Nordlund & Associates, Inc. v. Village of Hesperia

792 N.W.2d 59, 288 Mich. App. 222
CourtMichigan Court of Appeals
DecidedApril 20, 2010
DocketDocket No. 289304
StatusPublished
Cited by17 cases

This text of 792 N.W.2d 59 (Nordlund & Associates, Inc. v. Village of Hesperia) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nordlund & Associates, Inc. v. Village of Hesperia, 792 N.W.2d 59, 288 Mich. App. 222 (Mich. Ct. App. 2010).

Opinion

PER CURIAM.

Plaintiff, Nordlund & Associates, Inc., appeals as of right the circuit court’s order confirming an arbitration award and denying plaintiffs motion to vacate or modify the arbitration award. We affirm.

I. FACTS

On January 7, 2005, plaintiff filed a breach of contract action against the village of Hesperia.1 Defendant filed a counterclaim alleging breach of contract and demanding indemnification.

On January 22, 2007, the circuit court entered a stipulation and order for arbitration pursuant to MCL 600.5001 et seq. The order provided that the parties would submit “all issues in this action which are subject to the jurisdiction of this court” to binding arbitration. Pursuant to the circuit court’s order, the parties executed an arbitration agreement, which stated that “[a]ll theories/defenses and affirmative defenses raised in the pleadings of the parties during the course of these proceedings and associated damages, offsets, and failure to mitigate claims” would be submitted for arbitration.

Before this dispute, plaintiff acted as defendant’s engineer for roughly 22 years. Two projects are relevant to this appeal: (1) the Sunset Boulevard/Family Dollar [224]*224water main project and (2) improvements to the sewer system and wastewater treatment plant, known as “the SRF project” for its connection to the State Revolving Fund.

A. SUNSET BOULEVARD/FAMILY DOLLAR PROJECT

Innovative Construction hired plaintiff to do work in relation to the opening of a Family Dollar store near Sunset Boulevard. In furtherance of this project, plaintiff filed an application on behalf of defendant, seeking authorization to extend a water main along Sunset Boulevard. Plaintiff billed defendant $600 for this work, but never received payment.

Plaintiff also prepared additional permit applications and gave them to defendant to submit to the proper authorities. These permits, which were subsequently denied, required approval by the Michigan Department of Environmental Quality (MDEQ) before the water main could be installed. However, Innovative Construction installed the water main before any permits were approved. As a result, the MDEQ fined defendant $12,140. Defendant sought reimbursement from plaintiff for that amount, charging that plaintiff was responsible for the premature installation.

B. SRF PROJECT

On November 10, 2003, by written contract, defendant hired plaintiff to perform professional services. On August 5, 2004, defendant terminated the contract. The contract provided that it could be terminated without cause and that, upon termination, “[a]n equitable adjustment shall be made in the contract price.” Defendant argued that because only 65 percent of plaintiffs work was salvageable by the engineering firm that [225]*225replaced plaintiff, the “equitable adjustment” should equal that percentage of the fees plaintiff earned, reduced by any payment already made. Defendant claimed that it had paid plaintiff $10,000. Plaintiff disagreed, claiming that it should be paid the full amount of $39,677.18. Plaintiff also disputed the $10,000 reduction, on the ground that defendant’s $10,000 payment was for work performed on another, unrelated job, the Division Street Bridge project.

The parties submitted to the arbitrator an “arbitration summary,” in which they fully briefed the issues to be decided. Following a hearing, the arbitrator issued an opinion setting forth the following findings: (1) plaintiff was entitled to $14,787.29 for the use of its plans and specifications on the SRF project, (2) defendant was entitled to $19,787.42 in compensation for plaintiffs breach of the SRF project contract (that amount being the difference between plaintiffs contract price and what defendant ultimately paid another party to complete the contract), (3) defendant failed to prove that it had paid plaintiff $10,000 on the SRF project, (4) defendant was not entitled to recover any damages attributable to the Sunset Boulevard/Family Dollar project, and (5) plaintiff was entitled to payment of its overdue $600 invoice relating to the Sunset Boulevard/Family Dollar project. After calculating all offsets, the arbitrator awarded defendant a total of approximately $4,400.

