Northbilt Mfg. Co. v. United States

43 F. Supp. 676, 1942 U.S. Dist. LEXIS 3064
District Court, D. Minnesota·Decided January 13, 1942·No. No. 311 Civil·Published

Opinion

NORDBYE, District Judge.

The Northbilt Manufacturing Company entered into a written contract on May 27, 1938, with the Government, wherein and whereby it agreed to furnish and deliver at the Eighth Corps Area General Depot, Fort Sam Houston, Texas, 18,824 mackinaw coats, in accordance with certain specifications and the terms and conditions of said contract, for a consideration of $61,178. It appears that the defendant has paid $59,-530.26, but has retained $1,647.74 on account of delays in complying with the contract with respect to deliveries. This suit in effect contests the right of the Government to retain any money by way of liquidated damages and seeks recovery of the sum so retained. It is stipulated that, if the Government is sustained in its right to retain liquidated damages, the sum withheld is correct and not unreasonable in amount.

The requirements of the contract with reference to deliveries provided that, in ninety days, or by August 29, 1938, five per cent should be delivered; during the next sixty days, or by October 28th, thirty per cent; during the next thirty days, or by November 27th, thirty per cent; and the remaining thirty-five per cent by March' 27, 1939.

Deliveries were made on August 27th of some 1,080 coats. Of this number, 805 were accepted and 275 were rejected. On September 21st, 3,258 coats were delivered, and of this number 2,541 were accepted and 717 rejected. The large number of rejections evidently caused considerable concern to the plaintiff, and it asserts that it suspended any further production because of the high rejections. That is, the rejections were so large that no profit could be made on the contract and there was a probability that it might have to break the contract and refuse to make any further deliveries. It seems that the primary cause for the rejections was due to defective stitching. Northbilt had employed a so-called overcast stitching at or on certain seams, and it was with regard to this workmanship that the Government inspectors rejected a large number of coats.

Article 4 o f the contract provides: “Inspection. — • * * * (c) Final inspection and acceptance of materials and finished articles will be made after delivery, unless otherwise stated. * * * Final inspection shall be conclusive except as regards latent defects, fraud, or such gross mistakes as amount to fraud. * * * ”

After receiving notice of the rejections in the shipments referred to, representatives of Northbilt made trips to Fort Sam Houston. Conferences were held with Government officials, and it was apparently recognized by Northbilt that shoddy work had been done which caused an unworkmanlike product. See, Exhibits 73, 84, 94 and 121. It may be gathered that the overcast seams required careful and painstaking effort to avoid defective stitching. The result of these conferences led to the understanding that, in all future coat manufacturing under the contract, Northbilt would employ piped seams — a more expensive method — and thus avoid, if possible, the trouble which had arisen in connection with the overcast seams. The specifications provided that either overcast or piped seams could be used. The Government representatives agreed that, if the next shipment evidenced that the seam difficulties had been overcome by the use of the piped seam, they would be willing to make a reinspection of those goods which had been rejected in the September and October shipments.

The evidence indicates that the remaining shipments under the contract were free from most of the defects found in the earlier production. Piped seams had replaced the overcast seams, and, in accordatice with the understanding, a reinspection of the earlier shipments was made. Of the 275 coats rejected on August 27th, the reinspection resulted in 197 of the rejected coats being accepted, as of November 9th, and of the 717 coats rejected on September 21st, 605 were accepted as of October 27th.

The penalty in question arose by reason of the failure of Northbilt to ship the sped[678] fied number of coats on or before November 27, 1938. The contract in regard thereto provides in part: “Article 17. Delays— Liquidated damages. * * * The contractor shall not be charged with liquidated damages * * * when the delay in delivery is due to unforeseeable 'causes beyond the control and without the fault or negligence of the contractor, including, but not restricted to, acts of God, or the public enemy, acts of the Government * * * .”

Free access — add to your briefcase to read the full text and ask questions with AI

Northbilt Mfg. Co. v. United States, 43 F. Supp. 676, 1942 U.S. Dist. LEXIS 3064 (mnd 1942).

43 F. Supp. 676 (Northbilt Mfg. Co. v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.