Nordin v. May

188 F.2d 411, 1951 U.S. App. LEXIS 3792
CourtCourt of Appeals for the Eighth Circuit
DecidedApril 27, 1951
Docket14258
StatusPublished
Cited by6 cases

This text of 188 F.2d 411 (Nordin v. May) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nordin v. May, 188 F.2d 411, 1951 U.S. App. LEXIS 3792 (8th Cir. 1951).

Opinion

SANBORN, Circuit Judge.

■This is an appeal from a summary judgment dismissing an action brought by Andrew Nordin against W. D. May for an injunction and damages. The action is based upon the claim that May, the lessee of a sawmill and steam plant, was *412 obligated to furnish steam power at cost for the operation of an adjoining dry kiln and hardwood flooring plant owned by Nordin, and had failed and refused to do so. Jurisdiction is based on diversity of citizenship and amount in controversy.

The record is meagre and consists mainly of the pleadings, the motion for summary judgment, and an affidavit and a statement of May. Apparently the facts relative to the issue of liability were not seriously in dispute. The District Court and counsel evidently knew more about them than we can glean from the record on appeal. The brief of the appellant contains the following “Statement of the Case”, and, since its accuracy is not challenged by the appellee, we shall assume its correctness for the purpose of this opinion:

“Each party to this appeal is in possession of a tract of land formerly owned by the Star City Lumber Company. On the tract owned by the appellant, Andrew Nordin, there is situated an oak flooring plant and three kilns used to dry lumber preparatory to processing it into flooring. On the adjacent tract which is occupied by the appellee, W. D. May, as lessee, there is situated a sawmill operated by steam power. During the time when both plants were owned by the Star City Lumber Company, steam from the , sawmill power plant was used to heat the kilns on the oak flooring plant property.
“On February 19, 1947, the Star City Lumber Company executed to the appellant, Andrew Nordin, a mortgage securing advances made by Nordin, which mortgage conveyed as security the oak flooring plant only. This mortgage was duly acknowledged and recorded immediately. The mortgage contained the following provision:
‘In the event of foreclosure of this mortgage, or in the event the mortgagee becomes the mortgagee in possession of said mortgaged premises, the parties of the first part hereby contract and agree and bind themselves, their successors, heirs, and assigns to furnish to the purchaser or owner of said hardwood flooring plant and dry kiln or the mortgagee in-
possession thereof, sufficient steam power to operate said hardwood flooring plant and dry kiln. The charge for furnishing said steam power shall be the actual cost to said parties of first part, their successors, heirs or assigns.’
“Subsequently, the Star City Lumber Company defaulted in payment of the mortgage and the appellant Andrew Nordin brought suit in 'the United States District Court for the Eastern District of Arkansas for foreclosure of his mortgage, together with other mortgages held and acquired by him on the same property, which suit resulted in a decree of foreclosure and the sale of the property to Nordin on August 4, 1950, which was duly concluded with delivery and approval of the Commissioner’s Deed.
“The adjacent tract on which the sawmill is situated was mortgaged by the Star City Lumber Company to one Also-brook. The lumber company defaulted in payment. of ■ that, mortgage also and Alsobrook brought'’a foreclosure suit in the Chancery Court of Lincoln County, Arkansas, which had, not been concluded at the time of trial of the instant case. A receiver was appointed by the Chancery ■Court of Lincoln . County in Alsobrook’s suit and by written .lease agreement the receiver leased the sawmill : property to the appellee W. D. May for a ■ term of seven months,' beginning March 10; 1950.
“According to May’s statement, before leasing the property he consulted with, Nordin about furnishing steam to the dry kilns and agreed that he would furnish the steam in return for the use of one kiln. As he put it, ‘at that time this was temporary until he could find out about the title.’ They began operations under this oral agreement and after two or three months, because of expansion of Nordin’s operations in the flooring plant,, it was agreed that May should use only one-half a kiln in return for furnishing the steam. After Nordin acquired title to the property, he called May’s attention to the provision in the mortgage upon which Nordin’s foreclosure, was based— that the Star City : Lumber Company, their successors, heirs and assigns should *413 furnish to the purchaser or owner of the hardwood flooring plant sufficient steam power to operate the dry kiln at the actual cost. Nordin stated that because of expansion of his operations it was necessary to have the complete use of the kiln and he demanded that steam power be furnished in accordance with the agreement. It is not denied that Nordin has been at all times ready, willing and able to pay any sums due as the cost of steam furnished by the appellee. May denied that he was bound by the agreement in the Star City Lumber Company mortgage (referred to in his statement as Horne’s obligations because Horne was the principal owner) and refused to furnish steam except in return for the use of a kiln. After some dispute, May cut off the supply of steam, thereby stopping the operation of the plant. This suit followed with a prayer for a temporary restraining order to prevent May from stopping the supply of steam, and for damages.
“Motion for summary judgment on the issue of liability alone was filed by the plaintiff, Nordin. There was virtually no dispute as to the material facts. After considering briefs and argument, the Court concluded that the agreement in Nordin’s mortgage for the furnishing of steam to the kiln was not a covenant running with the land binding upon May. Memorandum opinion was filed October 12, 1950, and since plaintiff’s cause was predicated entirely upon the theory that the agreement was a covenant running with the land and could not be sustained otherwise, an order of dismissal was entered October 17, 1950. Notice of appeal was filed November 7, 1950.”

The grounds stated by the District Court for its conclusion that the covenant in the mortgage to Nordin did not run with the land and was not binding upon May, are, in substance as follows: (1) In the foreclosure proceedings under which Nordin acquired title to the flooring plant property, the covenant was treated as personal, and was not made an issue in those proceedings nor reserved in the decree or in the deed of foreclosure. (2) The covenant did not describe the tract from which the steam power was to be furnished by the Star City Lumber Company and its successors and assigns. (3) The mortgage to Alsobrook covering the sawmill and steam plant property contained no covenant that the mortgagee, his heirs, successors or assigns, were obligated to furnish steam power for the operation of the flooring plant pursuant to the covenant in suit. (4) The record title of the land leased to May contained nothing which would constitute constructive notice of the existence of- the covenant. (5) At the time May leased the sawmill property, he had no actual notice of the covenant. (6) The existence of the connection between the sawmill steam plant and the flooring plant and dry kilns was not notice to May of the existence or terms of the covenant.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rooke v. Spickelmier
314 S.W.3d 718 (Court of Appeals of Arkansas, 2009)
Brumbaugh v. Mikelson Land Co.
2008 WY 66 (Wyoming Supreme Court, 2008)
Ark. State Highway Comm. v. McNeill
381 S.W.2d 425 (Supreme Court of Arkansas, 1964)
McMillan v. Malvern Gravel Co.
136 F. Supp. 567 (W.D. Arkansas, 1955)
Nordin v. May
208 F.2d 131 (Eighth Circuit, 1953)

Cite This Page — Counsel Stack

Bluebook (online)
188 F.2d 411, 1951 U.S. App. LEXIS 3792, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nordin-v-may-ca8-1951.