Norfolk Southern Railway Company v. Zayo Group, LLC

87 F.4th 585
CourtCourt of Appeals for the Fourth Circuit
DecidedDecember 8, 2023
Docket22-1554
StatusPublished

This text of 87 F.4th 585 (Norfolk Southern Railway Company v. Zayo Group, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Norfolk Southern Railway Company v. Zayo Group, LLC, 87 F.4th 585 (4th Cir. 2023).

Opinion

USCA4 Appeal: 22-1554 Doc: 49 Filed: 12/08/2023 Pg: 1 of 14

PUBLISHED

UNITED STATES COURT OF APPEALS FOR THE FOURTH CIRCUIT

No. 22-1554

NORFOLK SOUTHERN RAILWAY COMPANY,

Plaintiff - Appellee,

v.

ZAYO GROUP, LLC,

Defendant - Appellant.

Appeal from the United States District Court for the Eastern District of Virginia, at Alexandria. Liam O’Grady, Senior District Judge. (1:21-cv-01299-LO-JFA)

Argued: October 25, 2023 Decided: December 8, 2023

Before HARRIS and QUATTLEBAUM, Circuit Judges, and Kenneth D. BELL, United States District Judge for the Western District of North Carolina, sitting by designation.

Affirmed by published opinion. Judge Quattlebaum wrote the opinion, in which Judge Harris and Judge Bell joined.

ARGUED: William H. Hurd, ECKERT SEAMANS CHERIN & MELLOTT, LLC, Richmond, Virginia, for Appellant. Tobias S. Loss-Eaton, SIDLEY AUSTIN LLP, Washington, D.C., for Appellee. ON BRIEF: Annemarie DiNardo Cleary, Cody T. Murphey, Richmond, Virginia, Charles A. Zbedski, ECKERT SEAMANS CHERIN & MELLOTT, LLC, Washington, D.C., for Appellant. Gordon D. Todd, Cody L. Reaves, Stephen S. Laudone, SIDLEY AUSTIN LLP, Washington, D.C., for Appellee. USCA4 Appeal: 22-1554 Doc: 49 Filed: 12/08/2023 Pg: 2 of 14

QUATTLEBAUM, Circuit Judge:

When two companies agree to a method for resolving their disputes, they are bound

by their contract. An internet provider, Zayo Group, LLC, entered such an agreement when

it leased a utility duct from Norfolk Southern Railway Company. When it came time to

renew the lease, Zayo and Norfolk Southern could not agree to the renewal rent. As the

lease instructed, they submitted the dispute to three appraisers, who decided the rent by a

two-to-one vote. But because the appraisers did not unanimously agree, Zayo refused to

pay that rent. Norfolk Southern sued for breach of the lease and moved to confirm the

appraisal as an arbitration award under the Federal Arbitration Act (“FAA”), 9 U.S.C.

§§ 1–16. After confirming the appraisal, the district court entered judgment on the

pleadings for Norfolk Southern, ordering Zayo to pay the rental amount determined by the

appraisers. Regardless of whether the district court properly confirmed the appraisal under

the FAA, the lease was a contract and bound Zayo to pay the amount set by the appraisers,

even if not decided unanimously. Since Zayo did not pay that amount, we affirm the

judgment on the pleadings.

I.

To supply internet, Zayo operates a fiber optic cable buried in a two-inch duct

running along nearly twenty-five miles of railroad in Virginia. Zayo pays rent to use the

duct under a lease that the railroad company, Norfolk Southern, executed in 1999 with a

corporation called Metromedia Fiber Network Services, Inc. Zayo acquired Metromedia in

2012. The lease provided for an initial twenty-year term, with rent starting at $8,000 per

2 USCA4 Appeal: 22-1554 Doc: 49 Filed: 12/08/2023 Pg: 3 of 14

mile per year, for a total nearing $200,000 per year. The lease also gave Zayo the option of

renewing for two ten-year terms. Rent for those renewal terms was to be adjusted to “reflect

the fair market value” of the leased interest. J.A. 94.

Section 4(b) of the lease provided a process for determining that rent:

J.A. 94. Critically, if two party-appointed appraisers could not agree on the adjusted rent,

the appraisers would jointly select a third appraiser, whom both parties would compensate,

and “the three shall determine” the new rent with “final and binding” effect. J.A. 94. During

this process, the lease required Zayo to continue paying the prior rent and to pay “any

excess due” upon the “final determination” of the new rent. J.A. 94.

