Norfolk & W. Ry. Co. v. Graham

145 F. 809, 76 C.C.A. 385, 1906 U.S. App. LEXIS 4029
CourtCourt of Appeals for the Fourth Circuit
DecidedMay 1, 1906
DocketNo. 640
StatusPublished
Cited by11 cases

This text of 145 F. 809 (Norfolk & W. Ry. Co. v. Graham) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Norfolk & W. Ry. Co. v. Graham, 145 F. 809, 76 C.C.A. 385, 1906 U.S. App. LEXIS 4029 (4th Cir. 1906).

Opinion

McDOWEEE, District Judge.

The following is an excerpt from the opinion of die trial court:

“This was a suit in assumpsit instituted by John T. Graham, trustee of the estate of O. M. Rage, a bankrupt, against the Norfolk & Western Railway Company, for the recovery of certain moneys alleged to be due to said estate under a contract entered into between said Page and said railway company for the construction of a certain portion of its roadbed in West Virginia. The defendant pleaded nonassmnpsit and also filed a notice of recoupment under the "West Virginia statute, under which it sought to prove damages growing out of the contract or transaction upon which the suit was brought, to an amount equal to the demand against it.
“The parties by mutual consent waived a jury and submitted all matters of law and fact to the judgment of the court upon an agreed statement of all facts, from which statement it appears that O. M. Rage entered into a written contract on the 31th day of August, 3902, with the defendant, by which he agreed to construct for it, at certain prices therein named, sections 21 to 25 inclusive, of the Naugatuck Branch of the Ohio extension of its railroad. That, by the terms of the said contract, on or about the 35th day of each calendar month estimates of the work done by Pago during the preceding month were to be made, and an advance payment of eighty-five per cent. (85%) thereof made to him, the remaining fifteen per cent. (15%) to be retained by the railway company as a compensation for or on account of any damages which might be certified by its engineer to have been sustained from any failure of the said Page to perform said contract. That Page performed work and furnished materials under said contract until the latter part of August, 1903, [810]*810during the whole of which time his total work amounted, according to the terms of the contract, to thirty thousand seven hundred and fifty dollars and eleven cents ($30,750.11), ail of which was paid him, excepting $4,612.52 of retained percentages, and $3,428.25 worth of work estimated to have been done in the month of August, making a total still in the hands of the railway company, retained percentages and August estimate, amounting to $8,040.77. That the retained percentages for the month of May, 1903, amounted to $1,070.53; for the month of June, $570.66; for the month of July, $651.13, and for the month of August, $604.99; all of which percentages are embraced in the sum total retained percentages of $4,612.52 above named, and are separated ■ into months only for the purpose of showing what these percentages amounted to for the four months next preceding the adjudication of Page as a bankrupt. That Page broke his contract and abandoned his work on or about the 28th or 29th day of August, 1903, and the railway company, through its engineer construction work, branch lines, and in accordance with the terms of said contract, immediately declared in writing the same to be terminated and forfeited, which writing was filed with the railway company, a copy thereof mailed to Page’s last known address, and' another copy, as provided in the contract, posted at the front door of his office upon his work, on September 1, 1903. That a petition in bankruptcy was filed against Page on the 1st day of September, 1903, and he duly adjudged a bankrupt on the 10th day of said month. John T. Graham was chosen as trustee in bankruptcy by the creditors, and, by an order of the bankrupt court, was authorized and directed to institute this suit.
“It was further agreed that Page was insolvent at the time of his adjudication as a bankrupt, and that he was at that time indebted to laborers w„ho had performed work for him upon the sections agreed to be constructed by him during the three months next preceding such adjudication, in amounts aggregating five thousand dollars ($5,000.00), but exceeding in no individual case the sum of three hundred dollar^ ($300.00), all of whose claims were proven in the bankrupt court, in accordance with the provisions of the act of Congress. It was further agreed that, after Page had abandoned his work and the railway company, had declared his contract forfeited and at an end, it immediately advertised for bids in the customary way for the completion of the work that had been left unfinished by him. Many contractors made bids thereon, but, after the exercise of due care and diligence in the premises upon the part of the railway company, one John T. McKinney was declared to be the lowest and best bidder, and the contract for the completion of the abandoned work of O. •M. Page was given to the said McKinney. The new contractor entered upon his work and prosecuted the same with diligence, and under the reasonable supervision of the railway company, to completion; but. in consequence [as it was agreed] of the condition in which Page left the work that had been abandoned by him, the railway company was compelled to pay unto McKinney $11,112.80 more than it would have been required to pay to Page upon the completion of said work had ho performed the same at the prices and in accordance with the terms agreed upon by him.
“The defenses of the railway company were two: (1) That, under the plea of non-assumpsit, and by the Very terms' of the contract itself, it did not owe Page anything; because it had a right to keep not only the retained percentages of $4,612.52, but the August estimate of $3,428.25, as well; the title thereto never having vested in Page, in consequence of his agreement that no money was to become due or payable to him or demandable by him until after the whole work had been completed in a satisfactory manner and certified by the engineer of the railway company, which had not been done. (2) That, even if said retained percentages and August estimate should be held to be a debt due from the railway company to Page, still nothing would be recoverable against the railway company in consequence of its right to recoup, to the extent thereof, or offset against the same, the damages occasioned to it by the very breach by Page of the contract sued upon.”

