Northwest Bank & Trust Company v. Pershing Hill Lofts, LLC, John M. Carroll, and John G. Ruhl

Supreme Court of Iowa·Decided February 20, 2026·No. 22-1941·Published

Opinion

In the Iowa Supreme Court No. 22–1941

Submitted November 12, 2025—Filed February 20, 2026 Northwest Bank & Trust Company, Appellant,

vs.

Pershing Hill Lofts, LLC, John M. Carroll, and John G. Ruhl, Appellees.

On review from the Iowa Court of Appeals.

Appeal from the Iowa District Court for Scott County, Tom Reidel (summary judgment) and Meghan Corbin (trial), judges.

The defendants seek further review of a court of appeals decision that reversed the district court’s grant of summary judgment on a breach of contract claim and reversed a jury verdict on a fraud claim after finding evidence had been erroneously excluded. Decision of the Court of Appeals Vacated; District Court Judgment Affirmed.

McDermott, J., delivered the opinion of the court, in which all participating justices joined. Waterman, J., took no part in the consideration or decision of the case.

David T. Bower (argued) and Dana W. Hempy of Nyemaster Goode, P.C., Des Moines, and Candy K. Pastrnak of Pastrnak Law Firm, P.C., Davenport, for appellant.

Ian J. Russell (argued) of Lane & Waterman LLP, Davenport, for appellees.

McDermott, Justice.

A bank and a developer signed a conditional financing proposal. The proposal included an exclusivity clause requiring the developer to work solely with the bank in exchange for the bank’s due diligence efforts. When one of the proposal’s conditions failed to materialize, the bank proposed either to “kill the deal” or to proceed under different terms. The developer instead sought financing from other lenders without notifying the bank, prompting the bank to sue for breach of contract and fraud.

The district court granted summary judgment in the developer’s favor on the breach of contract claim, concluding that the proposal was an unenforceable agreement to agree or, alternatively, that it had terminated when the condition failed. The court also excluded the proposal from the trial on the fraud claim. The jury found for the developer. The bank appealed, and the court of appeals reversed. We granted further review.

I.

In 2012, Pershing Hill Lofts, LLC, purchased a building in Davenport for redevelopment. Although Quad Cities Bank initially loaned funds for the purchase, in 2013, Pershing Hill refinanced the loan with Northwest Bank & Trust Company. Pershing Hill’s managers, John Carroll and John Ruhl, later began discussions with Northwest about a construction loan. On August 31, 2015, Pershing Hill and Northwest signed a document titled “Proposed Financing for Pershing Hill Lofts, LLC Summary of Principal Terms.”

The financing proposal stated that it was a “summary of terms that may lead to a commitment to lend, subject to satisfactory completion of due diligence, and a subsequent Commitment Letter.” The “proposed transaction” included “the sale of certain federal and state tax credits relating to the Project to one or

more third party investors,” with a $5 million bridge loan to be repaid from “the sale or realization” of the tax credits.

The financing proposal included a section titled “Due Diligence” that listed twenty items Northwest “will need as part of necessary due diligence, and as a condition to making the Interim Loans available.” The list included state and federal tax credit awards, and it specifically included “Grayfield Tax Credit award documentation.”

The final paragraph of the financing proposal includes an exclusivity clause in favor of Northwest as lender on the project. The paragraph stated in full:

This is a summary of terms that may lead to a commitment to lend, subject to satisfactory completion of due diligence, and a subsequent Commitment Letter. Acceptance below assures Lender of Borrower’s exclusive consideration as “Lender” in exchange for the expense in time and travel of the proposed due diligence. This Summary of Principal Terms will expire if not signed by September 4, 2015.

The document bears signatures by Northwest’s president, and by Carroll and Ruhl for Pershing Hill.

In October 2015, Pershing Hill learned that, through no fault of its own, it had not been awarded the Grayfield tax credits, resulting in an $800,000 funding gap. On December 11, Northwest’s president sent an email to Pershing Hill stating in relevant part:

Without the Grayfield[] credits, [our participant bank] wants $800,000 more in equity. I have devised a plan to alter the current structure so as not to require this equity up front, but it costs Northwest Bank significant dollars. Moreover, it encompasses substantially more work for me. Even assuming we can resolve the first three issues [discussed earlier in the email], this issue alone presents three options[:] (i) kill the deal, (ii) raise $160,000 cash per partner or (iii) implement my solution at a cost of about $75,000. I know that is a lot of money, but if I am paid 1/3 at closing, I will defer the other 2/3 until construction is completed.

Would you like to meet? I think we can fix these things, but it will take my time and partnership money. Either way, it is now obvious there is no way we will close this year. Please let me know.

Soon after, on December 15, Pershing Hill began looking for an alternative lender to finance the project. But Pershing Hill also continued to communicate with Northwest. Northwest claims that between December and April, Pershing Hill made statements that led Northwest to believe it would still be the lender on the project. In late April or early May 2016, Pershing Hill secured financing with a different bank and informed Northwest.

Northwest filed a lawsuit against Pershing Hill for breach of contract and Carroll and Ruhl for negligent misrepresentation and fraud. The district court granted Pershing Hill’s motion for summary judgment on the contract claim, holding that the financing proposal was an unenforceable agreement to agree and that the failure to obtain tax credits was a failed condition precedent that discharged Pershing Hill’s exclusivity duty. The district court also granted summary judgment in Carroll and Ruhl’s favor on the negligent misrepresentation claims, but it denied summary judgment on the fraud claims.

Before the trial on the fraud claims, the district court granted a motion in limine excluding the financing proposal. The district court concluded that in light of its summary judgment ruling, the financing proposal’s probative value was outweighed by the danger that the jury would confuse it for a binding contract when considering the fraud claims. The jury ultimately entered a verdict in Carroll and Ruhl’s favor.

Northwest appealed. We transferred the case to the court of appeals.

Northwest argued that the district court erred in granting summary judgment on the breach of contract claim and that it abused its discretion by excluding the financing agreement (and any reference to it) in the fraud trial. The court of

appeals reversed, holding that the exclusivity clause was enforceable and not subject to a condition precedent. Given this conclusion, the court of appeals further held that the district court erred in excluding the financing proposal in the fraud trial. Pershing Hill sought further review, which we granted.

II.

Free access — add to your briefcase to read the full text and ask questions with AI

Northwest Bank & Trust Company v. Pershing Hill Lofts, LLC, John M. Carroll, and John G. Ruhl, (iowa 2026).

Northwest Bank & Trust Company v. Pershing Hill Lofts, LLC, John M. Carroll, and John G. Ruhl (Northwest Bank & Trust Company v. Pershing Hill Lofts, LLC, John M. Carroll, and John G. Ruhl) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Royal Indemnity Co. v. Factory Mutual Insurance Co.
786 N.W.2d 839 (Supreme Court of Iowa, 2010)
Whalen v. Connelly
545 N.W.2d 284 (Supreme Court of Iowa, 1996)
Miller v. Marshall County
641 N.W.2d 742 (Supreme Court of Iowa, 2002)
Mosebach v. Blythe
282 N.W.2d 755 (Court of Appeals of Iowa, 1979)
Air Host Cedar Rapids, Inc. v. Cedar Rapids Airport Commission
464 N.W.2d 450 (Supreme Court of Iowa, 1990)
Khabbaz v. Swartz
319 N.W.2d 279 (Supreme Court of Iowa, 1982)