Northeast Community Organization, Inc. v. Weinberger

378 F. Supp. 1287, 1974 U.S. Dist. LEXIS 7951
CourtDistrict Court, D. Maryland
DecidedJune 24, 1974
DocketCiv. 74-528-HM, 74-584-HM
StatusPublished
Cited by3 cases

This text of 378 F. Supp. 1287 (Northeast Community Organization, Inc. v. Weinberger) is published on Counsel Stack Legal Research, covering District Court, D. Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Northeast Community Organization, Inc. v. Weinberger, 378 F. Supp. 1287, 1974 U.S. Dist. LEXIS 7951 (D. Md. 1974).

Opinion

*1289 MURRAY, District Judge.

Northeast Community Organization, Inc. [hereinafter NECO], plaintiff in Civil No. 74-528-HM, is a non-profit corporation engaged in educational pursuits, and is one of the members of a consortium for which the Health and Welfare Council of Central Maryland, Inc. [hereinafter HWC], plaintiff in Civil No. 74-584-HM, acts as agent. Through HWC, NECO and seven other non-profit organizations making up the consortium, made application in December, 1973 to the United States Department of Health, Education and Welfare [hereinafter HEW] for grants under the Emergency School Aid Act, 20 U.S. C. § 1601 et seq. [hereinafter ESAA], Following a complex series of administrative actions, more fully discussed below, HEW notified the president of HWC, James E. Nix, in a letter dated May 17, 1974, that its application for ESAA assistance was denied. This suit challenges the propriety of that denial.

Temporary restraining orders in these two cases have enjoined HEW from reallocating to other projects a total of $397,000.00, pending the resolution of motions for a preliminary injunction. 1 The two cases have been consolidated and lengthy hearings have been held at which testimony was taken concerning the events preceding the May 17, 1974 denial of ESAA funding. The parties have agreed that these hearings shall be treated as a trial on the merits pursuant to Rule 65(a) of the Federal Rules of Civil Procedure. Although not herein separately enumerated, this opinion contains such findings of fact and law as are required by Rule 52(a) and a judgment on the merits of the plaintiffs’ claims.

In seeking to overturn HEW’s action, NECO and HWC make two main arguments. First, they assert that statements made over the telephone by various agents and employees of HEW in March and April, 1974, constituted approval of their application for ESAA funding and created a contract between HWC and HEW. Second, they assert that the denial of their application for such funding was based on an incorrect reading of the statute which made HWC’s eligibility dependent on the acceptability of a desegregation plan adopted by the Baltimore City School Board. When the Baltimore plan was found unacceptable by the HEW Office of Civil Rights, the agency also ruled as a consequence that HWC was ineligible for ESAA monies.

I.

The Facts

Before dealing with these contentions, the background facts should be briefly stated. In June of 1954, the Baltimore City School Board responded to the Supreme Court’s decision in Brown v. Board of Education, 347 U.S. 483, 74 S. Ct. 686, 98 L.Ed. 873 (1954) by adopting an “open enrollment plan” of desegregation. On December 22, 1973, the Baltimore City School Board submitted an application for ESAA funding as a “local educational agency” [hereinafter LEA] within the meaning of the Act. 20 U.S.C. §§ 1619 and 1605. Two days later, HWC submitted its application to HEW, proceeding as a “non-profit organization” [hereinafter NPO]. 20 U. S.C. §§ 1619 and 1607(b). On January 2, 1974, these applications were received at HEW Region III headquarters in Philadelphia, Pennsylvania, and pursuant to normal procedure were processed by the Office of Civil Rights [hereinafter OCR]. Harold Davis of that Office notified the Office of Education on the *1290 same day that both applications were in support of what OCR regarded as an acceptable plan of desegregation, namely the above-mentioned “open enrollment plan”. The Office of Education then proceeded to process the HWC application through the requisite administrative procedures.

While these procedures were being pursued by HEW’s Office of Education, a letter was sent on February 5, 1974 by Peter Holmes of OCR to Dr. Roland Patterson, superintendent of the Baltimore City Schools, stating that the City’s “open enrollment plan” no longer complied with the standards of desegregation of Title VI of the Civil Rights Act of 1964 (42 U.S.C. §§ 2000d et seq.) as enunciated in Adams v. Richardson, 356 F.Supp. 92 (D.D.C.1973), affirmed en banc 156 U.S.App.D.C. 267, 480 F.2d 1159 (1973). The same letter allowed the City thirty days in which to submit a modified plan which would satisfy Title VI. After a series of extensions, the City was ultimately given a deadline of May 30 for the submission of its plan. On June 12, 1974, a plan for further student and faculty desegregation was finally delivered to HEW and is currently under active administrative review.

Meanwhile, the Office of Education had taken several actions with regard to HWC’s ESAA application. The first rounds of administrative approval were passed and on March 18, 1974 Ann Weber, acting contract officer for Region III, called HWC to inform them that certain reductions in budgetary requests must be submitted by March 20, 1974. Witnesses for the plaintiff assert that Miss Weber said the application had been “approved” at a lower level of funding than originally requested. Miss Weber, however, denies ever using such terms. At this same time, HWC was given to understand that three consortium members, including NECO, had been deleted, allegedly because their proposed activities under the plan would supplant similar activity of the LEA.

John Geist, Executive Director of HWC, and Mary Ann Martin, his assistant, called Region III on March 19, 1974 and spoke with John Rooks, a program officer in the Office of Education. In response to their request for information about the status of the HWC application, Rooks told them that he was no longer their program officer and was therefore unable to answer their inquiries. Geist and Martin assert, however, that they were informed by Rooks that the HWC proposal was “approved”. Again, th'e HEW employee denies using that term.

On the next day, Geist and Martin spoke with a program officer named Anderson who purportedly indicated that Baltimore’s application had been approved and this testimony is undisputed. The proposal with the requisite alterations was then delivered to Region III on the same day.

In the first week of April, 1974, Edward Cooper, program manager in the Office of Education, spoke with Martin and told her that new evidence indicated that the deleted members might be restored. Martin acquiesced in the suggestion that the entire HWC application be reprocessed through the administrative machinery. After this was done, the new proposal was recommended for approval and Weber again instructed HWC to submit altered budgetary figures with a telephone call on April 11, 1974.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Board of Education of the City School District v. Califano
464 F. Supp. 1114 (E.D. New York, 1979)
MONTGOMERY CTY., MARYLAND v. Ball
416 F. Supp. 737 (D. Maryland, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
378 F. Supp. 1287, 1974 U.S. Dist. LEXIS 7951, Counsel Stack Legal Research, https://law.counselstack.com/opinion/northeast-community-organization-inc-v-weinberger-mdd-1974.