Northern Natural Gas Company v. Donnelly Farms Limited Partnership

CourtDistrict Court, D. South Dakota
DecidedMay 22, 2025
Docket4:23-cv-04089
StatusUnknown

This text of Northern Natural Gas Company v. Donnelly Farms Limited Partnership (Northern Natural Gas Company v. Donnelly Farms Limited Partnership) is published on Counsel Stack Legal Research, covering District Court, D. South Dakota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Northern Natural Gas Company v. Donnelly Farms Limited Partnership, (D.S.D. 2025).

Opinion

UNITED STATES DISTRICT COURT DISTRICT OF SOUTH DAKOTA □ SOUTHERN DIVISION

NORTHERN NATURAL GAS COMPANY, A □ 4:23-CV-04089-RAL DELAWARE CORPORATION; Plaintiff, OPINION AND ORDER GRANTING | MOTION TO BIFURCATE AND MOTION | VS. TO AMéiND SCHEDULING ORDER DONNELLY FARMS LIMITED PARTNERSHIP, A SOUTH DAKOTA □ LIMITED PARTNERSHIP; . Defendant.

Pending before this Court is Plaintiff Northern Natural Gas Company’s (“Northern”) Motion to Bifurcate, Doc. 27, and Defendant Donnelly Farms Limited Partnership’s (“Donnelly”) Motion to Amend/Correct Scheduling Order, Doc. 29. For the following reasons, both motions are granted. I. Facts, the Prior Ruling, and Procedural Background! Northern is a Delaware corporation with a principal place of business in Nebraska that sells and transports natural gas through interstate pipelines. Doc. 1 at 1-2. Donnelly is the record owner of real property in Union County, South Dakota described as “[t]he Southeast Quarter of the

1 The parties previously stipulated to a statement of undisputed material facts in connection with a Joint Motion for Partial Summary Judgment. Doc. 16. This Court denied that Joint Motion as both parties in briefing and at oral argument argued facts beyond the stipulated ones. Doc. 26. This Court draws the facts largely from that statement of undisputed material facts and other matters of record that appear to be uncontested. 1 .

Southeast Quarter (SE/4 SE/4), Section Thirteen (13), Township Ninety-One (91), Range Fifty (50) (“the Property”).” Doc. 16 at 2. On June 5, 1952, Donnelly’s predecessors in interest conveyed to Northern a multiple-line-rights easement (“MLR Easement”). Id.; Doc. 1-1. The MLR Easement granted Northern the right to “construct, maintain and operate pipe lines, and appurtenances thereto” on the Property along with “the right of ingress and egress from [the Property], for the purpose of constructing, inspecting, repairing, maintaining and replacing” the pipeline facilities. Doc. 1-1. Northern obtained the MLR Easement to construct, operate, and maintain a segment of its M561 A-Line natural gas transmission pipeline. Doc. 1 at 2. To mitigate safety risks from aging pipelines, the United States Federal Energy Regulatory Commission (“FERC”) in March 2021 authorized Northern to abandon a portion of the M561 A- line and replace certain facilities as part of the Sioux Falls A-Line Replacement Project

_ (Project”). Id. at 3. As part of that Project, Northern obtained a Pipeline Facility Easement (“Facility Easement”) from Donnelly that granted Northern the “right, privilege, and easement to construct, inspect, repair, maintain, operate, replace, and remove below ground and above ground natural gas facilities.” Doc. 1-2; Doc. 16-2 at 2. The Facility Easement also granted to Northern the “right of ingress to and egress from the [Property], for the purpose of constructing, inspecting, repairing, maintaining, operating, replacing, and removing” the facilities. Doc. 1-2; Doc. 16-2 at 2. . Pursuant to the Facility Easement, Northern constructed a new, larger regulator facility north of the original facility on the Property. Doc. 16-3. South Dakota Highway 11 runs north and south along the Property’s eastern border. Doc. 1 at 4. Separating the new regulator facility and Highway 11 is a road ditch. Doc. 16-3. In October 2021, Northern claims it presented Donnelly with the options of accessing the new regulator facility from Highway 11 from either

