North Shore Lumber Co. v. South Side Lumber Co.

176 Ill. App. 96, 1912 Ill. App. LEXIS 33
CourtAppellate Court of Illinois
DecidedDecember 30, 1912
DocketGen. No. 16,747
StatusPublished
Cited by1 cases

This text of 176 Ill. App. 96 (North Shore Lumber Co. v. South Side Lumber Co.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
North Shore Lumber Co. v. South Side Lumber Co., 176 Ill. App. 96, 1912 Ill. App. LEXIS 33 (Ill. Ct. App. 1912).

Opinion

Mr. Justice Baker

delivered the opinion of the court.

This action was for the price of a cargo of maple lumber delivered by the plaintiff, the North Shore Lumber Co., to the defendant, the South Side Lumber Co., on plaintiff’s dock at Thompson, Michigan, August 25, 1908, pursuant to the following contract:

“Chicago, Ill., Feb. 20th, 1908.
South Side Lumber Co., Chicago, Ill.
Gentlemen:
We propose to sell you our 1908 season’s cut up to Sept. 1st of hard maple lumber estimated to be three million feet including 700 M. now on dock to be principally cut to 4/4, cutting what thicker you may require to be delivered on dock not more than two piles deep at Thompson, Mich., including about 700 M. of dry maple now on our docks, and including about 75 M. strips at the following prices:
First and Seconds, $22.00 per M.
No. 1 Common, 16.00 per M. and
No. 2 or shipping culls, 12.00 per M.
Terms 2°/o off in 10 days or 60 days’ acceptance; lumber to be shipped 60 days from completion of each % million sawed. Lumber to be inspected by J. S. Co-man, Menominee, Mich., or some other competent inspector mutually agreed upon, each party to pay one-half the inspection fees and said lumber to be inspected according to National Hardwood Lumber Association Inspection of 1907. Lumber to be carried on the docks 90 days, provided we have the room, if not, there should be enough of such lumber moved after being 60 days in pile to give us the room.
It being particularly understood that we will deliver you by Sept. 1st not less than 2% million feet and up to 3 million feet if possible, including the 700 M. dry now on dock, and all lumber to be in pile not later than September 1st, 1908, and all such lumber to be removed before the close of navigation or settled for by Dec. 1st, 1908.
The North Shore Lumber Co.,
By A. M. Chesebrough, Secy.
Accepted South Side Lumber Co.
By J. J. Nichols.”

The contract price of the cargo was $3,123.14, and the judgment was for that sum and interest.

The contention of the appellant is that the plaintiff failed to keep and perform the contract, and that thereby the defendant sustained damages which it had the right to recoup or set off against the claim of the plaintiff for the price of the cargo. As a basis of this contention it is claimed that before the contract was signed the parties agreed orally that the defendant should have the right to carry the lumber in its barge, the Sawyer, and that the plaintiff should dredge the harbor at Thompson so that the Sawyer could take away a full cargo.

The contract is complete as written and does not include either an agreement that the defendant should have the right or privilege to carry the lumber by the Sawyer, or any agreement that the plaintiff should dredge the harbor at Thompson so that the Sawyer could carry away a full cargo. No oral evidence of the previous negotiations is admissible to show what the contract was, unless it appears that the writing was not intended to embody the whole contract, and the question whether the parties intended to embody the whole contract in the writing is to be determined in the first instance by an inspection of the writing itself, and not otherwise. Telluride Power Transmission Co. v. Crane Co., 208 Ill. 218; Osgood v. Skinner, 211 Ill. 229; Schneider v. Sulzer, 212 Ill. 93; Seitz v. Brewers’ Refrigerating Mach. Co., 141 U. S. 510.

In the case first cited it was said: “The questions as to what writings should be considered, and whether or not those considered constituted a written contract, and whether or not the written contract fully-expressed the agreement between the parties, were for the court. The rule is, that when the writings show, upon inspection, a complete legal obligation, without any uncertainty or ambiguity as to the object and extent of the engagement, it is conclusively presumed that the whole agreement of the parties was included in the writings. The fact that a point has been omitted which might have been embodied therein will not open the door to the admission of parol evidence in that regard.”

We are clear that evidence tending to show the alleged independent collateral contract was inadmissible.

Again, by the terms of the writing the defendant was obligated to ship the lumber at certain specified times after it had been piled on the dock. Its duty to take away the lumber according to such provisions was, under the terms of the writing, absolute and unqualified. Evidence to show that it was not bound to take away lumber, no matter how long it had been piled on the dock, until the harbor was so dredged as to accommodaté the Sawyer, was evidence tending to vary and contradict its own written undertaking, and for that reason was inadmissible. Ryan v. Cooke, 172 Ill. 302.

A further contention of the defendant is that it was not, under the contract, obligated to take from the dock any part of the 700,000 feet of dry lumber on the dock when the contract was made until the close of navigation. The contract provides that, “Lumber to be carried on the docks ninety days, provided we have the room, if not, there should be enough of said lumber moved after being sixty days in pile to give us the room.”

We concur in the conclusion stated by the learned trial judge that this provision applies to the 700,000 feet then on the dock, as well as to lumber sawed after the contract was made; that the defendant was bound to ship the 700,000 feet of lumber whenever after the expiration of sixty days from February 20 the plaintiff needed the room which it occupied, and in any event was bound to ship said lumber in ninety days from February 20.

The lumber first taken by the defendant from the dock was the cargo of 161,054 feet taken June 23, and the next was the cargo of 202,515 feet taken July 14. This delay was not caused by any fault or omission on the part of the plaintiff, and because of it the plaintiff was hindered and delayed in the manufacture of lumber under the contract. June 3 it was compelled to shut down its mill because its piling space was filled, and it did not resume operation until shortly after July 4. If the 700,000 feet of dry lumber in question had been removed by defendant before June 3, the plaintiff could have run its mill fifteen working days, or allowing for Sundays, two weeks and a half longer than it did. . The failure of the plaintiff to have not less than two and one-half million feet in pile by September 1 was caused in part by the defendant’s delay and default in removing the dry lumber from the dock, and the plaintiff was entitled to a reasonable extension of time in which to saw and pile the remainder of the lumber. T. Wilce Co. v. Kelley Shingle Co., 130 Mich. 319; Tyers v. Rosedale Ferry Hill Co., L. R. 10 Exch. 195.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Consumers Mutual Oil Co. v. Western Petroleum Co.
216 Ill. App. 382 (Appellate Court of Illinois, 1920)

Cite This Page — Counsel Stack

Bluebook (online)
176 Ill. App. 96, 1912 Ill. App. LEXIS 33, Counsel Stack Legal Research, https://law.counselstack.com/opinion/north-shore-lumber-co-v-south-side-lumber-co-illappct-1912.