North Coast Electric Company v. Safari Electric LLC

CourtDistrict Court, W.D. Washington
DecidedMay 4, 2021
Docket2:19-cv-00763
StatusUnknown

This text of North Coast Electric Company v. Safari Electric LLC (North Coast Electric Company v. Safari Electric LLC) is published on Counsel Stack Legal Research, covering District Court, W.D. Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
North Coast Electric Company v. Safari Electric LLC, (W.D. Wash. 2021).

Opinion

1 HONORABLE RICHARD A. JONES

9 UNITED STATES DISTRICT COURT WESTERN DISTRICT OF WASHINGTON 10 AT SEATTLE

11 THE UNITED STATES FOR THE USE OF 12 NORTH COAST ELECTRIC COMPANY, Case No. 2:19-cv-00763-RAJ Plaintiff, 13 ORDER DENYING MOTION FOR v. 14 PARTIAL SUMMARY JUDGMENT 15 SAFARI ELECTRIC, LLC, et al., 16 Defendants. 17 I. INTRODUCTION 18 This matter comes before the Court on Plaintiff’s First Motions for Partial 19 Summary Judgment (Dkt. # 37). Having considered the submissions of the parties, the 20 relevant portions of the record, and the applicable law, the Court finds that oral argument 21 is unnecessary. For the reasons below, the motion is DENIED. 22 II. BACKGROUND 23 Defendant RORE Inc. (“RORE”), a general contractor, had a federal construction 24 project at Substation 6A of the Bangor Naval Base in Bremerton, Washington 25 (“Substation 6A Project”). Dkt. # 40 ¶ 2. To secure the project, RORE furnished a 26 Miller Act payment bond. Id. ¶ 3. RORE in turn contracted with Defendant Safari 27 1 Electric LLC (“Safari”) to provide RORE with “electrical contracting services to the 2 Substation 6A Project.” Id. ¶ 2. Safari then in turn contracted with Plaintiff North Coast 3 Electric Company (“North Coast”), a distributor of electrical materials. Id. ¶ 4; Dkt. # 29 4 ¶ 2. At issue in this motion is Safari’s agreement with North Coast. Dkt. # 37. 5 Safari and North Coast entered a contract to replace the “15Kv Switchgear” for the 6 Substation 6A Project. Dkt. # 40 ¶ 4. A “switchgear” is a set of “complex controls and 7 switches for controlling the flow of electricity.” Dkt. # 29 ¶ 6. Under their agreement, 8 North Coast would sell to Safari materials and services, including among other things a 9 switchgear, “[e]ngineering,” “[f]actory [t]esting,” and “[f]ield [s]upervision.” Dkt. # 40- 10 1 at 2, 4; see also Dkt. # 29 ¶¶ 6-7; Dkt. # 40 ¶¶ 4-6. The parties entered several 11 agreements to that end. Dkt. # 29 ¶¶ 3-6; Dkt. # 40 ¶¶ 5-6. Which agreements and terms 12 are controlling is in dispute. Compare Dkt. # 37 with Dkt. # 39. 13 North Coast indeed supplied some of the materials, but Safari did not pay the full 14 contract price. Dkt. # 30 ¶¶ 7, 13; Dkt. # 40 ¶ 26. Given Safari’s failure to pay, in 15 January 2019, North Coast notified Safari and RORE of its Miller Act bond claim. Dkt. 16 # 30-5. 17 A month later, on February 7, 2019, Safari sued North Coast for breach of contract 18 and declaratory relief in Kitsap County Superior Court. Dkt. # 41 ¶ 2; see also Dkt. 19 ## 41-1, 41-2. More than three months after that, on May 21, 2019, North Coast sued 20 Safari, RORE, and several other Defendants in this action. Dkt. # 1. 21 Given the pending, first-filed state court action, Defendants moved to dismiss, or 22 in the alternative stay, this action. Dkt. # 16. The Court granted the motion in part and 23 denied it in part. Dkt. # 47. The Court dismissed all Miller Act bond claims, but granted 24 North Coast leave to amend two, its Bangor Substation 6A and Joint Base Lewis-McCord 25 Miller Act bond claims. Id. And despite the ongoing proceeding in state court, the Court 26 denied Defendants’ request to stay this action. Id. Soon after, North Coast filed its Third 27 Amended Complaint. Dkt. # 48. 1 This matter now comes before the Court on North Coast’s motion for partial 2 summary judgment. Dkt. # 37. According to North Coast, it “seeks relief only against 3 one party, Defendant Rore, on only one of the multiple contracts in dispute.” Id. at 4. It 4 also seeks several “motions for declaratory relief” regarding the formation and 5 interpretation of the parties’ various contracts. Id. The motion fully briefed and ripe for 6 adjudication. Dkt. ## 39, 44. 