Norberry One Condominium Ass'n v. Commonwealth, Department of Transporatation

805 A.2d 59, 2002 Pa. Commw. LEXIS 757
Commonwealth Court of Pennsylvania·Decided August 14, 2002·Published·Cited by 6 cases

Opinion

OPINION BY

Judge LEAVITT.

This is an appeal of the order of the Court of Common Pleas of Butler County (trial court) sustaining the preliminary objections of the Department of Transportation (DOT) to a Petition for Appointment of Viewers1 filed by the Norberry One Condominium Association (Association), a non-profit corporation, and twelve individual condominium owners (collectively Nor-berry). Norberry asserts that construction of a highway entrance ramp 60 feet from the Norberry One Condominium Building (Norberry One) effects a defacto condemnation and, therefore, the trial court erred in sustaining DOT’s preliminary objections. For the reasons set forth below, we affirm the trial court.

This matter arises out of a Connector Project (Connector Project) undertaken by DOT and by the Pennsylvania Turnpike Commission (Turnpike) to connect the Pennsylvania Turnpike and Interstate Route 79 (1-79) at the Cranberry Interchange of the Pennsylvania Turnpike in Cranberry Township, Butler County. The Turnpike and DOT divided responsibilities for the joint project; DOT agreed to be responsible for the acquisition of property needed to complete the Connector Project. Planning for the Connector Project began in 1989. By 1995, DOT published a report that selected a plan entitled ‘Alternative 3A Modified” from the number of alternate plans considered for the Connector Project. The 3A Modified Plan called for the total taking of Norberry One.

In January of 1996 the Connector Project was put on hold due to funding problems. In October of 1997, DOT considered the Connector Project ready to proceed, but it was delayed again due to a decision of the Turnpike to alter its toll collection system, necessitating a design change.

In 1998, a consultant retained by DOT for relocating persons displaced by the Connector Project, made initial contact with Cheryl Stanley, a resident and unit owner in Norberry One and the secretary of the Association. At this meeting Ms. Stanley directed the DOT consultant to talk with her and no one else; he provided Ms. Stanley with a number of brochures [63]*63for the residents of Norberry One and, consistent with her directions, did not contact any other tenants or unit owners.

In 1999, as a result of the design change, the Turnpike adopted an alternative implementation plan known as “Alternate K.” The Connector Project was reconfigured so that only a portion of the Norberry One parking lot would be taken, as opposed to the entire property. “Alternate K” required the construction of an access ramp to the connector highway to be built within sixty feet of a corner of the Norberry One budding. The sloping ramp was to be elevated by a concrete wall twelve to fourteen feet in height above ground level with a fifty-two inch high “jersey barrier” on top.

On May 3, 2000, DOT filed a Declaration of Taking and served a Notice of Filing of Declaration of Taking upon the Association president, who was also the property manager, but not upon any individual unit owner. The Declaration of Taking identified a part of the Norberry One parking lot and a construction easement as the “taking.”

On June 1, 2000, Norberry filed preliminary objections to the Declaration of Taking, requesting the trial court to declare the Declaration of Taking void and of no effect or to declare the taking to be a de facto condemnation of the entire building. Norberry’s preliminary objections identified procedural deficiencies in the Declaration of Taking, and it alleged that the project would so deplete the parking lot as to make the units uninhabitable as would the noise, fumes, debris and other effects of the construction. On June 15, 2000, DOT filed preliminary objections to Nor-berry’s preliminary objections to DOT’s Declaration of Taking.2

On June 19, 2001, Norberry filed a Petition for the Appointment of Viewers asserting a de facto taking arising from DOT’s pre-condemnation activities. On June 29, 2001, DOT filed preliminary objections to Norberry’s Petition for Appointment of Viewers.

Upon agreement of the parties and approval of the trial court, the record was developed by depositions and other discovery. After the issues were briefed, the trial court issued its ruling sustaining DOT’s preliminary objections to Norber-ry’s preliminary objections to DOT’s Declaration of Taking. It also sustained DOT’s preliminary objections to Norber-ry’s Petition for Appointment of Viewers. The trial court vacated its prior order appointing a Board of View and dismissed Norberry’s Petition for Appointment of Viewers. Norberry appeals the trial court’s order to this court.3

On appeal, Norberry raises both procedural and substantive issues, as it did below. It contends that DOT’s Declaration of Taking was procedurally deficient because of improper service and failure to include certain information required by statute. Substantively, it contends that the pre-condemnation activities of DOT effected a de facto taking of Norberry One thereby entitling it to just compensation.

I.

Norberry initially challenges the trial court’s decision because it did not rule [64]*64on procedural deficiencies Norberry raised in its preliminary objections. This challenge is compromised by Norberry’s failure to place into the record the specific documents needed to prove the alleged deficiencies. An appellate court may only consider evidence developed below that is duly certified in the record. For purposes of appellate review, what is not of record does not exist. Pa. R.A.P. 302(a); City of Pittsburgh Commission on Human Relations v. DeFelice, 782 A.2d 586 (Pa.Cmwlth.2001). However, to the extent the procedural claims of Norberry are pure questions of law, we may resolve them. Otte v. Covington Township Road Supervisors, 539 Pa. 44, 650 A.2d 412 (1994). With these principles in mind, we address Norberry’s claim of procedural deficiencies.

First, Norberry argues that the description provided in the Declaration of Taking is inadequate to meet the requirements of Section 402(b) of the Eminent Domain Code (Code), 26 P.S. § 1 — 402(b).4 The caption itself states that the taking is “for a right-of-way for State Route 0079m, Section 290, a limited access highway in the township of Cranberry.” However, Norberry claims the description “in fee simple and a temporary construction easement” does not adequately describe the title, and it further decries DOT’s failure to attach a plan of its Declaration of Taking.

Section 402 of the Code does not require a plan to be attached to the filing of a Declaration of Taking. It requires “[a] description of the property condemned sufficient for the identification thereof ....” 26 P.S. § l-402(b)(5). The schedule of property attached to the declaration identifies the deed book, by volume and page number, where the condemned property is located as well as the pages where a plot plan are recorded in the Recorder’s Office. We cannot agree that this does not describe the property to be condemned.

Free access — add to your briefcase to read the full text and ask questions with AI

Norberry One Condominium Ass'n v. Commonwealth, Department of Transporatation, 805 A.2d 59, 2002 Pa. Commw. LEXIS 757 (Pa. Ct. App. 2002).

805 A.2d 59 (Norberry One Condominium Ass'n v. Commonwealth, Department of Transporatation) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

S.J. Szabo & M.B. Szabo v. DOT
212 A.3d 1168 (Commonwealth Court of Pennsylvania, 2019)
PBS Coals, Inc. and Penn Pocahontas Coal, Co. v. Comwlth of PA, DOT
206 A.3d 1201 (Commonwealth Court of Pennsylvania, 2019)
Szabo, S. v. PennDOT, Aplt.
202 A.3d 52 (Supreme Court of Pennsylvania, 2019)
Com. v. Brown, G.
Superior Court of Pennsylvania, 2018
In Re Condemnation by Com. of Pennsylvania
805 A.2d 59 (Commonwealth Court of Pennsylvania, 2002)