Northern States Power Co. v. International Telephone & Telegraph Corp.

550 F. Supp. 108, 35 U.C.C. Rep. Serv. (West) 1124, 1982 U.S. Dist. LEXIS 15573
CourtDistrict Court, D. Minnesota
DecidedOctober 27, 1982
DocketCiv. 4-80-280
StatusPublished
Cited by13 cases

This text of 550 F. Supp. 108 (Northern States Power Co. v. International Telephone & Telegraph Corp.) is published on Counsel Stack Legal Research, covering District Court, D. Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Northern States Power Co. v. International Telephone & Telegraph Corp., 550 F. Supp. 108, 35 U.C.C. Rep. Serv. (West) 1124, 1982 U.S. Dist. LEXIS 15573 (mnd 1982).

Opinion

MEMORANDUM OPINION AND ORDER

DIANA E. MURPHY, District Judge.

Plaintiff Northern States Power Co. (NSP) brings this action for damages against defendant International Telephone and Telegraph Corp. (ITT) alleging breach of warranties, contract breach, misrepresentation, strict liability in tort, 1 negligence, and fraudulent inducement to contract. Diversity jurisdiction is alleged under 28 U.S.C. § 1332. The matter comes before the court on ITT’s motion to dismiss NSP’s tort claims (Counts III, IV, V, and VI of the Amended Complaint) for failure to state a claim upon which relief can be granted and for partial summary judgment dismissing NSP’s claims for consequential damages.

Factual Background

NSP contracted with Meyer Industries of Red Wing, Minnesota (Meyer), a division of ITT. 2 Meyer was to manufacture, and NSP to buy, certain 16,000 ft. lb. screw anchors and extensions for use in the installation and erection of power line towers by contract was negotiated in Minnesota. It was largely executed in Minnesota, but the screw anchors were assembled in Wisconsin.

The screw anchors were to be emplaced in the ground and attached by guy wires to a point near the top of a power line tower. Four anchors were to be placed around each tower to hold the tower firmly in place. Each screw anchor consisted of 10' long lead sections capable of being augured into the ground. Extensions either 5' or 10' long could be added so that the extended anchor was emplaced deeply enough into the ground to adequately anchor the towers. Numerous extensions could be added if necessary. Each anchor extension had a coupling welded to one end to attach to a connecting section of anchor by bolting them together.

On June 9,1978, NSP sent a “Request for Quotation” to Meyer and others for the *110 manufacture of the screw anchors. Meyer responded with a proposal (Roberts Affidavit, Ex. A) on July 6, 1978, which included an attachment entitled “Provisions of Proposal.” This provided in part:

2) Reference RFQ Form 3 , Additional Instructions, Section 1, Paragraph 6. “In accepting an order, Seller/Contractor agrees ... ”. Delete this paragraph and replace with Item 16, Meyer Industries Warranty and Limitation of Liability Clause.

An attached document, entitled “Terms and Conditions of Sale. Meyer Industries.”, contained “Item 16” which states in part:

(16) WARRANTY AND LIMITATION OF LIABILITY
Meyer Warrants for one (1) year that all Products (a) are designed in accordance with generally accepted engineering practice, (b) will withstand destruction test loads to the extent of the calculated loads of yield stress the Products are designed to withstand, (c) will be fabricated in accordance with drawings furnished by Meyer and approved by Buyer, and (d) are free from defects in materials and workmanship.”
Meyer’s liability for any breach of this warranty shall be limited solely to job site replacement or repair, at the sole option of Meyer, of any defective part or parts, during a period of one (1) year from the date of shipment, providing the Product is properly installed and is being used as originally intended.
IT IS EXPRESSLY AGREED THAT THIS SHALL BE THE SOLE AND EXCLUSIVE REMEDY OF THE BUYER. UNDER NO CIRCUMSTANCES SHALL MEYER BE LIABLE FOR ANY COSTS, LOSS, EXPENSE, DAMAGES, SPECIAL DAMAGES, INCIDENTAL DAMAGES OR CONSEQUENTIAL DAMAGES ARISING DIRECTLY OR INDIRECTLY FROM THE USE OF THE PRODUCTS. WHETHER BASED UPON WARRANTY, CONTRACT, NEGLIGENCE OR STRICT LIABILITY.

After contract discussions in July and August of 1978 (during which no discussion of the limitation of liability took place), NSP issued a “Purchase Order” on August 17, 1978 which made no specific mention of the liability limitations of Meyer’s proposal. It did contain the general reference “Confirming Verbal Order of 8-11-78 Per Your Proposal # 780049 of 7-16-78.” In response, Meyer issued a “Sales Acknowledgment” showing an “acceptance date” of September 5, 1978 and providing a statement of the “Basis of Acceptance” which included the “Meyer Terms and Conditions of Sale as stated in Proposal 780049 dated July 6, 1978.” On the reverse side of the acknowledgment appeared the “Terms and Conditions of Sale. Meyer Industries.” Among those listed was “Item 16.” NSP made no additional response, and the parties proceeded to carry out the contract.

In December, 1978, the screw anchors were manufactured and in February and March of 1979, about 1,000 were emplaced in the ground by NSP contractors. About five months later, aluminum power line towers were flown into place and attached by guy wires to the anchors.

In late September, shortly after the guy wires were tightened and the installation completed, four towers fell to the ground. In each case a coupling at the end of a screw anchor extension had come apart at the weld.

NSP asserts that Meyer was immediately apprised of the fallen towers and that it learned shortly thereafter that tests conducted by Twin City Testing showed the anchors were defective. NSP claims Meyer failed to take remedial action at its own cost and denied that the anchors were defective.

Two or three weeks after the towers fell, NSP determined that all of the previously installed screw anchors needed repair by replacing the welded couplings with a bolted connector. NSP had contractors remove each anchor and had various other contractors, including defendant, replace the welded couplings. The anchors were then reinstalled.

*111 NSP claims a total cost of repair of $2,404,016, including approximately $100,-000 in cost to repair the damaged towers. The total cost breaks down as follows: NSP’s own labor, transportation and equipment rental costs $148,647; contract labor costs for anchor removal, repair of damaged towers, transportation and installation of modified anchors — $731,093; material rework including material costs, heat treatment, testing, galvanizing, transportation — • $316,545; contract cost with ITT for reworking — $207,731. NSP seeks to recover these costs, together with interest, costs, and attorney’s fees in this lawsuit.

Discussion

1. Motion to Dismiss Plaintiffs Tort Claims

ITT bases its motion to dismiss plaintiff’s tort claims upon the ground that Superwood Corporation v. Siempelkamp Corporation, 311 N.W.2d 159 (Minn.1981), bars recovery of tort damages for actions arising from a commercial transaction primarily involving economic loss. This decision of the Minnesota Supreme Court is being frequently cited for a variety of propositions. Its import and precedential value are a topic of debate. 4

Superwood

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
550 F. Supp. 108, 35 U.C.C. Rep. Serv. (West) 1124, 1982 U.S. Dist. LEXIS 15573, Counsel Stack Legal Research, https://law.counselstack.com/opinion/northern-states-power-co-v-international-telephone-telegraph-corp-mnd-1982.