Northwest Boring Company, Inc. v. Admiral Insurance Company

CourtDistrict Court, W.D. Washington
DecidedOctober 21, 2025
Docket2:24-cv-01310
StatusUnknown

This text of Northwest Boring Company, Inc. v. Admiral Insurance Company (Northwest Boring Company, Inc. v. Admiral Insurance Company) is published on Counsel Stack Legal Research, covering District Court, W.D. Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Northwest Boring Company, Inc. v. Admiral Insurance Company, (W.D. Wash. 2025).

Opinion

1 2 3 4

5 6 7 UNITED STATES DISTRICT COURT 8 WESTERN DISTRICT OF WASHINGTON AT SEATTLE 9 10 NORTHWEST BORING COMPANY, CASE NO. C24-1310 MJP INC., 11 ORDER ON CROSS-MOTIONS FOR Plaintiff, SUMMARY JUDGMENT 12 v. 13 ADMIRAL INSURANCE COMPANY, 14 Defendant. 15

16 17 This matter comes before the Court on Plaintiff’s Motion for Partial Summary Judgment 18 (Dkt. No. 28-1) and Defendant’s Motion for Summary Judgment (Dkt. No. 29). Having reviewed 19 the Motions, the Oppositions (Dkt. Nos. 32 & 35), the Replies (Dkt. Nos. 33 & 39), and all 20 supporting materials, the Court DENIES both Motions. 21 BACKGROUND 22 Plaintiff Northwest Boring Company (NWB) asserts that Defendant Admiral Insurance 23 Company (Admiral) failed to defend it against claims arising out of NWB’s microtunneling work 24 on a water quality project in Seattle. NWB pursues breach of contract and extracontractual 1 claims against Admiral. Admiral admits that there is coverage and that it would have defended 2 against the claims made against NWB, but contends that it cannot face liability because NWB 3 failed to timely tender the counterclaim giving rise to NWB’s liability and violated its 4 contractual duty to cooperate with Admiral. To unpack these arguments, the Court reviews the

5 timeline of events and the communication between the Parties. 6 A. NWB’s Microtunneling Work 7 NWB was hired by Lane Construction Co. as a subcontractor for the City of Seattle’s 8 Ship Canal Water Quality Project. (Second Amended Complaint ¶ 5 (Dkt. No. 19).) Starting in 9 2021, NWB performed microtunneling for the project and experienced two setbacks. (Deposition 10 of Dennis Molvik at 7 (Ex. B to the Declaration of Jared Kiess) (Dkt. No. 31-2).) First, in 11 September 2021, a joint on a pipe NWB installed burst and caused a catastrophic failure that 12 delayed NWB’s work until November 2022. (Id. at 8-10.) Second, on December 8, 2022, a 13 sinkhole was found near NWB’s tunneling site, causing the worksite to close after the City 14 issued a stop-work order. (Id. at 11, 21-24; Kiess Decl. Exs. E-G (Dkt. Nos. 31-5, 31-6, 31-7)

15 (City stop work orders and Lane’s notice of holding NWB responsible).) Lane blamed NWB for 16 the costs incurred in filling the sinkhole and for the delay. (Kiess Decl. Exs. E-G.) 17 The December 8th sinkhole is the only incident relevant to the present dispute, primarily 18 because Admiral’s commercial general policy was only in force between June 1, 2022 to June 1, 19 2023. (SAC ¶ 6.) 20 B. NWB Informs Admiral of the December 2022 Sinkhole 21 Immediately after the December 8th sinkhole was discovered, Lane gave notice to NWB 22 that it would “be held responsible for all additional cost and schedule impact caused by this event 23 if it is determined to be NWB’s fault.” (Molvik Decl. Ex. C (Dkt. No. 28-5).) Eleven days later,

24 1 NWB’s insurance broker contacted Admiral to notify it of the “12/8/22 sinkhole discovered at 2 Fremont, WA jobsite” and to ask Admiral to “Please open new potential claim and contact 3 insured, per below preliminary information.” (Ex. B to the Declaration of Ruth Cutuli (Dkt. No. 4 30-2).) That same day (December 20, 2022), Admiral retained a third-party adjuster, McLarens,

5 to investigate the claim, and an individual named Crockett Blanchard promptly contacted NWB 6 to discuss. (Cutuli Decl. Exs. C & D (Dkt. No. 30-3, 30-4).) Blanchard prepared a preliminary 7 report dated January 6, 2023, which indicated that “[t]here are currently no damages claimed by 8 any party” and that there had been no tender. (Cutuli Decl. Ex. E (Dkt. No. 30-5).) NWB paid 9 Blanchard for his work, as this was part of the deductible. (Molvik Decl. Ex. D (Dkt. No. 28-6).) 10 And on January 10, 2023, Admiral directed McLarens to close the file “[a]s no claim is being 11 presented[.]” (Hayes Decl. Ex. C at 9-10.) Admiral did not inform NWB that it closed the file. 12 C. Lane and NWB Dispute Impacts Related to December 8th Sinkhole Event 13 In early 2023, Lane informed NWB that it expected about $20,000 to $25,000 in costs 14 associated with the sinkhole. (Kiess Decl. Ex. K (Dkt. No. 31-1).) This sum increased as Lane

