Northern Improvement Co. v. Wyoming State Highway Commission

802 P.2d 889, 1990 Wyo. LEXIS 158, 1990 WL 201397
CourtWyoming Supreme Court
DecidedDecember 14, 1990
DocketNo. 89-287
StatusPublished
Cited by1 cases

This text of 802 P.2d 889 (Northern Improvement Co. v. Wyoming State Highway Commission) is published on Counsel Stack Legal Research, covering Wyoming Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Northern Improvement Co. v. Wyoming State Highway Commission, 802 P.2d 889, 1990 Wyo. LEXIS 158, 1990 WL 201397 (Wyo. 1990).

Opinions

MACY, Justice.

Appellant Northern Improvement Company appeals from a judgment in favor of Appellee Wyoming State Highway Commission, denying Appellant’s claim for costs of grinding a portion of Interstate 80, which Appellant paved pursuant to a contract with Appellee.

We affirm.

Appellant presents the following issues:

1. Were the contract specifications adequate to insure the quality of ride demanded by the Appellee?
2. Did reasonable conformity with grade, as imposed by Appellee, become arbitrarily and capriciously identified and measured by a subjective ride test, such that excessive remedial costs were incurred by Appellant?
3. Did the contract plans and specifications grant Appellee unlimited discretion to determine the satisfactory and acceptable fulfillment of the contract?
4. Was the evidence sufficient to support the trial court’s finding that public policy safety considerations were a component of Appellee’s decision to direct Appellant to grind the pavement surface?

In 1985, Appellant and Appellee entered into a contract for the repavement of a portion of Interstate 80 near Rock Springs, Wyoming. The contract was subject to specifications articulated in the Highway Department’s Specifications for Road & Bridge Construction (1980 ed.) and certain supplementary specifications. The specifications described, inter alia, the procedure for determining the quality and acceptability of the completed project. Section 105.01 of the Specifications for Road & Bridge Construction stated in pertinent part:

The Engineer will decide all questions which may arise as to: The quality and acceptability of materials furnished and work performed; the rate of progress of the work; cooperation between Contractors; the interpretation of the plans and specifications; and the acceptable fulfillment of the contract on the part of the Contractor.

Section 105.03 provided:

All work performed and all materials furnished shall be in reasonably close conformity with the lines, grades, cross sections, dimensions, and material requirements, including tolerances, shown on the plans or indicated in the specifications.
⅜ * ⅝ ⅜ ⅜ *
If the Engineer finds that the materials or the finished product in which the materials are used or the work performed are not in reasonably close conformity with the plans and specifications and have resulted in an inferior or unsatisfactory product, the work or materials shall be removed and replaced or otherwise corrected by and at the expense of the Contractor.

Section 105.08 stated in pertinent part:

The Engineer will set construction stakes establishing lines, slopes, and continuous profile grade in road work, and centerline and bench marks for bridge work, culvert work, protective and accessory structures, and appurtenances as he may deem necessary, and will furnish the Contractor with all necessary information relating to lines, slopes, and grades. These stakes and marks shall constitute the field control by and in accordance with which the Contractor shall establish other necessary controls and perform the work.

The specifications also stated:

As soon as the concrete has hardened sufficiently, the pavement surface shall be tested with a ten-foot (3 m) straightedge or other specified devices. Areas showing high spots of more than xh inch (3 mm), but not exceeding ½ [891]*891inch (13 mm) in ten feet (3 m) shall be marked and immediately ground down with an approved grinding tool to an elevation where the area or spot will not show surface deviations in excess of ⅛ inch (3 mm) when tested with a ten-foot (3 m) straightedge.

Section 414.16. Section 414.15F provided in pertinent part:

Straightedge testing and surface corrections shall continue until the entire surface is found to be free from observable departures from the straightedge and the slab conforms to the required grade and cross section.

Appellant completed the project in two phases. After Appellant completed phase I, Appellee’s district engineer drove a vehicle over the pavement and approved-the quality of the surface.1 When Appellant completed phase II, Appellee’s district engineer again drove a vehicle over the paved surface. He discovered that the surface had a series of flaws described at trial as a “harmonic wave.” He advised Appellant that the quality of the surface was unacceptable and that the surface would have to be ground to remove the wave. A straightedge test revealed that the surface deviated from the straightedge requirement in more than 200 places. The grade of the pavement was also compared to the grade requirements as designated by stakes which had been placed at fifty-foot intervals along the course of the interstate.2 The pavement did not deviate from the grade requirements on those stakes at the location of the stakes, but a string test indicated that deviations as great as three-fourths of an inch existed at points between the stakes.

Appellee directed Appellant to grind the surface of the pavement until the harmonic wave was removed. Appellant asked Ap-pellee to provide an objective standard for grinding the pavement. In response, Ap-pellee demanded that Appellant grind the surface to meet a standard measured by a profilograph, which profiles the surface of the road. Neither the contract nor the specifications mandated the use of the pro-filograph or a ride test as a method for testing the quality of the surface. The grinding required to meet Appellee’s profi-lograph standard was more extensive than the grinding required to meet the straightedge test. Appellant ground the pavement to the district engineer’s satisfaction and filed a claim with Appellee, seeking reimbursement for the additional cost of grinding the surface in phase II to the profilograph standard.

Appellee’s chief executive staff reviewed and denied Appellant’s claim. Appellant subsequently filed a petition for review with the district court. The district court viewed the petition as an original complaint.3 Appellant alleged that Appel-lee used standards not specified in their contract to require excessive grinding of the entire phase II surface and sought recovery for grinding work not attributable to its failure to meet the straightedge test. The district court conducted a bench trial and ruled in favor of Appellee. The court found that the specifications gave Appel-lee’s district engineer sufficient authority to require Appellant to remove a defect which was unsafe and unacceptable.

The disposition of this case depends upon the answers to two questions:

1. Did the terms of the highway construction contract between Appellant and Appellee permit Appellee to require that Appellant remove a flaw in the pavement even though the surface satisfied a standard incorporated into the contract?
[892]*8922. Is the district court’s decision supported by sufficient evidence?

The answer to the first question is dependent upon our interpretation of the parties’ contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
802 P.2d 889, 1990 Wyo. LEXIS 158, 1990 WL 201397, Counsel Stack Legal Research, https://law.counselstack.com/opinion/northern-improvement-co-v-wyoming-state-highway-commission-wyo-1990.