North American Philips Company, Inc. v. United States

292 F.2d 861
CourtUnited States Court of Claims
DecidedOctober 4, 1961
Docket354-56
StatusPublished

This text of 292 F.2d 861 (North American Philips Company, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
North American Philips Company, Inc. v. United States, 292 F.2d 861 (cc 1961).

Opinion

LARAMORE, Judge.

This is a suit for the recovery of alleged termination costs growing out of a contract that was terminated for the convenience of the Government pursuant to the Contract Settlement Act of 1944, 41 U.S.C.A. § 101 et seq.

The contract involved in this case was originally entered into with Philips Laboratories, Inc. However, on July 2,1954, they entered into an agreement with the defendant whereby the plaintiff herein was substituted as the contractor under the contract.

The facts in this case are set out fully in the findings and will only briefly be related in this opinion.

Towards the end of World War II a Dutch company known as N. V. Philips Gloeilampenfabrieken was engaged in developmental work on an external combustion engine. In September of 1944, after the Germans had been driven out of Holland, an Allied mission went to the Netherlands to obtain technical intelligence on various projects. Reports on the nature of the Philips’ developmental work were sent to Washington where they created interest on the part of the Navy’s Bureau of Ships. As a result of this interest, the Navy and Philips Eindhoven decided to join forces for the further development of these engines. It was determined that these engines could best be developed in the United States and a new corporation known as Philips Laboratories, Inc., was formed on June 11, 1945, for that purpose. Pursuant to this plan it was agreed between the parties that a group of Dutch technicians and their families, together with special equipment and technical data, would be brought to this country for a period of 18 months. Even though no contract was signed at that time, this group immediately began work at Dobbs Ferry, New York, on the development of the new engine.

Thereafter, following nearly nine months of negotiations, a contract was *863 entered into on June 19, 1946. tract was dated June 1,1946. This con-

During the negotiations, Philips proposed to undertake a cost contract with the Navy which would include task orders for various units of work. It was ultimately agreed that each task order would fall into one of three categories, depending upon the relative commercial and military value of the engine to be developed. The Navy would pay 60 percent of the cost of a task order with high commercial potential, 80 percent of the cost where there was only a moderate commercial potential, and 100 percent of the cost where the end product of a task order had only military potential.

It was intended that the contract would last 10 years. The general provisions of the contract provided that title to all property purchased or produced for use under the contract should vest in the Government. The contract contained provisions whereby Philips would pay 40 percent of the cost under the first three task orders. The contract further provided that the Government must reimburse the contractor, upon termination, for all costs and expenses for which the contractor was to be reimbursed or otherwise compensated under the contract and for which payment had not been made prior to the termination. In the event of such a termination by the Government, Philips was to transfer title (to the extent that title had not already been transferred), and deliver to the Government the fabricated or unfabricated parts, work in progress, completed work, supplies and other material produced as a part of or acquired in respect of the performance of the work terminated, as well as special tools and tooling acquired or manufactured for the performance of the contract.

On September 10,1946, Task Order No. 1 was issued, and on December 20, 1946, Task Order No. 2 was issued. The spirit and intent of these task orders was stated to be embodied in the Navy letter of intent dated September 26,1945. These orders, containing special details, called for the development and construction of a new type external combustion engine to be incorporated in a standard generating set. It was estimated that the work would require 20 months of development. However, technical difficulties were encountered, and in February 1947 Philips, advised that the work on the first three task orders would run over 27 months.

Due to a limitation on the Navy’s funds, as well as some impatience with the progress of the work on Task Orders Nos. 1 and 2, the Navy amended these orders so as to remove electrical generator requirements and permit the work to concentrate on engine development.

On March 12, 1948, Task Order No. 2 was issued and three days later Task Order No. 2 was terminated. However, it was provided that work under Task Order No. 3 should not begin until the first “basic” engineering prototype engine covered by Task Order No. 1 was accepted by the Government. Philips prematurely delivered the work product under Task Order No. 1, which was accepted by the Government on June 1, 1948. The Navy then authorized Philips to proceed with Task Order No. 3. Shortly thereafter, Philips admitted being overanxious on the first engine and requested its return for additional development.

On April 26, 1949, Philips proposed to the Navy that Task Orders Nos. 1 and 3 be terminated and that a fourth task order be issued. In support of this proposal Philips pointed out that the requirements of Task Order No. 1 had been substantially satisfied and that it would be impractical to press for further refinements. As to Task Order No. 3, it was stated that there was no apparent interest in that type of engine. Philips suggested the development of a 1-horse-power engine as the next logical step in the development process. This proposal was rejected by the Government on May 12, 1949.

On October 25, 1949, it was decided that the contract be terminated for the convenience of the Government.

On March 2, 1950, the contracting officer determined that Philips’ performance was complete, but disagreements arose *864 concerning the scope of Philips’ termination claim. It is as a result of these disagreements that this lawsuit was instigated. The plaintiff seeks a fair and reasonable amount for its termination costs and expenses.

The plaintiff predicates a claim for recovery on each of four counts: First, an equity in the termination inventory equal to 65 percent of 40 percent of the cost of such inventory. Second, interest on the amount of its claim from the date of the termination of the contract. Third, expenses alleged to have been incurred as a result of the termination of the contract. Fourth, expenses alleged to have been incurred as post-termination expenditures.

We will deal with each of these counts in order. In the first count, the plaintiff contends that it never intended to enter into a contract that provided that it would pay 40 percent of the costs of machinery, materials and equipment which would be required for use during the life of the contract, which was to be for a period of 10 years, give the Government immediate title to those things, and then give the Government the right to terminate the contract at any time thereafter, and thereby obtain a windfall of 40 percent of the costs of those items. The plaintiff recognizes that it did just that, but emphasizes that it is not an equitable situation. This is a reasonable interpretation and we agree with this contention of the plaintiff.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Time for filing suit
28 U.S.C. § 2501
Administrator
41 U.S.C. § 101