15 issued “Change Order 04,” which identified a variety of costs it claimed to have incurred as a 16 result of the December 2022 sinkhole for which it blamed NWB. (Molvik Decl. Ex. E (Dkt. Nos. 17 28-7).) NWB did not necessarily dispute liability for the delay and costs associated with the 18 December 8th sinkhole, but it demanded that Lane provide it with a change order so that it could 19 pursue an incentive payment from the City. (Kiess Decl. Ex. O (Dkt. No. 31-15).) Lane did not 20 comply with NWB’s request. 21 In August 2023, NWB decided to file suit against Lane in an effort to obtain 22 approximately $3.1 million that Lane had withheld from NWB, though these funds were not 23 linked exclusively to the December 2022 sinkhole (aka Change Order 04). (Kiess Decl. Ex. Q

24 1 (Dkt. No. 31-17).) The allegations against Lane were made in existing litigation between NWB 2 and the pipe manufacturer whose joint failed in 2021. Rather than file a separate suit against 3 Lane, NWB added Lane as a party to its Third Amended Complaint. (Kiess Decl. Ex. Q (Dkt. 4 No. 31-17).)

5 In response to NWB’s claim, Lane filed a counterclaim against NWB on September 7, 6 2023. (Molvik Decl. Ex. F (Dkt. No. 28-8).) In the counterclaim, Lane alleged that NWB 7 breached the construction agreement by installing the pipe which failed and caused damage. (Id. 8 at 17.) Lane identified Change Order 04, which was specific to the December 2022 sinkhole, as 9 one of several change orders that it “incurred due to NWB[’s] . . . failure to perform” according 10 to the construction agreement. (Id.) And it claimed over $4 million in additional costs it incurred 11 as a result. (Id.) 12 D. NWB Provides Admiral Late Notice of its Dispute with Lane 13 Until April 2024, NWB did not apparently reach out to Admiral to discuss the December 14 8th sinkhole or the counterclaim filed against it, and Admiral similarly did not reach out to NWB

15 to follow up on the sinkhole. Admiral’s claim file shows no entries between January 2023 and 16 April 8, 2024. (Hayes Decl. Ex. C at 9 (Dkt. No. 27-3).) On April, 2024, Admiral received 17 “[r]eport from government” and reopened the claim. (Id.) The claim file also shows Admiral 18 reopened the claim in April 2024 after it reviewed “communications from the insured as they 19 relate to this claim previously tendered regarding a sinkhole” and that other information from 20 Lane “may indicate an ongoing loss[.]” (Hayes Decl. Ex. C at 10 (Dkt. No. 27-3).) This is 21 consistent with other documents in the record showing that in April 2024, Admiral reopened the 22 claim for the December 8, 2022 sinkhole after NWB notified its broker that Lane was making 23 new monetary demands related to a new sinkhole at or near the same site. (See Cutuli Decl. Ex.

24 1 G (Dkt. No. 30-7).) McLarens also reopened its file and continued to work with NWB through 2 the process of assessing the new sinkhole. (See Cutuli Decl. Exs. G & H (Dkt. Nos. 30-7 & 30- 3 8).) 4 On April 12, 2024, NWB’s Molvik reached out to both McLarens and Admiral to notify

5 them that NWB was still awaiting Admiral’s coverage determination on the December 2022 6 sinkhole. (Kiess Decl. Ex. R (Dkt. No. 31-18).) Molvik invited Admiral to participate in the 7 April 23, 2024 mediation, where NWB and Lane were “mediat[ing] the claims between them— 8 including the sinkhole claim[.]” (Id.) Molvik did not identify that the claims were in litigation or 9 forward on a copy of Lane’s counterclaim. Nor did NWB ask for any defense to the 10 counterclaim.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Unigard Insurance v. Leven
983 P.2d 1155 (Court of Appeals of Washington, 1999)
Felice v. St. Paul Fire & Marine Insurance
711 P.2d 1066 (Court of Appeals of Washington, 1985)
Oregon Automobile Insurance v. Salzberg
535 P.2d 816 (Washington Supreme Court, 1975)
Campbell v. Campbell
143 P.2d 534 (Washington Supreme Court, 1943)
Tran v. State Farm Fire & Casualty Co.
136 Wash. 2d 214 (Washington Supreme Court, 1998)
Coventry Associates v. American States Insurance
136 Wash. 2d 269 (Washington Supreme Court, 1998)
Staples v. Allstate Insurance
295 P.3d 201 (Washington Supreme Court, 2013)
Griffin v. Allstate Insurance
108 Wash. App. 133 (Court of Appeals of Washington, 2001)
Sprint Corp. v. Dep't of the Interior
356 F. Supp. 3d 12 (D.C. Circuit, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
Northwest Boring Company, Inc. v. Admiral Insurance Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/northwest-boring-company-inc-v-admiral-insurance-company-wawd-2025.