North Coast Premier Soccer, L.L.C. v. Ohio Dept. of Transp.

2012 Ohio 5296
CourtOhio Court of Claims
DecidedMarch 30, 2012
Docket2009-07091
StatusPublished

This text of 2012 Ohio 5296 (North Coast Premier Soccer, L.L.C. v. Ohio Dept. of Transp.) is published on Counsel Stack Legal Research, covering Ohio Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
North Coast Premier Soccer, L.L.C. v. Ohio Dept. of Transp., 2012 Ohio 5296 (Ohio Super. Ct. 2012).

Opinion

[Cite as North Coast Premier Soccer, L.L.C. v. Ohio Dept. of Transp., 2012-Ohio-5296.]

Court of Claims of Ohio The Ohio Judicial Center 65 South Front Street, Third Floor Columbus, OH 43215 614.387.9800 or 1.800.824.8263 www.cco.state.oh.us

NORTH COAST PREMIER SOCCER, LLC

Plaintiff

v.

OHIO DEPARTMENT OF TRANSPORTATION, et al.

Defendants

Case No. 2009-07091

Judge Joseph T. Clark Magistrate Lewis F. Pettigrew

DECISION OF THE MAGISTRATE

{¶ 1} Plaintiff brought this action alleging negligence. The issues of liability and damages were not bifurcated and the case proceeded to trial on both issues. {¶ 2} Plaintiff, North Coast Premier Soccer (NCPS), owns and maintains a large soccer complex situated on property both north and west of the interchange of U.S. Route 224 (US 224), Interstate 71 (I-71), and Interstate 76 (I-76) in Seville, Ohio.1 NCPS’s property, which it purchased from Medina Sod Farms, consists of a front parcel, back parcel, and an indoor facility. At issue in this case is a flood that occurred in August 2007, on NCPS’s 38-acre front parcel. The front parcel is divided by a ditch (middle ditch) that empties into a second ditch to the north of the property (north ditch). Another ditch forms a western boundary (west ditch). It is not disputed that NCPS’s property sits in a designated flood plain and routinely floods. {¶ 3} Prior to the commencement of this action and prior to the flooding at issue in this case, the Ohio Department of Transportation (ODOT) commenced an eminent domain proceeding against NCPS in the Medina County Court of Common Pleas

1 US 224 and I-76 are the same road as they pass NCPS’s property. Case No. 2009-07091 -2- DECISION

captioned Gordon Proctor, Director of Ohio Department of Transportation v. North Coast Premier Soccer, Ltd., et al., Case No. 06-CIV-0108. As a part of the proceeding, ODOT acquired property from NCPS for a construction and improvement project.2 {¶ 4} As a part of the improvement project, ODOT was required to obtain a permit from the Ohio Environmental Protection Agency for a national pollutant discharge elimination system (NPDES). Such a permit allows a contractor to discharge sediment- laden storm water onto the surrounding property so long as the contractor has in place a storm water pollution prevention plan (SWPPP) with appropriate temporary sediment erosion controls (TSEC) utilizing best management practices (BMPs). BMPs are controls that regulate the release of storm water during construction to ensure compliance with the NPDES permit. Supplemental specification 832 requires the contractor to perform its operations in accordance with the permit.3 {¶ 5} The improvement project required the construction of a new 30-foot-high earthen embankment-style ramp (ramp E-S) for westbound traffic from I-76 to southbound I-71. At the base of the embankment, ODOT installed two temporary culverts designed to allow draining water to flow through the embankment and empty into the middle ditch on NCPS’s property. {¶ 6} Project engineer, Luke Wysocki, explained that the method of constructing the earthen damn consists of hauling thousands of tons of earthen fill to the site and then laying and compacting the fill in eight-inch increments per day. ODOT also installed both an inclinometer and a piezometer to measure the water pressure in the earth. {¶ 7} On or about July 11, 2007, Wysocki performed an inspection of the construction project and identified several “deficiencies and concerns.” (Plaintiff’s

2 On November 29, 2011, this court ruled that NCPS had settled and released all claims with respect to the property identified in the Judgment Entry in the eminent domain proceeding. 3 ODOT engineer Ron Trivisonno explained that supplemental specification 833 was merged into the body of supplemental specification 832 eliminating the need for two separate specifications. Case No. 2009-07091 -3- DECISION

