17, 1986.

(4) Alternatively, the date or dates of transfer were the dates upon which Northwest earned the right to payment under its contract with Trumbull County.

The defendants, Edison and O’Horo, argue that upon the execution of the assignments, the property covered thereby, and the money ultimately transferred, was no longer property of the debtor; that as of the date of the execution of the assignments, the title to the property which *402 Northwest seeks was irrevocably transferred, never became property of the debtor, and the money paid is not recoverable under § 547. Further, the assignments were executed four and one-half months and six and one-half months prior to the bankruptcy, well outside the 90 day preference period. Also, each assignment, well prior to the 90 day preference period, was, in fact, a transfer of complete ownership, stripping Northwest of all interest in and right to payments under the assignment agreement.

Edison also argues that it gave further consideration for the assignment, in that the assignment was given “to induce Ohio Edison to energize the project” and that such language was a part of the assignment.

O’Horo also argues that by signing the assignment agreement, Northwest was discharged of its obligation to O’Horo.

Defendants also argue that even if the assignment agreement was not a complete assignment of ownership, and was only a security interest, it was nevertheless perfected without the filing of a financing statement pursuant to Ohio Revised Code § 1309.21(A)(5) [UCC 9-302(l)(e) ] since the assignment to each subcontractor was not a “significant part of the outstanding accounts of the assignor” as provided in the UCC.

Nothing persuasive is shown to us to indicate that the Ohio Mechanic’s Lien Law is the exclusive method of obtaining a lien or a prior right to a particular fund. Hence, the argument of Northwest that these subcontractors may establish their claims only under the Ohio Mechanic’s Lien Law, and not otherwise, is not determinative.

Edison’s argument that the assignment was given as consideration to induce Edison to energize the project is also without merit. Even if we were to assume the assignment was given as consideration, although we express our reservations in light of the pre-existing duty rule, the consideration was a promise to energize the project and was given at the time the assignment was executed. Thus, no new value was exchanged when the transfer occurred during the preference period. In light of the foregoing, we fail to see the relevance of this argument other than an attempt to bring the transfer within an exception listed in § 547(c).

The contention of the defendants that they became the outright owners of the account is also disregarded since the plain terms of the assignment agreements state that the assignments are only valid to the extent of the claim of the subcontractor against Northwest even though both assignments are otherwise blanket assignments of the entire claim of Northwest against the owner. It is quite clear and we find that the assignments were for security purposes.

The court will not determine whether the security interests were perfected without the filing of financing statements on these facts. The O’Horo assignment and certain interrogatories indicate that the owner was indebted to Northwest in the amount of $169,114.05 as of July 15, 1986. However, the May 19, 1986 assignment to Edison indicated the balance due to be $140,000.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
84 B.R. 400, 1988 WL 26515, Counsel Stack Legal Research, https://law.counselstack.com/opinion/northwest-electric-co-of-ohio-v-ap-ohoro-co-in-re-northwest-electric-pawb-1988.