When Zayo first sought to renew the lease in April 2019, Zayo and Norfolk Southern

could not agree on the adjusted rent. Under section 4(b) of the lease, Norfolk Southern

proposed a rate in late 2019, and Zayo objected. Zayo failed to offer a counter appraisal

within the required sixty days under section 4(b). While Norfolk Southern believed that

3 USCA4 Appeal: 22-1554 Doc: 49 Filed: 12/08/2023 Pg: 4 of 14

Zayo’s delay breached the lease, the parties resolved that timing dispute by amending the

lease in April 2020. The amendment extended Zayo’s appraisal deadline to September

2020 in exchange for “Extension Payments.” J.A. 111–12. And the amendment

acknowledged that, even though Zayo had yet to provide its own appraisal, Norfolk

Southern had commissioned and completed an appraisal, constituting the “second

appraisal” under section 4(b). J.A. 112. The amendment also detailed a process for jointly

selecting the third appraiser: if Norfolk Southern’s and Zayo’s appointed appraisers could

not agree on the adjusted rent within thirty days of their initial consultation, Norfolk

Southern’s appointed appraiser had ten business days to provide a list of three possible

appraisers, all of whom must have been “Members of the Appraisal Institute,” to Zayo’s

appointed appraiser, who would have an additional ten business days to select a name from

the list. J.A. 85; J.A. 112. Once the third appraiser had been selected, the three appraisers

were to “proceed as prescribed by Section 4(b)” of the lease. J.A. 112.

After the party-appointed appraisers reached a stalemate, Norfolk Southern

provided three possible third appraisers to Zayo, which picked one. In corresponding about

engaging the third appraiser, the parties expressed disagreement about section 4(b) of the

lease. Zayo claimed that section meant the parties would be bound only by a unanimous

decision of all three appraisers, while Norfolk Southern said a majority decision would

suffice. Having registered their disagreement, the parties permitted the appraisal to

proceed.

The appraisers reached a “Panel Determination” by a two-to-one vote. J.A. 67. Over

the dissent of the appraiser appointed by Zayo, the other two appraisers agreed that the rent

4 USCA4 Appeal: 22-1554 Doc: 49 Filed: 12/08/2023 Pg: 5 of 14

for the renewal term should begin at $2,340,000 per year. Norfolk Southern sought to

collect, issuing two invoices. Zayo did not pay in full, maintaining that a nonunanimous

decision was not binding.

Norfolk Southern sued Zayo to recover the rent due on a breach of contract theory,

invoking the district court’s diversity jurisdiction. 1 See 28 U.S.C. § 1332. Norfolk Southern

then moved to confirm the appraisal as an arbitration award under the FAA. See 9 U.S.C.

§ 9. Less than a week later, Norfolk Southern filed its operative amended complaint,

alleging breach of contract and seeking both damages for Zayo’s past failure to pay and a

declaration that Zayo owed the panel-determined amount moving forward.

The district court confirmed the appraisal as an arbitration under the FAA. In doing

so, the district court rejected Zayo’s argument that the appraisal panel could act only

unanimously. First, the court concluded, “[A]n interpretation of the contract that requires

the appraisal panel’s decision to be unanimous is inconsistent with the plain language of

the contract.” J.A. 258. Alternatively, the district court decided that the appraisers could

decide for themselves whether to return a finding based on a majority vote rather than a

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hobson v. Heirs of McArthur
41 U.S. 182 (Supreme Court, 1842)
Eure v. Norfolk Shipbuilding & Drydock Corp.
561 S.E.2d 663 (Supreme Court of Virginia, 2002)
Donnelly v. Donatelli & Klein, Inc.
519 S.E.2d 133 (Supreme Court of Virginia, 1999)
Martin & Martin, Inc. v. Bradley Enterprises, Inc.
504 S.E.2d 849 (Supreme Court of Virginia, 1998)
Rash v. Hilb, Rogal & Hamilton Co.
467 S.E.2d 791 (Supreme Court of Virginia, 1996)
Durham v. National Pool Equipment Co.
138 S.E.2d 55 (Supreme Court of Virginia, 1964)
Amos v. Coffey
320 S.E.2d 335 (Supreme Court of Virginia, 1984)
W. F. Magann Corp. v. Virginia-Carolina Electrical Works, Inc.
123 S.E.2d 377 (Supreme Court of Virginia, 1962)
Wilson v. Holyfield
313 S.E.2d 396 (Supreme Court of Virginia, 1984)
Meade v. Wallen
311 S.E.2d 103 (Supreme Court of Virginia, 1984)
City of Chesapeake v. Dominion Securityplus Self Storage, L.L.C.
785 S.E.2d 403 (Supreme Court of Virginia, 2016)
RLM Communications, Inc. v. Amy Tuschen
831 F.3d 190 (Fourth Circuit, 2016)
Erie Ins. Exchange v. EPC MD 15, LLC
822 S.E.2d 351 (Supreme Court of Virginia, 2019)
Lamps Plus, Inc. v. Varela
587 U.S. 176 (Supreme Court, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
87 F.4th 585, Counsel Stack Legal Research, https://law.counselstack.com/opinion/norfolk-southern-railway-company-v-zayo-group-llc-ca4-2023.