7 III. LEGAL STANDARD 8 Summary judgment is appropriate if there is no genuine dispute as to any material 9 fact and the moving party is entitled to judgment as a matter of law. Fed. R. Civ. P. 10 56(a). The moving party bears the initial burden of demonstrating the absence of a 11 genuine issue of material fact. Celotex Corp. v. Catrett, 477 U.S. 317, 323 (1986). 12 Where the moving party will have the burden of proof at trial, it must affirmatively 13 demonstrate that no reasonable trier of fact could find other than for the moving party. 14 Soremekun v. Thrifty Payless, Inc., 509 F.3d 978, 984 (9th Cir. 2007). On an issue where 15 the nonmoving party will bear the burden of proof at trial, the moving party can prevail 16 merely by pointing out to the district court that there is an absence of evidence to support 17 the non-moving party’s case. Celotex Corp., 477 U.S. at 325. If the moving party meets 18 the initial burden, the opposing party must set forth specific facts showing that there is a 19 genuine issue of fact for trial to defeat the motion. Anderson v. Liberty Lobby, Inc., 477 20 U.S. 242, 250 (1986). The court must view the evidence in the light most favorable to 21 the nonmoving party and draw all reasonable inferences in that party’s favor. Reeves v. 22 Sanderson Plumbing Prods., 530 U.S. 133, 150-51 (2000). 23 IV. DISCUSSION 24 A. Miller Act 25 To prevail under the Miller Act, a material supplier needs to prove four elements: 26 (1) the materials were supplied in prosecution of the work provided for in the contract; 27 (2) he has not been paid; 1 (3) he had a good faith belief that the materials were intended for the 2 specified work; and 3 (4) the jurisdictional requisites were met. 4 U.S. ex rel. Martin Steel Constructors, Inc. v. Avanti Constructors, Inc., 750 F.2d 759, 5 761 (9th Cir. 1984). 6 For the first three elements, there appears to be no dispute. RORE and Safari 7 entered a contract to replace the 15Kv Switchgear at Substation 6A on the Bangor Naval 8 Base in Bremerton, Washington. Dkt. # 40 ¶ 2. In turn, Safari contracted with North 9 Coast. Id. ¶ 4; Dkt. # 29 ¶ 6. Under their agreement, North Coast sold to Safari materials 10 and services, including among other things a switchgear, “[e]ngineering,” “[f]actory 11 [t]esting,” and “[f]ield [s]upervision.” Dkt. #40-1 at 2, 4; see also Dkt. # 29 ¶¶ 6-7; Dkt. 12 # 40 ¶¶ 4-6. The parties do not dispute that North Coast supplied at least some of those 13 materials, satisfying the first element. Dkt. # 30 ¶ 13. There is also no dispute that North 14 Coast has not been paid the full contract price, satisfying the second. Id. ¶ 7; Dkt. # 40 15 ¶ 26. Finally, the parties do not dispute that North Coast had a good faith belief that the 16 materials were intended for the Bangor Substation 6A project. 17 The fourth element, on the other hand, is in genuine dispute, defeating summary 18 judgment. “Jurisdictional requisites” refer to the “timely notice and filing” requirements 19 under the Miller Act. Martin Steel, 750 F.2d at 761; see also United States ex rel. 20 Hawaiian Rock Prod. Corp. v. A.E. Lopez Enterprises, Ltd., 74 F.3d 972, 975 (9th Cir. 21 1996). Under 40 U.S.C. § 3133, a supplier bringing a Miller Act bond claim must give 22 written notice to the contractor within 90 days from “the date on which the person did or 23 performed the last of the labor or furnished or supplied the last of the material for which 24 the claim is made.” The “test to be applied” is “the last date on which work was 25 performed under the contract,” not the date “when repairs were made following 26 inspection of the project.” United States ex rel.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brown v. Jackson
20 U.S. 218 (Supreme Court, 1822)
Helen Thomas v. United States
239 F.2d 7 (Tenth Circuit, 1956)
United States v. Avanti Constructors, Inc.
750 F.2d 759 (Ninth Circuit, 1984)
Reeves v. Sanderson Plumbing Products, Inc.
530 U.S. 133 (Supreme Court, 2000)
Soremekun v. Thrifty Payless, Inc.
509 F.3d 978 (Ninth Circuit, 2007)
Standard Oil Co. v. Atlantic Coast Line R.
6 F.2d 911 (E.D. North Carolina, 1925)

Cite This Page — Counsel Stack

Bluebook (online)
North Coast Electric Company v. Safari Electric LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/north-coast-electric-company-v-safari-electric-llc-wawd-2021.