Northwest and Intermountain Power Producers v. PGE

480 P.3d 981, 308 Or. App. 110
CourtCourt of Appeals of Oregon
DecidedDecember 23, 2020
DocketA167707
StatusPublished
Cited by1 cases

This text of 480 P.3d 981 (Northwest and Intermountain Power Producers v. PGE) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Northwest and Intermountain Power Producers v. PGE, 480 P.3d 981, 308 Or. App. 110 (Or. Ct. App. 2020).

Opinion

Argued and submitted September 24, 2019, petition for judicial review dis- missed as moot December 23, 2020

NORTHWEST AND INTERMOUNTAIN POWER PRODUCERS COALITION, Community Renewable Energy Association, Renewable Energy Coalition, and The Public Utility Commission of Oregon, Respondents, v. PORTLAND GENERAL ELECTRIC COMPANY, Petitioner. Public Utility Commission of Oregon UM1805; A167707 480 P3d 981

In 2005, the Public Utility Commission of Oregon (PUC) issued Order 05-584. In that order, it adopted a policy requiring standard contracts for purchase of electricity from qualifying facilities to, among other things, set fixed prices for the purchase of electricity for the first 15 years of every 20-year contract. Order 05-584 arguably left ambiguous whether the fixed-price term ran from the date of contract execution or from the first day of power supply. Following the order, the price term in Portland General Electric’s (PGE) standard contracts ran from the date of contract execution, and complainants initiated an action to require PGE’s fixed-price terms to run from the first day of power supply. On review, the PUC declined to interpret PGE’s already approved contracts but clarified that Order 05-584 required fixed-price terms to run from the date of power supply. PGE petitioned for judicial review of the PUC’s decision, but, during the judicial- review proceeding, the PUC promulgated OAR 860-029-0120, which requires that fixed-price terms commence from the date of power supply. Complainants contend that the PUC’s rulemaking has rendered this appeal moot. Held: The PUC’s rulemaking mooted the appeal; no ruling on any of the issues PGE raised before the Court of Appeals would have had a practical effect on PGE’s rights or obligations. Petition for judicial review dismissed as moot.

Anna M. Joyce argued the cause for petitioner. Also on the briefs were Dallas S. DeLuca, Anit K. Jindal, and Markowitz Herbold PC. Nadia H. Dahab argued the cause for respondents Northwest and Intermountain Power Producers Coalition, Community Renewable Energy Association, and Renewable Cite as 308 Or App 110 (2020) 111

Energy Coalition. Also on the answering brief were Steven C. Berman, Keil M. Mueller, Stoll Stoll Berne Lokting & Shlachter PC, Irion A. Sanger, and Sanger Law PC. Also on the supplemental brief were Steven C. Berman, Keil M. Mueller, Stoll Stoll Berne Lokting & Shlachter PC, Irion A. Sanger, and Sanger Thompson PC. Jordan R. Silk, Assistant Attorney General, argued the cause for respondent The Public Utility Commission of Oregon. On the answering brief were Ellen F. Rosenblum, Attorney General, Benjamin Gutman, Solicitor General, and Keith L. Kutler, Assistant Attorney General. On the supple- mental brief were Ellen F. Rosenblum, Attorney General, Benjamin Gutman, Solicitor General, and Jordan R. Silk, Assistant Attorney General. Before Lagesen, Presiding Judge, and DeVore, Judge, and Powers, Judge. LAGESEN, P. J. Petition for judicial review dismissed as moot. 112 Northwest and Intermountain Power Producers v. PGE