Exhibit 8.) On July 18, 2007, Wysocki placed the Ruhlin Company on “notice that deficiencies exist throughout the project that will need to be corrected in order to be compliant with Supplemental Specifications 832, 833, and the NPDES Construction Storm Water General Permit.” (Plaintiff’s Exhibit 8.) Specifically, Wysocki identified a need to install sediment basins, ditch checks, sediment dams, rock channel protection, and perimeter fabric fencing. Wysocki also noticed a large crack in the embankment. (Plaintiff’s Exhibits 38 and 39.) {¶ 8} In early August 2007, Wysocki observed that the piezometers began to read higher than what was allowed by the project specifications and that there was a large depression in the embankment directly above the culverts, all of which led him to believe that one of the temporary culverts had collapsed. (Plaintiff’s Exhibit 9.) By August 14, 2007, Wysocki noticed that “two large depressions” had formed over the culvert pipes, which appeared to him to have “completely collapse[d].” (Plaintiff’s Exhibit 12.) On August 17, 2007, Wysocki met with several ODOT engineers and determined that the capacity of the culverts was significantly reduced and that there were concerns about storm water management. Although ODOT decided to install a sump pump to reduce ground water and control storm water, Wysocki admitted that ODOT never installed such a pump. {¶ 9} On August 20, 2007, heavy rains forced a shutdown of the construction site. As a result of both the heavy rains and the failed culverts, water began accumulating on the south side of ramp E-S. The storm water eventually backed up onto I-76, forcing the closure of several lanes of traffic. Wysocki subsequently directed Ruhlin Company to pump the water off of I-76 and into a ditch along I-76 (I-76 ditch). Wysocki testified that the water was pumped into the I-76 ditch, which he believed emptied directly into the west ditch on the west side of NCPS’s property. However, Wysocki admitted that he did not confirm that any of the redirected storm water was actually reaching the west ditch and that he was unaware that ODOT was pumping the water against the grade of the property. Wysocki stated that no one from ODOT asked NCPS for permission to Case No. 2009-07091 -4- DECISION

pump water onto its property and that ODOT did not have a permit to discharge water into the west ditch. {¶ 10} Wysocki testified that pumping stopped either on August 23, 2007, or August 24, 2007. According to Wysocki’s daily diary report dated August 22, 2007, pumping was to continue throughout the night and the pumps were to be “hauled off site tomorrow.” (Plaintiff’s Exhibit 18.) {¶ 11} NCPS’s representative Michael Sweeney testified that part of the 38-acre front parcel routinely floods but that the water usually recedes within a day or a day and a half. According to Sweeney, when the water receded in August 2007, the soccer fields were covered with a thick layer of sediment, clay, and silt. Sweeney explained that a typical flood would have clear water and the fields would be ready for use within days, but that was not the case in this instance. {¶ 12} Ryan Gregoire, owner of Medina Sod Farms, which sits adjacent to NCPS’s front parcel, testified that in a typical flood, the water is fairly clear. According to Gregoire, the water in August 2007 was brown and muddy, and that when the water receded, he noticed a very strong silt line on the vegetation. Gregoire explained that silt and clay are fine particles that clog porous spaces and eliminate drainage. Gregoire asserted that too much silt can kill vegetation because it blocks the plants from receiving light. Sweeney testified that as a result of the flood, much of the 38-acre parcel was unusable for soccer without extensive repairs. Sweeney asserted that because some of the fields were unusable, soccer tournaments and games were either relocated or cancelled and that the business’s reputation was harmed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wagenheim v. Alexander Grant & Co.
482 N.E.2d 955 (Ohio Court of Appeals, 1983)
Franklin County District Board of Health v. Paxson
2003 Ohio 1331 (Ohio Court of Appeals, 2003)
Henry v. City of Akron
501 N.E.2d 659 (Ohio Court of Appeals, 1985)
Laipply v. Bates
849 N.E.2d 308 (Ohio Court of Appeals, 2006)
Henderson v. Spring Run Allotment
651 N.E.2d 489 (Ohio Court of Appeals, 1994)
Abraham v. BP Exploration & Oil, Inc.
2002 Ohio 4392 (Ohio Court of Appeals, 2002)
Reith v. McGill Smith Punshon, Inc.
840 N.E.2d 226 (Ohio Court of Appeals, 2005)
Pryor v. Webber
263 N.E.2d 235 (Ohio Supreme Court, 1970)
Columbus Finance, Inc. v. Howard
327 N.E.2d 654 (Ohio Supreme Court, 1975)
McGlashan v. Spade Rockledge Terrace Condo Development Corp.
402 N.E.2d 1196 (Ohio Supreme Court, 1980)
O'Stricker v. Jim Walter Corp.
447 N.E.2d 727 (Ohio Supreme Court, 1983)
Menifee v. Ohio Welding Products, Inc.
472 N.E.2d 707 (Ohio Supreme Court, 1984)
Armstrong v. Best Buy Co.
2003 Ohio 2573 (Ohio Supreme Court, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
2012 Ohio 5296, Counsel Stack Legal Research, https://law.counselstack.com/opinion/north-coast-premier-soccer-llc-v-ohio-dept-of-tran-ohioctcl-2012.