north or south of the regulator facility. Doc. 1 at 4. Donnelly allegedly preferred access from the north; however, in November 2021, Donnelly advised Northern that it preferred neither option. Id. Instead, Northern alleges Donnelly requested Northern build an access approach directly between the regulator facility and Highway 11. Id. Donnelly contests that it ever gave permission for Northern to build such an access approach off Highway 11 to the new regulator facility. On January 13, 2022, Northern applied for a highway access permit (“the Permit”) from the South Dakota Department of Transportation (“SDDOT”) to construct the access approach. Doc. 16 at 2. Northern sought permission to build a 20-foot by 40-foot approach directly adjacent to the regulator facility. Doc. 1 at 4. The SDDOT approved the Permit. Doc. 16 at 2; Doe. 1-3. Donnelly did not sign the Permit application. Doc. 16 at 2. Northern constructed the access approach in February 2022. Id. The access approach is a graveled driveway adjoining the regulator facility to Highway 11, cutting through the road ditch. Doc. 16-3. On October 31, 2022, Donnelly, through counsel, sent a letter to SDDOT demanding SDDOT cancel the Permit because Donnelly had not signed the Permit application. Doc. 16 at 3; Doc. 1 at 5. On May 4, 2023, the SDDOT entered an Order for Removal of Access Approach requiring Northern to remove the access approach by July 7, 2023. Doc. 16 at 3. Administrative proceedings regarding the Order for Removal of Access Approach are stayed pending the present litigation. Id. On May 31, 2023, Northern filed its Complaint, raising four claims against Donnelly: breach of contract, preliminary and permanent injunction, forcible exclusion from real property, and promissory estoppel. Doc. 1. On June 26, 2023, Donnelly filed its Answer and Affirmative Defenses. Doc. 8. Neither Northern nor Donnelly demanded a jury trial in their initial pleadings.

Docs. 1, 8. This Court entered a Rule 16 Scheduling Order on March 14, 2024, which set April 1, 2024, as the deadline to move to join additional parties and to amend the pleadings. Doc. 14. On March 29, 2024, Donnelly’s counsel emailed Northern’s counsel a draft stipulation to amend Donnelly’s Answer and a draft of a First Amended Answer and Counterclaims, stating in the email that “[if] we do not hear from you, you agreed this morning that we could have an extension on the deadline to amend now set for April 1st.” Docs. 31 at 1, 33-1 at 3. On April 15, Northern’s counsel contacted Donnelly’s counsel suggesting the parties first file cross-motions for summary judgment on the sole issue of whether the easement agreements authorized Northern to build the access approach and then extend the time for the parties to amend pleadings after. Doc. 31-1 at 8. On April 18, Donnelly’s counsel emailed Northern’s counsel stating “all deadlines are at a standstill at this time and we will continue the discussion of stipulating to a new scheduling order.” Doc. 31-1 at 6. Donnelly did not file a motion for leave to file the First Amended Answer and Counterclaims but joined Northern in a Joint Motion for Partial Summary Judgment. Northern and Donnelly filed the Joint Motion for Partial Summary Judgment along with a Stipulated Statement of Undisputed Material Facts requesting this Court decide the “narrow issue” of whether the easement agreements authorized Northern to build the access approach. Doc. 16. This Court held a hearing on the joint motion for partial summary judgment on October 17, 2024. Doc. 24. This Court denied summary judgment to either party. In ruling from the bench, this Court expressed an understanding on why the parties had filed a joint motion for summary judgment to avoid attorney’s fees exceeding what might be at stake. Doc. 26 at 32. This Court reasoned that “the interests of justice are served by an expeditious ruling that allows the parties then to decide where they go with this case.” Id. This opinion-and order summarizes the reasoning expressed on the record to frame the issues in this case.

The easements permitted Northern “the right of ingress to and egress . . . for the purpose of constructing, inspecting, repairing, maintaining, replacing, and removing” the pipeline and facilities. Doc. 1-2; Doc. 16-2.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Selway Homeowners Ass'n v. Cummings
2003 SD 11 (South Dakota Supreme Court, 2003)
Canyon Lake Park, L.L.C. v. Loftus Dental, P.C.
2005 SD 82 (South Dakota Supreme Court, 2005)
Stanga v. Husman
2005 SD 36 (South Dakota Supreme Court, 2005)
Vander Heide v. Boke Ranch, Inc.
2007 SD 69 (South Dakota Supreme Court, 2007)
DeHaven v. Hall
2008 SD 57 (South Dakota Supreme Court, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
Northern Natural Gas Company v. Donnelly Farms Limited Partnership, Counsel Stack Legal Research, https://law.counselstack.com/opinion/northern-natural-gas-company-v-donnelly-farms-limited-partnership-sdd-2025.