Northern Pacific Railway Co. v. Union Lumber Co.

137 P. 306, 76 Wash. 563, 1913 Wash. LEXIS 1858
CourtWashington Supreme Court
DecidedDecember 5, 1913
DocketNo. 11209
StatusPublished
Cited by2 cases

This text of 137 P. 306 (Northern Pacific Railway Co. v. Union Lumber Co.) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Northern Pacific Railway Co. v. Union Lumber Co., 137 P. 306, 76 Wash. 563, 1913 Wash. LEXIS 1858 (Wash. 1913).

Opinions

Mount, J.

This appeal is from an award of damages in a condemnation proceeding.

The Northern Pacific Railway Company brought the action to condemn a portion of an easement for its line of railway across the logging road of the Union Lumber Company, in Thurston county. After the action was brought, the trial court, upon a hearing, adjudged the public use and necessity for the taking of a portion of the easement by the railway company. The Union Lumber Company thereupon, by certiorari in this court, reviewed the decree of necessity and public use, and we held that the Northern Pacific Railway Company might, by condemnation, proceed to take a portion of the easement of the lumber company by constructing an overhead crossing for the use of the lumber company so long as the latter company should see fit to operate its logging road. Thereafter the question of the amount of damages to the lumber company was tried to the court and a jury. A verdict was,returned in favor of the lumber company for $8,000, and that company prosecutes this appeal.

[565]*565A large number of errors are assigned in the appellant’s brief, several of which it will not be necessary to notice by reason of the conclusion reached in the certiorari proceeding, which is found reported in State ex rel. Union Limber Co. v. Superior Court, 70 Wash. 540, 127 Pac. 109. We shall notice the alleged errors which were not therein considered.

After the jury had been selected to determine the award in damages, by consent of the court and counsel for the respective parties, the jury was permitted to examine the premises. Thereafter, by consent of the court and counsel for the respective parties, one of the jurors was excused from further consideration of the case. Another juror was thereupon selected. The appellant requested that this juror be permitted to view the premises also. The court denied this request. It is now alleged that the court erred in not permitting this juror to view the premises. There is no prejudicial error in this ruling. It is within the discretion of the court whether a view of the premises shall be permitted. Bellingham Bay & B. C. R. Co. v. Strand, 4 Wash. 311, 30 Pac. 144. In In re East Spring Street, 41 Wash. 366, 83 Pac. 242, we said:

“The jury is not permitted to view the premises for the purpose of gathering evidence, but for the purpose of better understanding the evidence which has been adduced before it regarding said premises.”

The fact that one juror was not allowed to view the premises cannot be held to be prejudicial error, in view of the rule that it is discretionary with the trial court to grant a view, and also in view of the rule that a view of the premises is merely for the purpose of understanding the evidence. It may be true that this juror might have understood the evidence more perfectly had he been conversant with the premises. But it certainly cannot be held reversible error because he was not permitted- to do so. The evidence seems plain upon its face and we are not satisfied that this juror did not [566]*566understand the evidence as well as those who actually viewed the premises.

The appellant next contends that the court erred in denying a motion for dismissal of the action at the close of petitioner’s case, and also at the close of all the evidence, for the reason that it is claimed by the appellant that no evidence was introduced upon the question of damages to the property taken or damaged by the railway company. It may be true that no specific items of damages were enumerated by the witnesses for the condemning party; but it is plain from the record that the whole plan of the improvement was stated to the jury; maps and drawings were introduced in evidence and explained by the witnesses, which showed exactly what the petitioning railway company desired to take. It seems too plain for argument that the jury was authorized upon these facts to determine what the amount of damages was, if any, even though no witness testified what the damages would amount to.

It is also urged by the appellant that the court erred in receiving in evidence a plan of the contemplated improvement without the same being reduced to the form of a stipulation and offer showing what the condemning party desired to do. Even if this might be considered as error, a stipulation was subsequently made in the case which conformed to the plan as shown by the exhibit referred to. There was, therefore, no error committed, because it is plain upon the face of the record that the exhibit, whether introduced before the stipulation or afterwards, became a part of it, and explained the stipulation. No error can be based upon the order of proof.

The appellant argues that the court erred in refusing to permit the respondent to show that the operation of the logging road over the four-track system of the Northern Pacific Railway Company, would decrease the fair market value of the appellant’s sawmill and plant, on account of the hazard of the operation of the logging road across the Northern Pacific Railway Company’s system. It is appar[567]*567ent, we think, that this item of damage is remote and speculative. While it is true that the logging railway was a part of the sawmill plant, which was operated at a distance of a mile or so from the crossing and was a plant facility merely, it does not necessarily follow that the sawmill plant itself was affected by the taking of a part of the easement of the logging road. If, after the part of the easement was taken by the Northern Pacific Railway Company, the operation of the logging road or plant facility was as convenient, economical, and efficient as it was before the taking, there could be no possible injury to the plant as such. The rule is stated in 15 Cyc. 698, as follows:

“Where one railroad company appropriates the right of way of another railroad, the measure of damages is the loss and inconvenience necessarily incidental to the reconstruction and keeping in repair of that part of the first road which is occupied by the second, excluding the loss resulting from mere competition. The first company is likewise entitled to damages for all actual or direct injuries resulting from a new and additional use to be made of its right of way. However, the inconvenience to or interruption of a company’s business, such as the stopping of trains at the crossing, is not an element to be considered in estimating damages; nor is the increased liability to accident by reason of the crossing a proper element of damage. However, the cost of erecting signals and maintaining a crossing system, as well as the cost of a watchman, is a proper element to be considered in awarding damages to the company whose right of way is sought to be crossed by another railroad.”

This was the rule adopted by this court in State ex rel. North Coast R. Co. v. Northern Pac. R. Co., 49 Wash. 78, 94 Pac. 907. The mere fact that this logging railroad was a plant facility did not change the measure of damages in the respect stated. We are satisfied that the damages which were attempted to be proved with relation to the mill and manufacturing plant of the Union Lumber Company were too remote and speculative to be considered by the jury, and that the court therefore properly excluded such testimony.

[568]*568The appellant argues at length that the court erred in refusing to give certain requested instructions and in giving certain instructions.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Justice v. United States
145 F.2d 110 (Ninth Circuit, 1944)

Cite This Page — Counsel Stack

Bluebook (online)
137 P. 306, 76 Wash. 563, 1913 Wash. LEXIS 1858, Counsel Stack Legal Research, https://law.counselstack.com/opinion/northern-pacific-railway-co-v-union-lumber-co-wash-1913.