North Country Development Corp. v. Massena Housing Authority

65 Misc. 2d 105, 316 N.Y.S.2d 894, 1970 N.Y. Misc. LEXIS 1459
CourtNew York Supreme Court
DecidedJuly 14, 1970
StatusPublished
Cited by8 cases

This text of 65 Misc. 2d 105 (North Country Development Corp. v. Massena Housing Authority) is published on Counsel Stack Legal Research, covering New York Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
North Country Development Corp. v. Massena Housing Authority, 65 Misc. 2d 105, 316 N.Y.S.2d 894, 1970 N.Y. Misc. LEXIS 1459 (N.Y. Super. Ct. 1970).

Opinion

Paul D. Graves, J.

This is a proceeding under article 78 of the CPLB, brought on by order to show cause, for an order directing the respondent, Massena Housing Authority, to rescind its determination, awarding a bid to respondent Stirling Homex Corporation for the construction of 50 low-income housing units or in the alternative to award the contract to the petitioner as the lowest responsible bidder.

The Massena Housing Authority, having received prior approval from the Village of Massena, determined to complete a low cost housing project by inviting developers or builders to submit proposals for the erection of 50 low-income housing units. Financing was to be through Federal aid from the United States Department of Housing and Urban Development. The proposals were based ón a so-called “ turn-key ” contract, which in this case, involved the Authority providing land deemed to be in excess of its needs for a stated amount and contracting to repurchase the land after the dwelling units were constructed and made ready for occupancy according to specifications set forth by the Authority.

After advertising five proposals were received April 21, 1970 by the Massena Housing Authority for this project. These ranged from a high proposal submitted by respondent Stirling Homex Corporation of $1,072,515 to a low bid of petitioners for $825,000. A subcommittee was created by the Housing Authority, and as the result of its recommendations, the Authority directed the five proposers to resubmit their proposals incorporating further specifications. On May 28, 1970, four of the developers resubmitted their proposals. The proposals received were as follows:

[107]*107North Country Development Corporation

(petitioner) ................................$ 930,000

Factory Automated Systems from Pennsylvania.. $ 986,095 Fournier Development Corporation.............$1,039,039

Stirling Homex Corporation (respondent)....... $1,039,215

On June 3, 1970, after reviewing the proposals and hearing representatives from the four developers, the Authority by unanimous secret ballot or vote determined to recommend to the United States Department of Housing and Urban Development acceptance of the proposal made by respondent, Stirling Homex Corporation, which had submitted the highest proposal, and was $109,215 over the low proposal submitted by petitioner.

The reasons assigned by the Authority in their answer for recommending respondent Stirling Homex were stated to be based upon the ability of said respondent to complete the project prior to the winter of 1970; that the statements made by the other developers were, in effect, they could not provide a definite completion date whereas respondent guaranteed completion within 60 working days; and further, the Authority considered its prior favorable experience with respondent developer.

The answer and arguments by respondent raise several defenses, which probably should be disposed of before considering the merits. The first defense contained in respondent Stirling Homex’ answer is that the order to show cause was not timely served, since such order required service by certified mail, return receipt requested, on or before June 6, 1970; that the papers were not served upon this respondent until June 8, 1970. Whether such service was timely made or not is of little concern since this respondent did file an answer containing denials to many of the allegations of the petition and has had full opportunity to argue the matter and submit briefs directed to the merits, and therefore has waived any objection it might have on the grounds of inadequacy of notice. (Cf. Schoenberg v. State of New York, 206 Misc. 493; Matter of Glasser, 180 Misc. 311.)

Respondent Stirling Homex’ second defense that the petition is legally insufficient in failing to allege a cause of action against respondent is likewise without merit. This respondent was properly made a party as the successful bidder in this proceeding, and in fact, it is probably a necessary party. (Matter of Cestone Bros. v. Solowinski, 276 App. Div. 970; Matter of Wiltom Coach Co. v. Central High School, Dist. No. 3, 36 Misc 2d 637.)

[108]*108Respondents also contend petitioner did not comply with section 157 of the Public Housing Law. Subdivision 1 of this section provides: “ In every action or special proceeding, for any cause whatsoever, prosecuted or maintained against an authority, the complaint or necessary moving papers shall contain am allegation that at least thirty days have elapsed since the demand, claim or claims upon which such action or special proceeding is founded were presented to the authority for adjustment and that it has neglected or refused to make an adjustment or payment thereof for thirty days after such presentment.”

In the court’s opinion, this section does not apply to this present article 78 proceeding. The quoted séction refers to adjustment ” or payment ” which would apply in actions where damages are claimed for tort or breach of contract. Even if requested, damages to petitioner could not be awarded since there is no contractual relationship between petitioner and the Authority by the mere submission of a proposal or low bid. (Molloy v. City of New Rochelle, 198 N. Y. 402.) An article 78 proceeding is sanctioned by an unsuccessful bidder to insure enforcement of applicable statutes. (Matter of Dictaphone Corp. v. O’Leary, 287 N. Y. 491; Matter of Allen v. Eberling, 24 A D 2d 594.) If required to wait 30 days before pursuing relief hereunder, it is possible petitioner would find itself without legal remedy since a. contract could be awarded and the work commenced or partly .completed in the interim. (See Matter of Carrol-Ratner Corp. v. City Manager of New Rochelle, 54 Misc 2d 625; Matter of General Steel Prods. Corp. v. City of New York, 18 Misc 2d 106.)

Respondents argue the special proceeding herein was prematurely commenced (CPLR 7801, subd. 1), since the recommendation of :'kn award,..to. respondent Stirling Homes was subject to approval of-the United- States Department of Housing and Urban Development. However, it does not appear any other than the one proposal recommended would be forwarded for approval, or that petitioner would be given an opportunity to contest the recommendation before the United States Department of Housing and Urban Development. Therefore, in the court’s opinioh, the proceeding was not premature, and; as,stated above, any delay in instituting the proceeding might result in leaving petitioner without a remedy.

Thus disposing of all preliminary matters contained in the defenses worthy of comment, the court now reaches the main issues posed by the pleadings. The petition alleges respondent, Massena Housing Authority, failed to comply with subdivision 3 [109]*109of section 220 of the Labor Law; and that also the bids received did not contain a statement of noncollusion as required by section 151 of the Public Housing Law (see, also, General Municipal Law, § 103, subd. 7). Subdivision 3 of section 220 is applicable to the Municipal Housing Law under section 152 of the Public Housing Law.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Subolo Contracting Corp. v. County of Westchester
282 A.D.2d 737 (Appellate Division of the Supreme Court of New York, 2001)
Opn. No.
New York Attorney General Reports, 1981
Marvec-All State, Inc. v. Purcell
110 Misc. 2d 67 (New York Supreme Court, 1981)
People v. Lang
378 N.E.2d 1106 (Appellate Court of Illinois, 1978)
King v. Alaska State Housing Authority
512 P.2d 887 (Alaska Supreme Court, 1973)
Empire Electrical Contractors Ass'n v. Fabber
71 Misc. 2d 167 (New York Supreme Court, 1972)
Marino v. Town of Ramapo
68 Misc. 2d 44 (New York Supreme Court, 1971)

Cite This Page — Counsel Stack

Bluebook (online)
65 Misc. 2d 105, 316 N.Y.S.2d 894, 1970 N.Y. Misc. LEXIS 1459, Counsel Stack Legal Research, https://law.counselstack.com/opinion/north-country-development-corp-v-massena-housing-authority-nysupct-1970.