Plaintiff moved to vacate or modify the arbitration award, arguing that the arbitrator had “miscalculated” the award of damages, MCR 3.602(K)(2)(a), and exceeded his powers by deciding an issue that had not been submitted to arbitration, MCR 3.602(J)(2)(c). Specifically, plaintiff argued that the breach of contract claim, which the arbitrator found entitled defendant to [226]*226$19,787.42 in compensation, was never brought or argued at arbitration, and that the arbitrator’s decision thus reached “beyond the boundaries of the submission” and should be vacated.

In response, defendant argued that there was no mathematical “miscalculation” as envisioned by MCR 3.602(E)(2)(a) and that the arbitrator did not exceed his powers because no express limit was placed on those powers under the arbitration agreement. The motion was heard on November 10, 2008, and the circuit court ruled from the bench as follows:

I thought the arbitrator was quite thorough relative to the matter and the Court would not intervene and set aside. I agree that none of the statutory bases were clearly struck which would cause this Court to . . . intervene relative to the settlement and the Order and the findings of the arbitrator.

For that reason, I deny your Motion.

The circuit court thereafter issued a written order confirming the arbitration award and denying plaintiffs motion.

II. ANALYSIS

Plaintiff argues that the trial court erred by confirming the arbitration award because the arbitrator both exceeded his powers when he rendered a decision on an issue that had not been submitted to arbitration and “miscalculated” the award of damages. We disagree. A trial court’s decision to enforce, vacate, or modify an arbitration award is reviewed de novo. Saveski v Tiseo Architects, Inc, 261 Mich App 553, 554; 682 NW2d 542 (2004).

If an agreement to arbitrate provides that judgment may be entered on the arbitration award, then it is considered a statutory arbitration. Gordon Sel-Way, Inc [227]*227v Spence Bros, Inc, 438 Mich 488, 495; 475 NW2d 704 (1991). Here, the parties’ arbitration agreement stated that a party could move to enforce the award and that the circuit court could enforce the arbitration award. Therefore, the agreement is for statutory arbitration.

MCR 3.602 governs judicial review and enforcement of statutory arbitration agreements. MCR 3.602(A). MCR 3.602(E) sets forth the reasons for which a trial court may correct or modify an arbitration award:

(2) On motion of a party filed within 91 days after the date of the award, the court shall modify or correct the award if:
(a) there is an evident miscalculation of figures or an evident mistake in the description of a person, a thing, or property referred to in the award;
(b) the arbitrator has awarded on a matter not submitted to the arbitrator, and the award may be corrected without affecting the merits of the decision on the issues submitted; or

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dart Bank v. Pollicella Pllc
Michigan Court of Appeals, 2025
James M Perna v. Health One Credit Union
Michigan Court of Appeals, 2023
Laura Lynn McNay v. James Michael McNay
Michigan Court of Appeals, 2023
20230202_C357990_51_357990.Opn.Pdf
Michigan Court of Appeals, 2023
Domestic Uniform Rental v. Bronson's
Michigan Court of Appeals, 2023
Domestic Uniform Rental v. A2 Auto Center
Michigan Court of Appeals, 2022
2727 Russell Street LLC v. Bert W Dearing Jr
Michigan Court of Appeals, 2019
Darshan Singh Grewal v. Gurmale Singh Grewal
Michigan Court of Appeals, 2019
Kordoba LLC v. Landmark Contracting Company
Michigan Court of Appeals, 2018
Galasso Pc v. James Gruda
Michigan Court of Appeals, 2018
Lesley G McCarthy v. Eugene Pallisco
Michigan Court of Appeals, 2016
Mark L McAlpine v. Donald a Bosco Building Inc
Michigan Court of Appeals, 2014
Mastech Inc v. Bleichert Inc
Michigan Court of Appeals, 2014
Nejla Israel v. Ramiz Putrus
Michigan Court of Appeals, 2014

Cite This Page — Counsel Stack

Bluebook (online)
792 N.W.2d 59, 288 Mich. App. 222, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nordlund-associates-inc-v-village-of-hesperia-michctapp-2010.