Norcon Power Partners, L.P., Plaintiff-Counter-Defendant-Appellee v. Niagara Mohawk Power Corp., Defendant-Counter-Claimant-Appellant

163 F.3d 153, 1998 U.S. App. LEXIS 32614, 1998 WL 908101
CourtCourt of Appeals for the Second Circuit
DecidedDecember 31, 1998
DocketDocket 96-7283
StatusPublished
Cited by6 cases

This text of 163 F.3d 153 (Norcon Power Partners, L.P., Plaintiff-Counter-Defendant-Appellee v. Niagara Mohawk Power Corp., Defendant-Counter-Claimant-Appellant) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Norcon Power Partners, L.P., Plaintiff-Counter-Defendant-Appellee v. Niagara Mohawk Power Corp., Defendant-Counter-Claimant-Appellant, 163 F.3d 153, 1998 U.S. App. LEXIS 32614, 1998 WL 908101 (2d Cir. 1998).

Opinion

JOHN M. WALKER, Jr., Circuit Judge:

Defendant-Counter-Claimant-Appellant Niagara Mohawk Power Corp. appealed from a judgment of the United States District Court for the Southern District of New York, John E. Sprizzo, District Judge, declaring that Niagara Mohawk has no right to demand additional security or other adequate assurances of the performance of appellee’s contractual obligations under New York law, dismissing Niagara Mohawk’s counterclaim, and enjoining Niagara Mohawk from terminating the contract with Norcon for failure to provide adequate assurances. See Encogen Four Partners, L.P. v. Niagara Mohawk Power Corp., 914 F.Supp. 57, 63 (S.D.N.Y.1996). We certified to the New York Court of Appeals the question of whether a party has the right to demand reasonable assurances outside the confines of contracts governed by the Uniform Commercial Code (“UCC”) where the other party is solvent. See Norcon Power Partners, L.P. n Niagara Mohawk Power Corp., 110 F.3d 6 (2d Cir. 1997) (“Norcon I”). The New York Court of Appeals issued an opinion on December 1, 1998 that answered the question in the affirmative. See Norcon Power Partners, L.P. v. Niagara Mohawk Power Corp., 92 N.Y.2d 458, 682 N.Y.S.2d 664, 705 N.E.2d 656 (1998) (“Norcon II”), attached as an Appendix to this opinion. The background of this case is set forth in the certification order, see Norcon I, 110 F.3d at 6-8, and we will therefore only recapture the salient facts here.

Niagara Mohawk entered into a 25-year contract for the purchase of electricity generated at Norcon’s Pennsylvania facility. The contract provided for three pricing periods. The parties are currently in the second period. During the first period, Niagara Mohawk would pay Norcon six cents per kilowatt hour for electricity. During the second and third periods, the price paid by Niagara Mohawk is based on “Avoided Cost.” Avoided Cost is a measure of the costs Niagara Mohawk would have incurred if it were to generate the electricity itself or purchase it from other sources. During the second period, the payments are calculated by a formula and bounded by a floor and a ceiling. An “Adjustment Account” tracks the difference between the avoided costs and the actual payments made by Niagara Mohawk. During the third period, the price paid by Niagara Mohawk is based on its avoided costs without any ceiling or floor price and payments are further adjusted to reduce the outstanding balance in the Adjustment Account. If, at the end of the second period, the Adjustment Account reflects a balance in favor of Niagara Mohawk (the case where the Avoided Costs were below the floor price) then Niagara Mohawk would correspondingly reduce its payments to Norcon. On the other hand, if the Adjustment Account reflects a balance in favor of Norcon power (the result if the Avoided Costs exceeded the ceiling price), then Niagara Mohawk would correspondingly increase its payments. Any balance remaining at the end of the third period must be paid by either party within thirty days following the end of the third period.

In February 1994, Niagara Mohawk sent Norcon a letter (“Demand Letter”) expressing Niagara Mohawk’s concern that because “analysis shows that the Cumulative Avoided Cost Account ... will reach over $610 million by the end of the second period” it is likely that “Norcon cannot and will not perform its payment obligations in the later years of the [contract].” To prevent a possible loss to Niagara Mohawk, the Demand Letter requested that “Norcon provide adequate assurance to Niagara Mohawk that Norcon will duly perform all of its future repayment obligations.”

Norcon initiated this suit for a declaratory judgment that Niagara Mohawk has no right to demand assurances beyond the rights in the contract, and requested a permanent in *155 junction to enjoin Niagara Mohawk from terminating the contract for the reasons set forth in the Demand Letter. Niagara Mohawk counterclaimed, seeking a declaratory-judgment that it properly exercised its right to demand adequate assurances of Nor eon’s future performance.

The district court rejected Niagara Mohawk’s argument that, under New York common law, a party to a contract may demand adequate assurances of future performance, and then treat the failure to provide the assurances as the repudiation of the contract. Consequently it denied Niagara Mohawk’s counterclaim and enjoined Niagara Mohawk from terminating the contract with Norcon for failure to provide adequate assurances. See Encogen Four Partners, 914 F.Supp. at 60, 63. In our order certifying the question to the New York Court of Appeals, we noted that under present New York law, no right existed to demand adequate assurances of performance as to transactions not covered by the UCC, except where the debtor was insolvent. There was no indication that Norcon was insolvent, and the UCC does not apply to sale of electricity which is a service under New York law. See, e.g., Bowen v. Niagara Mohawk Power Corp., 183 A.D.2d 293, 590 N.Y.S.2d 628, 631 (4th Dep’t 1992). However, the right to demand assurances set forth in UCC § 2-609 has been adopted by the American Law Institute in the Restatement (Second) of Contracts § 251, and several states have extended the right to demand assurances to non-UCC contracts. See, e.g., Lo Re v. Tel-Air Communications Inc., 200 N.J.Super. 59, 490 A.2d 344, 350 (1985) (radio station purchase); Conference Center Ltd. v. TRC-The Research Corp. of New England, 189 Conn. 212, 455 A.2d 857, 863-64 (1983) (constructive eviction); Carfield & Sons, Inc. v. Cowling, 616 P.2d 1008, 1010 (Colo.App. 1980) (construction contract); L.E. Spitzer Co. v. Barron, 581 P.2d 213, 216-17 (Alaska 1978) (construction contract); Drinkwater v. Patten Realty Corp., 563 A.2d 772, 776 (Me.1989) (real estate sale); Jonnet Development Corp. v. Dietrich Industries, Inc., 316 Pa.Super. 533, 463 A.2d 1026, 1032 (1983) (real estate sale).

While we were uncertain as to whether New York would want to extend the right to demand reasonable assurances under New York law to cover the circumstances presented in this case, the possibility that the New York Court of Appeals might wish to do so led us to certify the following question to the New York Court of Appeals:

Does a party have the right to demand adequate assurance of future performance when reasonable grounds arise to believe that the other party will commit a breach by non-performance of a contract governed by New York law, where the other party is solvent and the contract is not governed by the U.C.C.?

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
163 F.3d 153, 1998 U.S. App. LEXIS 32614, 1998 WL 908101, Counsel Stack Legal Research, https://law.counselstack.com/opinion/norcon-power-partners-lp-plaintiff-counter-defendant-appellee-v-ca2-1998.