The declaration consisted of the common counts in assumpsit and several special counts founded on the contract. It does not appear whether or not the railway company knew of the bankruptcy proceed[811]*811ings prior to the institution of this action. The trial court ruled in favor of the railway as to the fifteen per cent, retained from the various monthly estimates. Tut, being of opinion that defense as to the 85 per cent, of the August estimate could only be made by way of counterclaim, and that section 5?n, 30 Stat. 561 [U. S. Comp. St. 1901, p. 3,444"], barred such counterclaim, the judgment below was as to this item adverse to the railway company. The opinion as to the effect of the bankrupt act reads as follows:

‘■The only other feature necessary to be considered is as to the applicability of the notice of recoupment filed with the plea of nouassumpsit. As the estate of Page, here represented by the trustee, is .’mt of a bankrupt, the question as to the availability of this notice is solvable! only under the provisions of the bankruptcy act, and under those provisions I must hold that it is ineffectual, it is provided by Act July 1, 1898, c. 541, § 68b, 30 Stat 565 [U. S. Comp. St. 3901. p. 3450], that a set-off or counter claim shall not be allowed in favor of any debtor of the bankrupt which is not made provable against the estate. This account for damages for failure to complete the bankrupt’s contract is not so provable, because of lapse of time, and therefore cannot now be set off.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

William J. Rochelle, Jr., Trustee v. United States
521 F.2d 844 (Fifth Circuit, 1975)
Willcox v. Goess
92 F.2d 8 (Second Circuit, 1937)
First Nat. Bank of Indianola v. Malone
76 F.2d 251 (Eighth Circuit, 1935)
Smith v. Hale
227 N.W. 373 (South Dakota Supreme Court, 1929)
Patten v. Hill County
297 S.W. 918 (Court of Appeals of Texas, 1927)
Gardner v. George F. Hills Co.
246 F. 790 (Third Circuit, 1917)
Standard Engineering & Construction Co. v. Smyser-Royer Co.
68 Pa. Super. 437 (Superior Court of Pennsylvania, 1917)
Mahr v. Maryland Casualty Co.
156 N.W. 668 (Supreme Court of Minnesota, 1916)
Couturie v. Roensch
134 S.W. 413 (Court of Appeals of Texas, 1911)
In re T. M. Lesher & Son
176 F. 650 (E.D. Pennsylvania, 1910)

Cite This Page — Counsel Stack

Bluebook (online)
145 F. 809, 76 C.C.A. 385, 1906 U.S. App. LEXIS 4029, Counsel Stack Legal Research, https://law.counselstack.com/opinion/norfolk-w-ry-co-v-graham-ca4-1906.