LAGESEN, P. J. This dispute about certain contracts to buy and sell electric power is before us on Portland General Electric Company’s (PGE) petition for judicial review under ORS 183.482 of a final order of the Public Utility Commission of Oregon (PUC). We conclude that it has become moot by vir- tue of subsequent rulemaking by the PUC. Accordingly, we dismiss the petition. At the core of this case are the PUC’s requirements for standard contracts for the purchase of electricity from operators known as “qualifying facilities” or “QFs.” In 2005, to implement the Public Utility Regulatory Policies Act, 16 USC § 824a-3, the PUC issued Order 05-584. In that order, the PUC adopted a policy requiring standard contracts for purchase of electricity from QFs to (1) have 20-year terms, (2) set fixed prices for the purchase of electricity for the first 15 years of the term, and (3) provide for market prices for the last five years of the contract term. What Order 05-584 arguably left ambiguous was the start date for the period of 15 years of fixed prices: Did it run from the date of contract execution or did it start when the QF became operational and began supplying power under the contract? Although Order 05-584 prescribed stan- dard terms for contracts with QFs, it did not prescribe a standard form for such contracts. Following the issuance of Order 05-584, some power companies provided in their standard contracts with QFs that the 15-year fixed-price period commenced when the QF became operational and began to supply power. PGE appar- ently took a different approach.1 Its standard contracts, in its view, allowed for the 15-year period to start on the date of contract execution. All of PGE’s standard contracts were filed with, and approved by, the PUC. 1 We say “apparently” because the parties dispute how PGE’s previous stan- dard contracts should be read. The PUC did not reach the issue in this proceed- ing, noting only that “PGE’s approved standard contract filings * * * may have limited the availability of fixed prices to the first fifteen years measured from contract execution,” and, further, that if the contracts did in fact do so, “PGE cannot be found to have been in violation of our orders” because the PUC had approved those contracts. Cite as 308 Or App 110 (2020) 113

In December 2016, the Northwest and Intermountain Power Producers Coalition, the Community Renewable Energy Association, and the Renewable Energy Coalition (collectively, complainants) initiated this complaint proceed- ing against PGE under ORS 756.500. They requested that (1) the PUC order PGE “to cease and desist * * * openly dis- puting that it must offer 15 years of fixed prices from the QF’s operation date,” which is what complainants alleged the PUC orders required; (2) the PUC declare that PGE’s standard contract “requires payment by PGE at fixed prices for 15 years after the QF’s operation date rather than merely 15 years after the time of contract execution, unless express language is inserted by the QF that demon- strates a contrary intent”; (3) in the alternative to the first two forms of relief requested, order “PGE to file revised standard contracts clearly stating that the 15 years of fixed prices run from the commercial operation date”; and (4) the PUC order any additional relief “deem[ed] necessary” by the PUC. Although it took a series of three orders,2 the PUC ultimately resolved the case by leaving the past murky and making the future clear. As for the past, the PUC declined to interpret PGE’s previously approved standard contracts. Consequently, it did not determine the date on which the 15-year fixed-price term began under them. Relatedly, the PUC declined to determine whether PGE’s past standard contracts complied with Order 05-584, explaining that the agency’s approval of them meant that PGE could not be found to be in violation of its orders. As for the future, the PUC explained how things should work going forward. It clarified that its policy in Order 05-584 should be understood “to explicitly require standard

2 After the PUC issued the final order on review, Order No. 17-256, one of the complainants requested rehearing or reconsideration and, in Order No. 17-465, the PUC denied that request but “amend[ed] and clarif[ied] Order No. 17-256.” Then, PGE requested rehearing or reconsideration and, in Order No. 18-079, the PUC denied that request but again made clarifying statements. For purposes of this opinion, general references to the order on review are to Order No. 17-256, as amended and clarified in the two later orders. 114 Northwest and Intermountain Power Producers v. PGE

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kragt v. Board of Parole
529 P.3d 1019 (Court of Appeals of Oregon, 2023)

Cite This Page — Counsel Stack

Bluebook (online)
480 P.3d 981, 308 Or. App. 110, Counsel Stack Legal Research, https://law.counselstack.com/opinion/northwest-and-intermountain-power-producers-v-pge-orctapp-2020.