North American Oil Co. v. Globe Pipe Line Co.

6 F.2d 564, 1925 U.S. App. LEXIS 2078
CourtCourt of Appeals for the Eighth Circuit
DecidedMay 12, 1925
DocketNos. 6727, 6760
StatusPublished
Cited by9 cases

This text of 6 F.2d 564 (North American Oil Co. v. Globe Pipe Line Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
North American Oil Co. v. Globe Pipe Line Co., 6 F.2d 564, 1925 U.S. App. LEXIS 2078 (8th Cir. 1925).

Opinion

STONE, Circuit Judge.

This is an action by the buyer for damages from breach of a contract to deliver oil. The court directed a verdict for $7,100. From the judgment entered thereon, each party has sued a writ of error.

The essential facts are not in dispute. The contract is as follows:

' “This indenture made and entered into the 27th day of November, 1922, by and between North American Oil Company, hereinafter called the North American Company, party of the first part, and Globe Pipe Line Company, hereinafter called the Globe Company, party of the second part, witnesseth the following facts and agreements:
“(1) The said North American Company owns the oil and gas lease covering the SE^ of the SW% of section 31, township 15, range 15, Ouachita county, Arkansas.
“(2) The Globe Company owns a twenty-eight (28) ear loading rack near Smackover •on the Missouri Pacific Railroad with a four-inch pipe line extending from said loading rack to the lease of said North American Company.
“(3) In consideration of the sum of $1.00 and the further payments to be made as hereinafter set out, the North American Company hereby agrees to deliver into the pipe line of the Globe Company such amount of the oil from the tanks on its lease as the Globe Company is able to take and market: Provided, however, that the Globe Company shall take an average of 1,000 barrels daily or more during the life of this contract.
“(4) The Globe Company shall pay for all oil so furnished the sum of 30e per barrel and payment shall be made on the 1st and 16th days of each calendar month for oil taken up on such dates.
fi(5) All oil furnished under this contract shall be clean pipe line oil and shall contain not more than 1% BS and water. .
“(6) The Globe Company also agrees to load through its line into ears placed on its rack for the North American Company whatever amount of oil can be loaded through its line after the oil it has purchased has been loaded; and the North American Company agrees to furnish for loading under this provision of this contract two-thirds of the idle capacity of said four-inch pipe fine each day: Provided, however, that this provision is subject to the North American Company being able to get ear service in and out for its cars. The Globe Company shall be paid by the North American Company the sum of 7%e per barrel for furnishing loading rack facilities and loading said oil through its line, and settlement for the same shall be made at the time herein-before provided for oil purchased.
“(7) The North American Company will make all the connections to its tanks and bring the oil to the gate valve and shall furnish pump for pumping oil.
“The term of this contract shall be twenty (20) days: Provided, -however, that the same shall be considered renewed for additional periods of twenty (20) days each, until one of the parties shall give the other ten (10) days written -notice of intention to terminate same.”

At the time this contract was made, defendant had, on this leasehold, a well producing about 20,000 barrels per day and about 400,000 barrels of oil in tanks and earthen pits. There was a necessary delay in getting ready to run the oil under the contract so that plaintiff was not prepared to receive oil until December 3d, when 1,267 barrels were run. At request of plaintiff, the oil was shut off that night. Before ordered turned on again, the stored oil was consumed by fire started by lightning. Be[566]*566cause of the fire, the oil well had to be shut down temporarily. The pits were not cool enough for some days to receive oil and deliveries could not be resumed until December 21st or 22d. From that date to January 27th, deliveries to plaintiff were 30,253 (or 30,283) barrels, at the rate of about 1.000 barrels a day. Within this same period (between December 21st and January 10th) defendant sold and delivered to the Standard Oil Company 80,246 barrels from this lease. After January 27th, there were no deliveries as the well had ceased flowing and the tankage was exhausted. Three times the contract was automatically renewed until, on January 27th, defendant gave notice of termination of the contract as of February 15th. February 4th, plaintiff wrote to defendant claiming that defendant had contracted to deliver 80,000 barrels during the 80 days of the contract; that less than 33.000 barrels had been delivered and demanded delivery by February 15th of the remaining 47,000 barrels. February 9th, defendant answered denying liability.

The court treated the arrangement as one contract for eighty days, with the requirement to take approximately 1,000 barrels each day; that there had been performance or legal excuse for nonperformance up to January 28th and held defendant liable for the period of January 28th to February 15th, both inclusive, at the rate of 1,000 barrels per day. The measure of damages was the difference in sale price and market price in this oil field for the period of liability.

The issues presented by the cross-writs of error are as follows:

(1) Were the requirements as to receipt and delivery of oil upon a daily basis, with a minimum requirement of approximately 1.000 barrels each day?
(2) Was this one contract for 80 days or four successive contracts of 20 days each?
(3) Was the fire a legal excuse for nondelivery during the period it prevented delivery?
(4) Irrespective of the two above matters, has the plaintiff the right to require delivery of more than 1,000 barrels a day, as it did February 4th, either on the ground that it was “able to take and market” the “over 47.000 barrels” then demanded or on the related ground that the contract provided for a minimum and maximum amount and the above demand was within the maximum?
(5) Was the measure of damages used by the court correct?

Daily Basis.

Plaintiff contends that the contract did not require it to accept and receive any oil upon any particular day during the contract but that it could order oil whenever it desired and in whatever quantities; provided only, that it took, at some time during the contract, a minimum amount equal to 1,000 barrels for every day the contract lasted. Defendant contends that the contract was on a strictly daily basis; that each day was a separate measuring period during which the plaintiff might order as much oil as it could take and market but must take approximately 1,000 barrels at least. The court adopted defendant’s view.

The contract provision particularly involved in this issue is that “ * * * the North American Company hereby agrees to deliver into the pipe line of the Globe Company such amount of the oil from the tanks on its lease-as the Globe Company is able to take and market: Provided, however, that the Globe Company shall take an average of 1,000 barrels daily or more during the life of this contract.” In respect to.the point now discussed, this quoted provision is ambiguous. The circumstances surrounding the parties when the contract was made remove this uncertainty.

When the contract was made, the situation was as follows: Defendant was engaged in producing crude oil upon a 40-acre leasehold. Plaintiff was engaged in piping and marketing oil.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
6 F.2d 564, 1925 U.S. App. LEXIS 2078, Counsel Stack Legal Research, https://law.counselstack.com/opinion/north-american-oil-co-v-globe-pipe-line-co-ca8-1925.